Practice PK0-005 Project Management Concepts questions with full explanations on every answer.
Start practicing
Project Management Concepts — choose a session length
Free · No account required
Click any question to see the full explanation and answer options, or start a focused practice session above.
A project manager is leading a team to develop a new mobile application. The project has a fixed budget and a strict deadline. During the execution phase, the stakeholder requests additional features that were not originally planned. Which project constraint is most directly affected by this request?
2A company is managing multiple projects simultaneously. One project focuses on upgrading the IT infrastructure, another on developing a new customer portal, and a third on training staff on new software. These projects are grouped together because they all contribute to the same strategic goal of digital transformation. According to CompTIA Project+, how is this grouping best described?
3A project manager is assigned to a new initiative in a matrix organization with a weak matrix structure. The project manager needs to obtain resources from functional departments. The functional managers have authority over their team members' assignments and priorities. What is the most likely challenge the project manager will face in this environment?
4An organization is evaluating two potential projects. Project A has an NPV of $50,000 and a payback period of 2 years. Project B has an NPV of $40,000 and a payback period of 1.5 years. The organization's policy is to select projects with the highest NPV. Which project should be selected?
5During project execution, the project team completes a deliverable that exceeds the specified requirements by adding extra features without authorization. This is an example of which concept?
6A project manager is defining the project life cycle for a construction project where requirements are well-defined and unlikely to change. Which project management methodology is most appropriate for this scenario?
7A project manager is assigned to a project in a strong matrix organizational structure. The project manager has significant authority over the project team, and team members report to both the project manager and their functional managers. Which of the following best describes the project manager's level of authority in this structure?
8During project initiation, the project sponsor provides the project manager with a document that authorizes the project and assigns the project manager. This document also outlines high-level scope, budget, and timeline. Which document is this?
9A company wants to select a project based on the time it takes to recover the initial investment. Which project selection method should be used?
10A project is in the planning phase. The project manager is determining the sequence of activities and their dependencies. The team uses a technique that represents activities as nodes and shows the logical flow of the project. Which technique is being used?
11A project manager is using a hybrid methodology. The project has a fixed overall budget and a high-level schedule, but some deliverables are developed iteratively with stakeholder feedback. The team works in two-week sprints for software development, while hardware procurement follows a sequential plan. Which project life cycle is being used?
12A project team is developing a new software product. The product owner frequently changes priorities based on customer feedback. The team needs to adapt quickly and deliver value incrementally. Which project management methodology is most suitable?
13A project manager is reviewing the project constraints. The triple constraint traditionally includes scope, time, and cost. However, quality is also often considered a constraint. Which TWO of the following are part of the triple constraint? (Select TWO).
14During project selection, an organization evaluates multiple projects using financial methods. Which THREE of the following are commonly used financial project selection methods? (Select THREE).
15A project manager is defining the roles and responsibilities for a project. Which TWO of the following are typical responsibilities of the project sponsor? (Select TWO).
16A company is undertaking a one-time initiative to develop a new mobile application with a defined budget, schedule, and scope. Which term best describes this initiative?
17A project manager is leading a team in an organization where team members are assigned to multiple projects and report to both a functional manager and the project manager. The project manager has moderate authority over the team. Which organizational structure does this describe?
18During project execution, a key stakeholder requests additional features that were not originally approved. The project manager is concerned about scope creep. Which type of project constraint is most directly impacted by scope creep?
19A project has been completed, and the project manager is conducting a lessons learned session and archiving project documents. Which project life cycle phase is being performed?
20A software development team uses short, time-boxed iterations, daily stand-up meetings, and a prioritized backlog. Requirements are expected to evolve throughout the project. Which project management methodology is being used?
21A project manager is evaluating two project proposals. Proposal A has an NPV of $50,000 and a payback period of 2 years. Proposal B has an NPV of $30,000 and a payback period of 1.5 years. Which proposal is more financially beneficial based on NPV?
22A project sponsor is responsible for providing resources and championing the project. Which of the following is also a primary responsibility of the project sponsor?
23An organization has multiple projects that are not directly related but are all aimed at achieving the company's strategic goal of expanding into new markets. Which term best describes this collection?
24A project team is adding extra features to a deliverable that were not requested by the customer, in an effort to improve the product. This practice is known as:
25A company is considering a project with an initial investment of $100,000 and expected annual cash inflows of $30,000 for 5 years. The discount rate is 10%. What is the approximate Net Present Value (NPV)? (Present value of annuity factor for 5 years at 10% is 3.791)
26In which type of organizational structure does the project manager have the least authority?
27A project to build a website is expected to take 6 months with a fixed budget. During planning, the team determines that the requirements are well-understood and unlikely to change. Which methodology is most appropriate?
28Which TWO of the following are primary responsibilities of the project manager? (Select two.)
29A project is falling behind schedule. The project manager considers crashing or fast-tracking. Which THREE statements about these techniques are correct? (Select three.)
30Which TWO of the following are examples of gold plating? (Select two.)
31A project manager is assigned to a new software development project. The requirements are well understood and unlikely to change. Which project management methodology is most appropriate for this project?
32In which organizational structure does the project manager have the least authority over project resources?
33During a project, the team adds extra features to a deliverable because they believe it will increase customer satisfaction, even though the features were not specified in the requirements. This is an example of:
34A project manager is evaluating two project proposals. Project A has an initial investment of $100,000 and is expected to generate cash flows of $30,000 per year for 5 years. Project B has an initial investment of $50,000 and cash flows of $20,000 per year for 3 years. Using payback period, which project should be selected?
35A project manager is working in a matrix organization. The project team members report to both the project manager and their functional managers. The project manager has moderate authority and shares resources. This type of matrix is known as:
36Which of the following best describes a program?
37A project sponsor is reviewing a project that has a Net Present Value (NPV) of -$15,000. What should the sponsor recommend?
38Which project life cycle phase involves obtaining formal acceptance of the project deliverables and releasing project resources?
39A project manager is managing a construction project. The scope is well-defined, but the customer is open to minor changes during execution. Which methodology is most suitable?
40During project execution, a key stakeholder requests a new feature that was not in the original scope. The project manager is concerned about the impact on the schedule and budget. This is an example of:
41A project has a cost performance index (CPI) of 0.8 and a schedule performance index (SPI) of 1.1. What does this indicate?
42Who is responsible for providing the project with resources and removing obstacles that are beyond the project manager's control?
43Which TWO of the following are characteristics of a project? (Select TWO).
44A project manager is selecting a project using financial methods. Which THREE of the following are valid project selection methods? (Select THREE).
45Which TWO of the following are examples of project constraints? (Select TWO).
46A project is defined as a temporary endeavor undertaken to create a unique product, service, or result. Which of the following BEST describes a key characteristic of a project?
47A company is initiating a project to develop a new mobile application. The project manager needs to secure approval and funding. Which project role is primarily responsible for providing the necessary resources and championing the project?
48A project manager is leading a software development project in a matrix organization. The project manager shares resources with functional managers. In this type of organizational structure, which of the following BEST describes the project manager's authority?
49A project is in the planning phase and the team is determining the sequence of activities. Which project life cycle phase follows planning?
50A project manager is evaluating two potential projects. Project A has an NPV of $50,000, while Project B has an NPV of -$10,000. Which project should the organization select based solely on NPV?
51A project team is using an agile methodology to develop a new feature. The product owner frequently reprioritizes the backlog based on changing customer needs. Which characteristic of agile does this BEST illustrate?
52During project execution, the project manager notices that the team is adding extra features that were not requested by the customer. This is an example of which common project constraint issue?
53A collection of projects and programs managed together to achieve strategic objectives is known as a:
54A project manager is managing a project in a functional organization. Due to resource constraints, the functional manager often reassigns team members to other tasks. What is the MOST significant challenge the project manager will face?
55A project has a cost performance index (CPI) of 0.8 and a schedule performance index (SPI) of 1.1. What does this indicate about the project's performance?
56A project manager is selecting a methodology for a project with well-understood requirements and low expected change. Which methodology is MOST appropriate?
57Which of the following is NOT a phase in the typical project life cycle?
58A project manager is reviewing the project selection methods for a new initiative. Which TWO of the following are financial project selection methods? (Choose two.)
59A project is being planned in a matrix organization. The project manager needs to identify key roles and their responsibilities. Which THREE of the following are typical project roles? (Choose three.)
60A project is experiencing scope creep. Which TWO of the following are effective ways to manage scope creep? (Choose two.)
61Which of the following best describes a project?
62In which organizational structure does a project manager have the highest level of authority?
63A project manager is leading a software development project with stable requirements and a fixed budget. The team prefers a sequential approach with clear phases. Which methodology is most appropriate?
64A project manager is reviewing project selection methods. Which method calculates the present value of future cash flows minus the initial investment?
65During a project, a stakeholder requests additional features that were not in the original scope. The project manager adds these features without formal change control. This is an example of:
66A project manager is assigned to a project in a matrix organization where the functional managers have significant control over team members. The PM has limited authority. This describes which type of matrix?
67Which project life cycle phase involves obtaining formal acceptance of the project deliverables?
68A project has a budget of $100,000 and a duration of 12 months. After 6 months, the project is 50% complete and has spent $60,000. What is the cost variance?
69Who is typically responsible for providing the project budget and resources, and for resolving issues that are beyond the project manager's authority?
70Which of the following is NOT a typical constraint in the triple constraint of project management?
71A project manager is leading a project in an organization that uses a hybrid methodology. The team follows a predictive approach for requirements gathering and design, but uses iterative sprints for development. Which life cycle best describes this project?
72A project manager is evaluating two potential projects. Project A has an NPV of $50,000, and Project B has an NPV of -$10,000. Which project should be selected based on NPV?
73Which TWO of the following are key characteristics of a project? (Select TWO).
74Which THREE of the following are responsibilities of a project manager? (Select THREE).
75Which TWO of the following are examples of project constraints? (Select TWO).
76Which of the following best defines a project?
77In which organizational structure does the project manager have the least authority?
78A project manager is assigned to a new project with unclear requirements and expects frequent changes. Which project management methodology is most suitable?
79During project execution, a stakeholder requests additional features that were not in the original scope. The project manager identifies this as scope creep. What is the best action for the project manager to take?
80A project has a Net Present Value (NPV) of -$5,000. What does this indicate?
81In which project life cycle phase are project risks identified and a risk management plan created?
82A project sponsor is a key stakeholder. Which of the following is a primary responsibility of the project sponsor?
83Which of the following is an example of gold plating?
84A company is evaluating two projects. Project A has an NPV of $50,000 and a payback period of 3 years. Project B has an NPV of $40,000 and a payback period of 2 years. Which project should be selected based on NPV?
85In a matrix organization, a project manager needs to acquire a team member from a functional department. The functional manager is reluctant to release the resource due to other work. What is the best way for the project manager to address this?
86A project manager is leading a project that uses a hybrid methodology. The project has a fixed deadline but the requirements are expected to evolve. Which approach best describes how the PM should handle the project?
87A steering committee is reviewing project performance. Which of the following is a key responsibility of the steering committee?
88A project manager is selecting a project selection method. Which TWO methods evaluate the profitability of a project? (Choose TWO.)
89Which TWO of the following are characteristics of the planning phase in the project life cycle? (Choose TWO.)
90A project manager is leading a project with a tight budget. The team has completed all required features, but there is some remaining budget. The sponsor suggests adding a few extra features. What are TWO potential issues the project manager should consider before approving? (Choose TWO.)
91Which of the following BEST defines a project?
92A project manager is assigned to a new software development project. The requirements are well understood and unlikely to change. The project team is collocated and has experience with similar projects. Which life cycle approach is MOST appropriate for this project?
93In a matrix organization, a project manager is struggling to get resources assigned to project tasks because the functional managers prioritize operational work. Which type of matrix organization is MOST likely in place?
94A project sponsor is reviewing a proposal for a new project. The expected cash flows are: Year 0: -$100,000; Year 1: $30,000; Year 2: $40,000; Year 3: $50,000. The discount rate is 10%. Which of the following is the Net Present Value (NPV) of the project?
95During project execution, the project manager notices that the development team has been adding extra features that were not requested by the customer. Which of the following describes this behavior?
96Which of the following is a key responsibility of the project sponsor?
97A project to build a new office is in the planning phase. The project manager wants to use a methodology that allows for flexibility in design while still having a clear upfront plan for the overall construction. Which approach is BEST?
98A project manager is evaluating two projects. Project A has an initial investment of $50,000 and expected annual returns of $15,000 for 5 years. Project B has an initial investment of $80,000 and expected annual returns of $22,000 for 5 years. Based on payback period, which project should be selected, and what is the payback period for that project?
99Which project life cycle phase involves formally accepting the project deliverables and releasing resources?
100A project manager is working in an organization where the project team members report to both a functional manager and the project manager. The project manager has moderate authority and shares resource management with functional managers. This is an example of which organizational structure?
101A project has a cost performance index (CPI) of 1.2 and a schedule performance index (SPI) of 0.9. Which of the following statements is TRUE?
102A company is implementing a new HR system. The project manager wants to ensure that all requirements are gathered up front and the scope is fixed. Which project management methodology is MOST appropriate?
103A project manager is planning a marketing campaign for a new product launch. The campaign has a tight budget and strict deadline. During execution, the marketing team proposes adding a social media component that was not in the original scope. The project manager is concerned about scope creep. Which TWO actions should the project manager take to manage this situation?
104A senior manager is comparing two projects for selection. The manager wants to use a method that considers the time value of money. Which TWO project selection methods incorporate the time value of money?
105A project to develop a mobile app is in the executing phase. The project manager uses a Kanban board to track tasks. The team is self-organizing and works in short iterations. The customer is actively involved and provides feedback frequently. Which THREE statements are true about this project?
106A project manager is assigned to a new software development project with clearly defined requirements and minimal expected changes. Which project management methodology is most appropriate for this scenario?
107A project manager works in an organization where team members report to both a functional manager and a project manager. The project manager has moderate authority and shares resource control with the functional manager. Which type of organizational structure does this describe?
108A project manager is evaluating the financial viability of several proposed projects. The steering committee wants to select projects that maximize return over time. Which TWO financial metrics should the project manager use to compare long-term profitability? (Select TWO).
109A project team is developing a new mobile application. During execution, a stakeholder requests additional features that were not in the original scope. The project manager is concerned about scope creep. Which TWO actions should the project manager take to manage this request? (Select TWO).
110A project manager is leading a cross-functional team in a matrix organization. The project is experiencing conflicts between team members due to competing priorities from their functional departments. Which THREE techniques should the project manager use to resolve resource conflicts? (Select THREE).
111A project manager is closing a project that delivered a new customer relationship management system. Which THREE activities are part of the closing process? (Select THREE).
112A project manager is assigned to a program that includes multiple projects aimed at digital transformation. Which TWO statements correctly describe the relationship between projects, programs, and portfolios? (Select TWO).
113A project manager is planning a construction project and identifies that the project has a fixed budget and a strict deadline. The sponsor emphasizes that quality cannot be compromised. Which THREE constraints are directly affected when a change request is approved? (Select THREE).
114A project manager is leading an agile project using Scrum. The product owner frequently changes priorities based on customer feedback. Which TWO roles are directly responsible for managing these changes? (Select TWO).
115A project manager is selecting a project from several proposals. The project with the highest Net Present Value (NPV) also has the longest payback period. Which TWO factors should the project manager consider when recommending this project? (Select TWO).
The Project Management Concepts domain covers the key concepts tested in this area of the PK0-005 exam blueprint published by CompTIA. Courseiva provides free domain-focused practice, mock exams, missed-question review, and readiness tracking across all PK0-005 domains — no account required.
The Courseiva PK0-005 question bank contains 115 questions in the Project Management Concepts domain. Click any question to see the full explanation and answer breakdown.
Start with a 10-question focused session to identify your baseline accuracy in this domain. Read every explanation — even for questions you answer correctly — to understand the reasoning. Once you score consistently above 80%, move to a 20–30 question session to confirm depth before moving to the next domain.
Yes — the session launcher on this page draws questions exclusively from the Project Management Concepts domain. Choose 10, 20, 30, or 50 questions for a focused session, or click individual questions to review them one by one.
Save your results, see per-domain analytics, and get readiness scores — free, for every certification.
Sign Up FreeFree forever · Every certification included