Courseiva
Project Management ConceptsmediumMultiple SelectObjective-mapped

PK0-005 Project Management Concepts Practice Question

Which TWO of the following are examples of project constraints? (Select TWO).

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Schedule

Scope, cost, and schedule are classic triple constraints. Quality is often added. Risk is not a constraint but an uncertainty.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Schedule

    Why this is correct

    Time is a constraint.

  • Stakeholder satisfaction

    Why it's wrong here

    This is an objective, not a constraint.

  • Team morale

    Why it's wrong here

    Not a formal constraint.

  • Risk

    Why it's wrong here

    Risk is an uncertainty, not a constraint.

  • Scope

    Why this is correct

    Scope defines what is included.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.