During which project phase is the project charter typically created and approved?
2A project manager is developing a network diagram and needs to represent an activity that can start only after its predecessor has finished. Which dependency type does this describe?
3A project manager is using the power/interest grid to classify stakeholders. Which group should be managed most closely because they have high power and high interest?
4A project has an Earned Value (EV) of $50,000, Actual Cost (AC) of $60,000, and Planned Value (PV) of $55,000. What is the Cost Performance Index (CPI), and what does it indicate?
5Which risk response strategy involves taking action to reduce the probability or impact of a risk?
6A project manager is estimating the cost of a new software development project. She uses the actual cost of a similar past project and adjusts for differences in size and complexity. Which estimation technique is she using?
7During which stage of Tuckman's team development model do team members begin to resolve conflicts and establish norms?
8A project manager is calculating the Expected Monetary Value (EMV) for a risk event. The probability of the risk occurring is 20%, and the impact if it occurs is $50,000. What is the EMV?
9Which document formally authorizes the project and assigns the project manager?
10A project manager is creating a Work Breakdown Structure (WBS). Which technique is used to break down deliverables into smaller, manageable components?
11In a project, the critical path has a duration of 100 days. Activity X on the critical path has a duration of 10 days and can be crashed to 7 days at an additional cost of $3,000. What is the crash cost per day for Activity X?
12A vendor is hired to provide a service with a fixed price of $100,000, regardless of actual costs incurred. Which contract type is this?
13A project team is entering the Storming stage of Tuckman's model. Which TWO characteristics are typical of this stage?
14A project manager is planning risk responses for identified risks. Which THREE are valid risk response strategies?
15During project closing, which TWO activities are typically performed?
16A project manager is developing the project charter. Which of the following should be included as a key element of the project charter?
17During project planning, the project manager creates a network diagram. Activity A has a duration of 5 days, Activity B has a duration of 3 days, and Activity C has a duration of 4 days. Activities A and B can start immediately. Activity C can start only after Activity A is complete. Activity B has no dependency on others. What is the duration of the critical path?
18A project is in the monitoring and controlling phase. The project manager is reviewing the earned value metrics: EV = $50,000, PV = $60,000, AC = $55,000. Which of the following statements is correct?
19A project team is experiencing conflicts and power struggles among members. According to Tuckman's stages of group development, which stage is the team likely in?
20A project manager is evaluating risk responses. For a risk with high probability and high impact, which risk response strategy is most appropriate to eliminate the threat?
21In a power/interest grid, stakeholders with high power and low interest should be managed with which approach?
22During the executing phase, a vendor delivers a product that does not meet the specifications outlined in the SOW. Which document should the project manager reference first to address this issue?
23A project manager is estimating costs for a new software development project. The company has completed three similar projects in the past. Which cost estimation technique is most appropriate in this scenario?
24During project closing, which of the following is the primary purpose of the lessons learned document?
25A project manager has identified a risk that could cause a $50,000 loss with a 20% probability. What is the Expected Monetary Value (EMV) of this risk?
26A project has a cost performance index (CPI) of 1.2 and a schedule performance index (SPI) of 0.9. Which of the following is true?
27Which of the following is a key input to the change control process when a change request is submitted?
28A project manager is assigning resources to activities. Activity X requires a specialized skill that is only available from a contractor. The project manager decides to hire the contractor. Which TWO documents are most likely to be used to define the work and terms for this contractor? (Select TWO).
29During project execution, the project manager notices that the team is struggling with communication, and key stakeholders are not receiving timely updates. Which THREE documents should the project manager review to improve the situation? (Select THREE).
30A project manager is closing a project. Which THREE activities are part of the project closure process? (Select THREE).
31During which project phase is the project charter created?
32A project manager is analyzing stakeholders and categorizes a key executive who has high power and high interest. According to the power/interest grid, how should the project manager engage this stakeholder?
33In a network diagram, Activity A has a duration of 5 days, Activity B has 3 days, and Activity C has 4 days. Activity A and B can start simultaneously, but Activity C cannot start until both A and B are complete. What is the critical path duration?
34Which cost estimation technique uses historical data from similar projects to estimate the current project?
35A project team is in the storming stage of Tuckman's model. Which behavior is most likely observed?
36A project has earned value (EV) of $50,000, planned value (PV) of $60,000, and actual cost (AC) of $55,000. What is the cost performance index (CPI)?
37A project manager identifies a risk with a probability of 30% and an impact of $50,000. What is the expected monetary value (EMV) of this risk?
38Which document is used to formally accept the project deliverables and signify project closure?
39A change request is submitted to add a new feature to a project. What is the first step the project manager should take?
40Which contract type places the most cost risk on the seller?
41A project has a budget at completion (BAC) of $200,000, earned value (EV) of $120,000, and actual cost (AC) of $130,000. What is the estimate at completion (EAC) if the cost performance is expected to continue?
42Which of the following is an example of a risk response strategy to avoid a risk?
43A project manager is developing a communication plan. Which two elements should be included in the plan? (Select TWO)
44During project closure, which three activities should be performed? (Select THREE)
45A project manager is creating a WBS. Which two best practices should be followed? (Select TWO)
46A project manager is leading a cross-functional team that is working together for the first time. The team members are polite but hesitant to share ideas. According to Tuckman's stages of group development, which stage is the team currently in?
47During project planning, a project manager is decomposing the project scope into smaller components. Which document is being created, and what is the lowest level of decomposition called?
48A project manager is reviewing the project schedule. Activity A has an early start (ES) of day 1 and an early finish (EF) of day 5. Activity B has an ES of day 6 and an EF of day 10. Activity C depends on both A and B. What is the total float of Activity B if the project must be completed by day 12?
49A project manager is estimating the cost of a new software development project. They use historical data from a similar project to derive the cost per function point and multiply it by the expected number of function points. Which estimation technique is being used?
50A project manager identifies a key stakeholder who has high interest in the project but low power to influence decisions. In the power/interest grid, where should this stakeholder be placed?
51During project execution, a team member proposes a change that will add a new feature to the product. The project manager documents the change request and analyzes its impact on scope, schedule, and cost. Who is typically responsible for approving or rejecting the change?
52A project has a cost performance index (CPI) of 1.2 and a schedule performance index (SPI) of 0.8. What does this indicate about the project?
53In which project management process group is the project charter formally approved, giving the project manager authority to allocate resources?
54A project manager is preparing a procurement document that asks vendors to provide a price for a specific product. Which type of document is this?
55A project manager is evaluating a risk with a probability of 30% and an impact of $50,000. What is the expected monetary value (EMV) of this risk?
56A project has a budget at completion (BAC) of $200,000. The actual cost (AC) is $80,000, earned value (EV) is $60,000, and planned value (PV) is $90,000. What is the estimate at completion (EAC) if the project will continue to perform at the same cost efficiency?
57Which of the following is the primary purpose of a feasibility study during the initiating phase?
58A project manager is conducting a lessons learned session at the end of a project. Which TWO activities are typically performed during project closure? (Select two.)
59A project manager is analyzing the network diagram and identifies that Activity X has a late start (LS) of day 10 and an early start (ES) of day 8. Which TWO statements are true about Activity X? (Select two.)
60During project planning, the project manager is creating a risk register. Which THREE pieces of information are typically included in a risk register? (Select three.)
61A project manager is developing the project charter. Which of the following should be included as a key element in the charter to define the project's boundaries?
62In the stakeholder power/interest grid, stakeholders with high power and low interest should be managed using which strategy?
63During the planning phase, a project manager is creating the WBS. Which of the following best describes the process of breaking down deliverables into smaller, more manageable components?
64A project has three activities on the critical path. Activity A has a duration of 5 days, Activity B has a duration of 3 days, and Activity C has a duration of 4 days. What is the total float for any activity on the critical path?
65Which cost estimation technique uses historical data from similar projects to estimate the cost of the current project?
66A project manager identifies a risk that could cause a $50,000 loss with a 20% probability. What is the expected monetary value (EMV) of this risk?
67During the executing phase, a project manager observes that team members are starting to collaborate and share ideas openly. According to Tuckman's stages of team development, which stage is the team likely in?
68A project manager needs to communicate project progress to stakeholders who have low power and high interest. Which of the following is the most appropriate communication method?
69A project manager is reviewing the procurement process. Which document is used to invite vendors to submit a proposal for a project?
70In a fixed-price contract, which party bears the risk of cost overruns?
71During project execution, a stakeholder requests a change to the project scope. What is the first step the project manager should take?
72A project has earned value (EV) of $120,000, planned value (PV) of $100,000, and actual cost (AC) of $110,000. What is the cost performance index (CPI)?
73A project manager is closing a project. Which TWO activities should be performed during project closure? (Select two.)
74A project manager is performing quantitative risk analysis. Which THREE of the following techniques are commonly used? (Select three.)
75Which TWO of the following are outputs of the monitoring and controlling process group? (Select two.)
76During the initiating phase of a project, a project charter is created. Which of the following is typically included in a project charter?
77A project manager is identifying stakeholders and analyzing their influence on the project. Using a power/interest grid, which group should the project manager 'manage closely'?
78A project team is decomposing the project scope into work packages. Which of the following best describes the purpose of a Work Breakdown Structure (WBS)?
79In a network diagram using PDM, activity B can start only after activity A has finished. Which dependency type does this represent?
80A project has the following activities and dependencies: A (5 days), B (3 days, after A), C (4 days, after A), D (2 days, after B), E (6 days, after C), F (1 day, after D and E). What is the total float of activity C?
81A project manager is estimating the cost of a new software development project. Since the project is similar to a previous one, the manager uses the cost of the previous project as a basis, adjusting for known differences. Which cost estimation technique is being used?
82During risk management, a team identifies a risk with a 20% probability of occurrence and a potential cost impact of $50,000. What is the Expected Monetary Value (EMV) of this risk?
83A project team is in the storming stage of Tuckman's model. Which of the following behaviors is most likely to be observed?
84A project manager is developing a communication plan. Which of the following should be determined first?
85During project execution, a vendor is hired to provide specialized services. The contract is structured so that the vendor is paid for all allowable costs plus a fixed fee. Which type of contract is this?
86A project manager receives a status report showing that the project's SPI is 0.9. What does this indicate?
87A change request to add a new feature has been submitted. After impact analysis, the change control board (CCB) approves the change. What should the project manager do next?
88A project manager is closing a project. Which TWO activities are typically performed during the closing phase?
89During the planning phase, a project team is selecting risk response strategies for identified risks. Which THREE are valid risk response strategies?
90A project manager is monitoring project performance. Which TWO earned value metrics are used to assess cost efficiency?
91During which project phase is the project charter created and the project manager officially assigned?
92A project manager is estimating the cost of a new software development project. The project is similar to a previous project that cost $500,000. The PM adjusts for size and complexity and estimates the new project will cost $600,000. Which estimation technique is being used?
93In a network diagram, Activity B has a duration of 5 days. Its predecessor is Activity A (duration 3 days) with a finish-to-start relationship. Activity C (duration 4 days) has a start-to-start relationship with Activity B with a 2-day lag. What is the earliest day Activity C can start?
94A project team is in the storming stage of Tuckman's model. Which behavior is most likely observed?
95Which document contains all identified risks, their probability and impact, and planned response strategies?
96A project manager needs to communicate the project's progress to stakeholders with high power and low interest. According to the power/interest grid, which communication approach is most appropriate?
97A project has an Earned Value (EV) of $50,000, Planned Value (PV) of $60,000, and Actual Cost (AC) of $55,000. What is the cost performance index (CPI) and what does it indicate?
98A change request to add a new feature is submitted. The project manager performs an impact analysis and presents it to the Change Control Board (CCB). The CCB approves the change. What is the next step?
99Which contract type places the most cost risk on the seller?
100A project has three activities on the critical path: A (5 days), B (10 days), C (5 days). Activity D (8 days) has a total float of 3 days. If activity B is delayed by 2 days, what is the new project duration?
101A project manager is decomposing the project scope into smaller components. Which output is produced?
102During project closing, which activity is performed to formally obtain acceptance of the project deliverables from the sponsor or customer?
103A project manager is identifying response strategies for a risk that could impact the project schedule. Which TWO options are risk response strategies? (Select TWO.)
104A project is in the Executing phase. The project manager needs to ensure effective communication with stakeholders. Which THREE elements should be included in the communications management plan? (Select THREE.)
105A project has a cost performance index (CPI) of 0.8 and a schedule performance index (SPI) of 1.2. Which TWO conclusions can be drawn? (Select TWO.)
106A project manager is in the process of developing the project charter. Which of the following would be included in the project charter?
107During project planning, the project manager decomposes the project scope into smaller, more manageable components. What is the resulting document called?
108In a precedence diagramming method (PDM) network, a successor activity cannot start until its predecessor activity has started. Which type of dependency does this represent?
109A project has a critical path duration of 45 days. Activity X on the critical path has an optimistic duration of 5 days, a pessimistic duration of 13 days, and a most likely duration of 8 days. What is the expected duration of activity X using PERT?
110Which of the following is a common response strategy for negative risks (threats) that involves reducing the probability or impact of the risk?
111A project manager has identified a stakeholder with high power and high interest. According to the power/interest grid, how should this stakeholder be managed?
112During project execution, the project team is experiencing conflicts and questioning the project manager's authority. According to Tuckman's model, which stage is the team in?
113A project manager is estimating costs for a new project using a top-down approach based on historical data from a similar project. Which estimation technique is being used?
114In earned value management, the project has an EV of $50,000, PV of $60,000, and AC of $55,000. What is the cost variance (CV)?
115A project manager receives a change request from a stakeholder. What is the first step the project manager should take?
116A project has a budget at completion (BAC) of $200,000. The earned value (EV) is $120,000, and the actual cost (AC) is $150,000. What is the estimate to complete (ETC) assuming the project will continue to perform at the same cost efficiency?
117Which type of contract places the greatest cost risk on the seller?
118Which TWO documents are typically created during the project initiating phase?
119During project closing, which THREE activities should be performed?
120A project manager is evaluating the cost performance of a project. Which TWO earned value metrics should be used to determine if the project is over budget?
121During which project phase is the project charter created and the project manager formally assigned?
122A project manager is developing a network diagram for a software rollout. Activity D (3 days) can start only after Activity C (2 days) finishes, and Activity E (4 days) can start when Activity C starts. Activities D and E must both finish before Activity F (1 day) begins. What type of dependency exists between Activity C and Activity E?
123A project has an Earned Value (EV) of $50,000, Planned Value (PV) of $60,000, and Actual Cost (AC) of $55,000. Which TWO statements are true regarding the project's performance? (Choose two.)
124A project manager is assigning stakeholders to quadrants on a power/interest grid. Which stakeholders require the most active management?
125Which document formally authorizes a project and provides the project manager with the authority to apply organizational resources?
126A project team is estimating costs for a new software development project. They use data from a similar previous project and adjust for size differences. Which estimating technique is being used?
127During project execution, a team member identifies a potential risk that was not included in the risk register. The project manager logs it and begins the risk assessment process. Where should this risk be recorded?
128A project manager is using a risk probability and impact matrix. A risk has a probability of 0.3 and an impact of $50,000. What is the expected monetary value (EMV) of this risk?
129In which Tuckman stage do team members begin to resolve their differences, establish norms, and develop closer relationships?
130A project team is in the process of obtaining seller responses, evaluating proposals, and awarding a contract. Which procurement document is used to formally request a proposal from potential sellers?
131A project has a cost performance index (CPI) of 1.2 and a schedule performance index (SPI) of 0.9. Which of the following is true?
132During project closing, which activity involves obtaining formal acceptance from the customer or sponsor that deliverables meet requirements?
133A project manager is analyzing the critical path of a network diagram. Which TWO statements about the critical path are true?
134A project manager is updating the risk register and plans to respond to a high-priority risk. Which THREE are valid risk response strategies?
135A project manager is creating a project schedule. Which THREE items are typically included in a schedule baseline?
136During which phase of the project life cycle is the project charter created and stakeholders initially identified?
137What is the primary purpose of a Work Breakdown Structure (WBS) in project planning?
138Which project management process group involves obtaining formal acceptance of the project deliverables and archiving project documents?
139A project manager is estimating the cost of a software development project. Using data from a similar past project, she adjusts for size and complexity. Which estimation technique is she using?
140In a network diagram, if Activity B cannot start until Activity A is complete, what type of dependency is this?
141A project has an EV of $40,000, PV of $50,000, and AC of $45,000. What is the cost performance index (CPI)?
142A project manager identifies a risk that a key team member might leave during the project. To reduce the impact, she cross-trains other team members. Which risk response strategy is being applied?
143According to Tuckman's model, during which stage do team members begin to resolve conflicts and establish norms?
144A project manager uses a power/interest grid to categorize stakeholders. Stakeholders with high power and low interest should be managed using which approach?
145During project execution, a team member proposes a change that will affect the scope baseline. What is the first step the project manager should take?
146A project has a budget at completion (BAC) of $200,000. The earned value (EV) is $100,000, actual cost (AC) is $120,000, and planned value (PV) is $90,000. What is the estimate at completion (EAC) if the project will continue to perform at the current cost performance index (CPI)?
147A project manager is calculating the critical path. The network diagram shows two paths: Path A: A(3 days) → B(4 days) → C(2 days) = 9 days; Path B: D(5 days) → E(1 day) → F(3 days) = 9 days. Both have total float of zero. What is the total float for an activity on Path A?
148A project has a CPI of 0.9 and an SPI of 1.1. Which two statements are true? (Select TWO.)
149During the planning phase, which three documents are typically created? (Select THREE.)
150A project manager is developing a communication plan. Which two factors should be considered for each stakeholder? (Select TWO.)
151A project manager is creating a document that formally authorizes the project and assigns the project manager. This document includes the business case, high-level scope, and budget constraints. What is this document called?
152During project planning, the team creates a hierarchical decomposition of the total scope of work to be carried out by the project team. Each descending level represents an increasingly detailed definition of the project work. What is this called?
153A project has three activities: Activity A (5 days), Activity B (7 days), Activity C (4 days). Activity B depends on A. Activity C depends on B. What is the total float for Activity B?
154A project manager is estimating the cost of a software development project. She uses the actual cost of a similar past project and adjusts it for known differences in size and complexity. Which cost estimation technique is she using?
155A project team is in the Performing stage of Tuckman's model. Which TWO behaviors are characteristic of this stage?
156A project manager is identifying stakeholders for a new product launch. She uses a power/interest grid to categorize stakeholders. For which TWO quadrants should the project manager apply the strategy of 'Manage Closely'?
157During project executing, the team is developing a communication plan. Which THREE factors should the project manager consider when determining the communication needs of stakeholders?
158A project manager is reviewing the risk register and notices a risk with a high probability (0.7) and high impact ($50,000). The team decides to purchase insurance to cover the potential loss. Which TWO risk response strategies are being applied?
159A project manager is calculating the cost performance index (CPI) for a project. The earned value (EV) is $50,000 and the actual cost (AC) is $60,000. What does the CPI indicate? (Select TWO correct statements.)
160A project is in the Monitoring and Controlling phase. A change request has been submitted to add a new feature. The change control board (CCB) has approved the change. Which THREE actions should the project manager take next?
161During project closing, a project manager must complete several activities. Which TWO are appropriate for project closure?
162A project manager is estimating activity durations for a construction project. She uses a parametric estimate based on 100 square meters per day. If the total area is 500 square meters, the estimated duration is 5 days. Which THREE statements are true about parametric estimation?
163A project manager is analyzing the network diagram for a project. The critical path is A-B-C, with durations 3, 4, 2 days respectively. Activity D (2 days) has a finish-to-start relationship with A and a start-to-start relationship with B. Which TWO statements are correct about the schedule?
164A project manager is preparing a request for proposal (RFP) for a vendor to provide specialized equipment. Which THREE items should be included in the RFP?
165A project has a budget at completion (BAC) of $200,000. After two months, the earned value (EV) is $80,000 and the actual cost (AC) is $90,000. The CPI is 0.89. Which THREE statements are correct regarding cost performance and forecasting?
The Project Life Cycle domain covers the key concepts tested in this area of the PK0-005 exam blueprint published by CompTIA. Courseiva provides free domain-focused practice, mock exams, missed-question review, and readiness tracking across all PK0-005 domains — no account required.
The Courseiva PK0-005 question bank contains 165 questions in the Project Life Cycle domain. Click any question to see the full explanation and answer breakdown.
Start with a 10-question focused session to identify your baseline accuracy in this domain. Read every explanation — even for questions you answer correctly — to understand the reasoning. Once you score consistently above 80%, move to a 20–30 question session to confirm depth before moving to the next domain.
Yes — the session launcher on this page draws questions exclusively from the Project Life Cycle domain. Choose 10, 20, 30, or 50 questions for a focused session, or click individual questions to review them one by one.
Save your results, see per-domain analytics, and get readiness scores — free, for every certification.
Sign Up FreeFree forever · Every certification included