Courseiva
Knowledge + Practice
CertificationsVendorsCareer RoadmapsLabs & ToolsStudy GuidesGlossaryPractice Questions
C
Courseiva

Free IT certification practice questions with explained answers for CCNA, CompTIA, AWS, Azure, Google Cloud, and more.

Certification Practice Questions

CCNA practice questionsSecurity+ SY0-701 practice questionsAWS SAA-C03 practice questionsAZ-104 practice questionsAZ-900 practice questionsCLF-C02 practice questionsA+ Core 1 practice questionsGoogle Cloud ACE practice questionsCySA+ CS0-003 practice questionsNetwork+ N10-009 practice questions
View all certifications →

Product

CertificationsCertification PathsExam TopicsPractice TestsExam Dumps vs Practice TestsStudy HubComparisons

Free Resources

Difficulty IndexLearn — Free ChaptersIT GlossaryFree Tools & LabsStudy GuidesCareer RoadmapsBrowse by VendorCisco Command ReferenceCCNA Scenarios

Company

AboutContactEditorial PolicyQuestion Writing PolicyTrust Center

Legal

Privacy PolicyTerms of Service

Courseiva is a free IT certification practice platform offering original exam-style practice questions, detailed explanations, topic-based practice, mock exams, readiness tracking, and study analytics for Cisco, CompTIA, Microsoft, AWS, and other technology certifications.

© 2026 Courseiva. Courseiva is operated by JTNetSolutions Ltd. All rights reserved.

Courseiva is an independent certification practice platform and is not affiliated with, endorsed by, or sponsored by Cisco, Microsoft, AWS, CompTIA, Google, ISC2, ISACA, or any other certification vendor. Vendor names and certification marks are used only to identify the exams learners are preparing for.

HomeCertificationsPK0-005DomainsProject Life Cycle
PK0-005Free — No Signup

Project Life Cycle

Practice PK0-005 Project Life Cycle questions with full explanations on every answer.

165questions

Start practicing

Project Life Cycle — choose a session length

10 questions~10 min20 questions~20 min30 questions~30 min50 questions~50 min

Free · No account required

PK0-005 Domains

Project Management ConceptsProject Life CycleConstraints and ChangesTools and DocumentationProject Life Cycle PhasesBasics of IT Infrastructure and IT Project Management

Practice Project Life Cycle questions

10Q20Q30Q50Q

All PK0-005 Project Life Cycle questions (165)

Start session

Click any question to see the full explanation and answer options, or start a focused practice session above.

1

During which project phase is the project charter typically created and approved?

2

A project manager is developing a network diagram and needs to represent an activity that can start only after its predecessor has finished. Which dependency type does this describe?

3

A project manager is using the power/interest grid to classify stakeholders. Which group should be managed most closely because they have high power and high interest?

4

A project has an Earned Value (EV) of $50,000, Actual Cost (AC) of $60,000, and Planned Value (PV) of $55,000. What is the Cost Performance Index (CPI), and what does it indicate?

5

Which risk response strategy involves taking action to reduce the probability or impact of a risk?

6

A project manager is estimating the cost of a new software development project. She uses the actual cost of a similar past project and adjusts for differences in size and complexity. Which estimation technique is she using?

7

During which stage of Tuckman's team development model do team members begin to resolve conflicts and establish norms?

8

A project manager is calculating the Expected Monetary Value (EMV) for a risk event. The probability of the risk occurring is 20%, and the impact if it occurs is $50,000. What is the EMV?

9

Which document formally authorizes the project and assigns the project manager?

10

A project manager is creating a Work Breakdown Structure (WBS). Which technique is used to break down deliverables into smaller, manageable components?

11

In a project, the critical path has a duration of 100 days. Activity X on the critical path has a duration of 10 days and can be crashed to 7 days at an additional cost of $3,000. What is the crash cost per day for Activity X?

12

A vendor is hired to provide a service with a fixed price of $100,000, regardless of actual costs incurred. Which contract type is this?

13

A project team is entering the Storming stage of Tuckman's model. Which TWO characteristics are typical of this stage?

14

A project manager is planning risk responses for identified risks. Which THREE are valid risk response strategies?

15

During project closing, which TWO activities are typically performed?

16

A project manager is developing the project charter. Which of the following should be included as a key element of the project charter?

17

During project planning, the project manager creates a network diagram. Activity A has a duration of 5 days, Activity B has a duration of 3 days, and Activity C has a duration of 4 days. Activities A and B can start immediately. Activity C can start only after Activity A is complete. Activity B has no dependency on others. What is the duration of the critical path?

18

A project is in the monitoring and controlling phase. The project manager is reviewing the earned value metrics: EV = $50,000, PV = $60,000, AC = $55,000. Which of the following statements is correct?

19

A project team is experiencing conflicts and power struggles among members. According to Tuckman's stages of group development, which stage is the team likely in?

20

A project manager is evaluating risk responses. For a risk with high probability and high impact, which risk response strategy is most appropriate to eliminate the threat?

21

In a power/interest grid, stakeholders with high power and low interest should be managed with which approach?

22

During the executing phase, a vendor delivers a product that does not meet the specifications outlined in the SOW. Which document should the project manager reference first to address this issue?

23

A project manager is estimating costs for a new software development project. The company has completed three similar projects in the past. Which cost estimation technique is most appropriate in this scenario?

24

During project closing, which of the following is the primary purpose of the lessons learned document?

25

A project manager has identified a risk that could cause a $50,000 loss with a 20% probability. What is the Expected Monetary Value (EMV) of this risk?

26

A project has a cost performance index (CPI) of 1.2 and a schedule performance index (SPI) of 0.9. Which of the following is true?

27

Which of the following is a key input to the change control process when a change request is submitted?

28

A project manager is assigning resources to activities. Activity X requires a specialized skill that is only available from a contractor. The project manager decides to hire the contractor. Which TWO documents are most likely to be used to define the work and terms for this contractor? (Select TWO).

29

During project execution, the project manager notices that the team is struggling with communication, and key stakeholders are not receiving timely updates. Which THREE documents should the project manager review to improve the situation? (Select THREE).

30

A project manager is closing a project. Which THREE activities are part of the project closure process? (Select THREE).

31

During which project phase is the project charter created?

32

A project manager is analyzing stakeholders and categorizes a key executive who has high power and high interest. According to the power/interest grid, how should the project manager engage this stakeholder?

33

In a network diagram, Activity A has a duration of 5 days, Activity B has 3 days, and Activity C has 4 days. Activity A and B can start simultaneously, but Activity C cannot start until both A and B are complete. What is the critical path duration?

34

Which cost estimation technique uses historical data from similar projects to estimate the current project?

35

A project team is in the storming stage of Tuckman's model. Which behavior is most likely observed?

36

A project has earned value (EV) of $50,000, planned value (PV) of $60,000, and actual cost (AC) of $55,000. What is the cost performance index (CPI)?

37

A project manager identifies a risk with a probability of 30% and an impact of $50,000. What is the expected monetary value (EMV) of this risk?

38

Which document is used to formally accept the project deliverables and signify project closure?

39

A change request is submitted to add a new feature to a project. What is the first step the project manager should take?

40

Which contract type places the most cost risk on the seller?

41

A project has a budget at completion (BAC) of $200,000, earned value (EV) of $120,000, and actual cost (AC) of $130,000. What is the estimate at completion (EAC) if the cost performance is expected to continue?

42

Which of the following is an example of a risk response strategy to avoid a risk?

43

A project manager is developing a communication plan. Which two elements should be included in the plan? (Select TWO)

44

During project closure, which three activities should be performed? (Select THREE)

45

A project manager is creating a WBS. Which two best practices should be followed? (Select TWO)

46

A project manager is leading a cross-functional team that is working together for the first time. The team members are polite but hesitant to share ideas. According to Tuckman's stages of group development, which stage is the team currently in?

47

During project planning, a project manager is decomposing the project scope into smaller components. Which document is being created, and what is the lowest level of decomposition called?

48

A project manager is reviewing the project schedule. Activity A has an early start (ES) of day 1 and an early finish (EF) of day 5. Activity B has an ES of day 6 and an EF of day 10. Activity C depends on both A and B. What is the total float of Activity B if the project must be completed by day 12?

49

A project manager is estimating the cost of a new software development project. They use historical data from a similar project to derive the cost per function point and multiply it by the expected number of function points. Which estimation technique is being used?

50

A project manager identifies a key stakeholder who has high interest in the project but low power to influence decisions. In the power/interest grid, where should this stakeholder be placed?

51

During project execution, a team member proposes a change that will add a new feature to the product. The project manager documents the change request and analyzes its impact on scope, schedule, and cost. Who is typically responsible for approving or rejecting the change?

52

A project has a cost performance index (CPI) of 1.2 and a schedule performance index (SPI) of 0.8. What does this indicate about the project?

53

In which project management process group is the project charter formally approved, giving the project manager authority to allocate resources?

54

A project manager is preparing a procurement document that asks vendors to provide a price for a specific product. Which type of document is this?

55

A project manager is evaluating a risk with a probability of 30% and an impact of $50,000. What is the expected monetary value (EMV) of this risk?

56

A project has a budget at completion (BAC) of $200,000. The actual cost (AC) is $80,000, earned value (EV) is $60,000, and planned value (PV) is $90,000. What is the estimate at completion (EAC) if the project will continue to perform at the same cost efficiency?

57

Which of the following is the primary purpose of a feasibility study during the initiating phase?

58

A project manager is conducting a lessons learned session at the end of a project. Which TWO activities are typically performed during project closure? (Select two.)

59

A project manager is analyzing the network diagram and identifies that Activity X has a late start (LS) of day 10 and an early start (ES) of day 8. Which TWO statements are true about Activity X? (Select two.)

60

During project planning, the project manager is creating a risk register. Which THREE pieces of information are typically included in a risk register? (Select three.)

61

A project manager is developing the project charter. Which of the following should be included as a key element in the charter to define the project's boundaries?

62

In the stakeholder power/interest grid, stakeholders with high power and low interest should be managed using which strategy?

63

During the planning phase, a project manager is creating the WBS. Which of the following best describes the process of breaking down deliverables into smaller, more manageable components?

64

A project has three activities on the critical path. Activity A has a duration of 5 days, Activity B has a duration of 3 days, and Activity C has a duration of 4 days. What is the total float for any activity on the critical path?

65

Which cost estimation technique uses historical data from similar projects to estimate the cost of the current project?

66

A project manager identifies a risk that could cause a $50,000 loss with a 20% probability. What is the expected monetary value (EMV) of this risk?

67

During the executing phase, a project manager observes that team members are starting to collaborate and share ideas openly. According to Tuckman's stages of team development, which stage is the team likely in?

68

A project manager needs to communicate project progress to stakeholders who have low power and high interest. Which of the following is the most appropriate communication method?

69

A project manager is reviewing the procurement process. Which document is used to invite vendors to submit a proposal for a project?

70

In a fixed-price contract, which party bears the risk of cost overruns?

71

During project execution, a stakeholder requests a change to the project scope. What is the first step the project manager should take?

72

A project has earned value (EV) of $120,000, planned value (PV) of $100,000, and actual cost (AC) of $110,000. What is the cost performance index (CPI)?

73

A project manager is closing a project. Which TWO activities should be performed during project closure? (Select two.)

74

A project manager is performing quantitative risk analysis. Which THREE of the following techniques are commonly used? (Select three.)

75

Which TWO of the following are outputs of the monitoring and controlling process group? (Select two.)

76

During the initiating phase of a project, a project charter is created. Which of the following is typically included in a project charter?

77

A project manager is identifying stakeholders and analyzing their influence on the project. Using a power/interest grid, which group should the project manager 'manage closely'?

78

A project team is decomposing the project scope into work packages. Which of the following best describes the purpose of a Work Breakdown Structure (WBS)?

79

In a network diagram using PDM, activity B can start only after activity A has finished. Which dependency type does this represent?

80

A project has the following activities and dependencies: A (5 days), B (3 days, after A), C (4 days, after A), D (2 days, after B), E (6 days, after C), F (1 day, after D and E). What is the total float of activity C?

81

A project manager is estimating the cost of a new software development project. Since the project is similar to a previous one, the manager uses the cost of the previous project as a basis, adjusting for known differences. Which cost estimation technique is being used?

82

During risk management, a team identifies a risk with a 20% probability of occurrence and a potential cost impact of $50,000. What is the Expected Monetary Value (EMV) of this risk?

83

A project team is in the storming stage of Tuckman's model. Which of the following behaviors is most likely to be observed?

84

A project manager is developing a communication plan. Which of the following should be determined first?

85

During project execution, a vendor is hired to provide specialized services. The contract is structured so that the vendor is paid for all allowable costs plus a fixed fee. Which type of contract is this?

86

A project manager receives a status report showing that the project's SPI is 0.9. What does this indicate?

87

A change request to add a new feature has been submitted. After impact analysis, the change control board (CCB) approves the change. What should the project manager do next?

88

A project manager is closing a project. Which TWO activities are typically performed during the closing phase?

89

During the planning phase, a project team is selecting risk response strategies for identified risks. Which THREE are valid risk response strategies?

90

A project manager is monitoring project performance. Which TWO earned value metrics are used to assess cost efficiency?

91

During which project phase is the project charter created and the project manager officially assigned?

92

A project manager is estimating the cost of a new software development project. The project is similar to a previous project that cost $500,000. The PM adjusts for size and complexity and estimates the new project will cost $600,000. Which estimation technique is being used?

93

In a network diagram, Activity B has a duration of 5 days. Its predecessor is Activity A (duration 3 days) with a finish-to-start relationship. Activity C (duration 4 days) has a start-to-start relationship with Activity B with a 2-day lag. What is the earliest day Activity C can start?

94

A project team is in the storming stage of Tuckman's model. Which behavior is most likely observed?

95

Which document contains all identified risks, their probability and impact, and planned response strategies?

96

A project manager needs to communicate the project's progress to stakeholders with high power and low interest. According to the power/interest grid, which communication approach is most appropriate?

97

A project has an Earned Value (EV) of $50,000, Planned Value (PV) of $60,000, and Actual Cost (AC) of $55,000. What is the cost performance index (CPI) and what does it indicate?

98

A change request to add a new feature is submitted. The project manager performs an impact analysis and presents it to the Change Control Board (CCB). The CCB approves the change. What is the next step?

99

Which contract type places the most cost risk on the seller?

100

A project has three activities on the critical path: A (5 days), B (10 days), C (5 days). Activity D (8 days) has a total float of 3 days. If activity B is delayed by 2 days, what is the new project duration?

101

A project manager is decomposing the project scope into smaller components. Which output is produced?

102

During project closing, which activity is performed to formally obtain acceptance of the project deliverables from the sponsor or customer?

103

A project manager is identifying response strategies for a risk that could impact the project schedule. Which TWO options are risk response strategies? (Select TWO.)

104

A project is in the Executing phase. The project manager needs to ensure effective communication with stakeholders. Which THREE elements should be included in the communications management plan? (Select THREE.)

105

A project has a cost performance index (CPI) of 0.8 and a schedule performance index (SPI) of 1.2. Which TWO conclusions can be drawn? (Select TWO.)

106

A project manager is in the process of developing the project charter. Which of the following would be included in the project charter?

107

During project planning, the project manager decomposes the project scope into smaller, more manageable components. What is the resulting document called?

108

In a precedence diagramming method (PDM) network, a successor activity cannot start until its predecessor activity has started. Which type of dependency does this represent?

109

A project has a critical path duration of 45 days. Activity X on the critical path has an optimistic duration of 5 days, a pessimistic duration of 13 days, and a most likely duration of 8 days. What is the expected duration of activity X using PERT?

110

Which of the following is a common response strategy for negative risks (threats) that involves reducing the probability or impact of the risk?

111

A project manager has identified a stakeholder with high power and high interest. According to the power/interest grid, how should this stakeholder be managed?

112

During project execution, the project team is experiencing conflicts and questioning the project manager's authority. According to Tuckman's model, which stage is the team in?

113

A project manager is estimating costs for a new project using a top-down approach based on historical data from a similar project. Which estimation technique is being used?

114

In earned value management, the project has an EV of $50,000, PV of $60,000, and AC of $55,000. What is the cost variance (CV)?

115

A project manager receives a change request from a stakeholder. What is the first step the project manager should take?

116

A project has a budget at completion (BAC) of $200,000. The earned value (EV) is $120,000, and the actual cost (AC) is $150,000. What is the estimate to complete (ETC) assuming the project will continue to perform at the same cost efficiency?

117

Which type of contract places the greatest cost risk on the seller?

118

Which TWO documents are typically created during the project initiating phase?

119

During project closing, which THREE activities should be performed?

120

A project manager is evaluating the cost performance of a project. Which TWO earned value metrics should be used to determine if the project is over budget?

121

During which project phase is the project charter created and the project manager formally assigned?

122

A project manager is developing a network diagram for a software rollout. Activity D (3 days) can start only after Activity C (2 days) finishes, and Activity E (4 days) can start when Activity C starts. Activities D and E must both finish before Activity F (1 day) begins. What type of dependency exists between Activity C and Activity E?

123

A project has an Earned Value (EV) of $50,000, Planned Value (PV) of $60,000, and Actual Cost (AC) of $55,000. Which TWO statements are true regarding the project's performance? (Choose two.)

124

A project manager is assigning stakeholders to quadrants on a power/interest grid. Which stakeholders require the most active management?

125

Which document formally authorizes a project and provides the project manager with the authority to apply organizational resources?

126

A project team is estimating costs for a new software development project. They use data from a similar previous project and adjust for size differences. Which estimating technique is being used?

127

During project execution, a team member identifies a potential risk that was not included in the risk register. The project manager logs it and begins the risk assessment process. Where should this risk be recorded?

128

A project manager is using a risk probability and impact matrix. A risk has a probability of 0.3 and an impact of $50,000. What is the expected monetary value (EMV) of this risk?

129

In which Tuckman stage do team members begin to resolve their differences, establish norms, and develop closer relationships?

130

A project team is in the process of obtaining seller responses, evaluating proposals, and awarding a contract. Which procurement document is used to formally request a proposal from potential sellers?

131

A project has a cost performance index (CPI) of 1.2 and a schedule performance index (SPI) of 0.9. Which of the following is true?

132

During project closing, which activity involves obtaining formal acceptance from the customer or sponsor that deliverables meet requirements?

133

A project manager is analyzing the critical path of a network diagram. Which TWO statements about the critical path are true?

134

A project manager is updating the risk register and plans to respond to a high-priority risk. Which THREE are valid risk response strategies?

135

A project manager is creating a project schedule. Which THREE items are typically included in a schedule baseline?

136

During which phase of the project life cycle is the project charter created and stakeholders initially identified?

137

What is the primary purpose of a Work Breakdown Structure (WBS) in project planning?

138

Which project management process group involves obtaining formal acceptance of the project deliverables and archiving project documents?

139

A project manager is estimating the cost of a software development project. Using data from a similar past project, she adjusts for size and complexity. Which estimation technique is she using?

140

In a network diagram, if Activity B cannot start until Activity A is complete, what type of dependency is this?

141

A project has an EV of $40,000, PV of $50,000, and AC of $45,000. What is the cost performance index (CPI)?

142

A project manager identifies a risk that a key team member might leave during the project. To reduce the impact, she cross-trains other team members. Which risk response strategy is being applied?

143

According to Tuckman's model, during which stage do team members begin to resolve conflicts and establish norms?

144

A project manager uses a power/interest grid to categorize stakeholders. Stakeholders with high power and low interest should be managed using which approach?

145

During project execution, a team member proposes a change that will affect the scope baseline. What is the first step the project manager should take?

146

A project has a budget at completion (BAC) of $200,000. The earned value (EV) is $100,000, actual cost (AC) is $120,000, and planned value (PV) is $90,000. What is the estimate at completion (EAC) if the project will continue to perform at the current cost performance index (CPI)?

147

A project manager is calculating the critical path. The network diagram shows two paths: Path A: A(3 days) → B(4 days) → C(2 days) = 9 days; Path B: D(5 days) → E(1 day) → F(3 days) = 9 days. Both have total float of zero. What is the total float for an activity on Path A?

148

A project has a CPI of 0.9 and an SPI of 1.1. Which two statements are true? (Select TWO.)

149

During the planning phase, which three documents are typically created? (Select THREE.)

150

A project manager is developing a communication plan. Which two factors should be considered for each stakeholder? (Select TWO.)

151

A project manager is creating a document that formally authorizes the project and assigns the project manager. This document includes the business case, high-level scope, and budget constraints. What is this document called?

152

During project planning, the team creates a hierarchical decomposition of the total scope of work to be carried out by the project team. Each descending level represents an increasingly detailed definition of the project work. What is this called?

153

A project has three activities: Activity A (5 days), Activity B (7 days), Activity C (4 days). Activity B depends on A. Activity C depends on B. What is the total float for Activity B?

154

A project manager is estimating the cost of a software development project. She uses the actual cost of a similar past project and adjusts it for known differences in size and complexity. Which cost estimation technique is she using?

155

A project team is in the Performing stage of Tuckman's model. Which TWO behaviors are characteristic of this stage?

156

A project manager is identifying stakeholders for a new product launch. She uses a power/interest grid to categorize stakeholders. For which TWO quadrants should the project manager apply the strategy of 'Manage Closely'?

157

During project executing, the team is developing a communication plan. Which THREE factors should the project manager consider when determining the communication needs of stakeholders?

158

A project manager is reviewing the risk register and notices a risk with a high probability (0.7) and high impact ($50,000). The team decides to purchase insurance to cover the potential loss. Which TWO risk response strategies are being applied?

159

A project manager is calculating the cost performance index (CPI) for a project. The earned value (EV) is $50,000 and the actual cost (AC) is $60,000. What does the CPI indicate? (Select TWO correct statements.)

160

A project is in the Monitoring and Controlling phase. A change request has been submitted to add a new feature. The change control board (CCB) has approved the change. Which THREE actions should the project manager take next?

161

During project closing, a project manager must complete several activities. Which TWO are appropriate for project closure?

162

A project manager is estimating activity durations for a construction project. She uses a parametric estimate based on 100 square meters per day. If the total area is 500 square meters, the estimated duration is 5 days. Which THREE statements are true about parametric estimation?

163

A project manager is analyzing the network diagram for a project. The critical path is A-B-C, with durations 3, 4, 2 days respectively. Activity D (2 days) has a finish-to-start relationship with A and a start-to-start relationship with B. Which TWO statements are correct about the schedule?

164

A project manager is preparing a request for proposal (RFP) for a vendor to provide specialized equipment. Which THREE items should be included in the RFP?

165

A project has a budget at completion (BAC) of $200,000. After two months, the earned value (EV) is $80,000 and the actual cost (AC) is $90,000. The CPI is 0.89. Which THREE statements are correct regarding cost performance and forecasting?

Practice all 165 Project Life Cycle questions

Other PK0-005 exam domains

Project Management ConceptsConstraints and ChangesTools and DocumentationProject Life Cycle PhasesBasics of IT Infrastructure and IT Project Management

Frequently asked questions

What does the Project Life Cycle domain cover on the PK0-005 exam?

The Project Life Cycle domain covers the key concepts tested in this area of the PK0-005 exam blueprint published by CompTIA. Courseiva provides free domain-focused practice, mock exams, missed-question review, and readiness tracking across all PK0-005 domains — no account required.

How many Project Life Cycle questions are in the PK0-005 question bank?

The Courseiva PK0-005 question bank contains 165 questions in the Project Life Cycle domain. Click any question to see the full explanation and answer breakdown.

What is the best way to practice Project Life Cycle for PK0-005?

Start with a 10-question focused session to identify your baseline accuracy in this domain. Read every explanation — even for questions you answer correctly — to understand the reasoning. Once you score consistently above 80%, move to a 20–30 question session to confirm depth before moving to the next domain.

Can I practice only Project Life Cycle questions for PK0-005?

Yes — the session launcher on this page draws questions exclusively from the Project Life Cycle domain. Choose 10, 20, 30, or 50 questions for a focused session, or click individual questions to review them one by one.

Free forever · No credit card required

Track your PK0-005 domain progress

Save your results, see per-domain analytics, and get readiness scores — free, for every certification.

Sign Up Free

Free forever · Every certification included

Practice Session

10 questions20 questions30 questions50 questions

Study Resources

All DomainsPractice TestMock ExamFlashcardsStudy Guide