Courseiva
Project Management ConceptshardMultiple SelectObjective-mapped

PK0-005 Project Management Concepts Practice Question

A project is being planned in a matrix organization. The project manager needs to identify key roles and their responsibilities. Which THREE of the following are typical project roles? (Choose three.)

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Project sponsor

The project sponsor, project manager, and project team are key roles. Functional manager is a role in matrix organizations but not a project role per se; it's an organizational role. Stakeholder is anyone with interest, but not a specific role on the project team.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Project sponsor

    Why this is correct

    The sponsor provides resources and support.

  • Functional manager

    Why it's wrong here

    Functional manager is an organizational role, not a project-specific role.

  • Project team

    Why this is correct

    Team members execute tasks.

  • Project manager

    Why this is correct

    The PM leads the project.

  • Stakeholder

    Why it's wrong here

    Stakeholder is a broad category, not a specific role.

About these practice questions

This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.