Courseiva
Knowledge + Practice
CertificationsVendorsCareer RoadmapsLabs & ToolsStudy GuidesGlossaryPractice Questions
C
Courseiva

Free IT certification practice questions with explained answers for CCNA, CompTIA, AWS, Azure, Google Cloud, and more.

Certification Practice Questions

CCNA practice questionsSecurity+ SY0-701 practice questionsAWS SAA-C03 practice questionsAZ-104 practice questionsAZ-900 practice questionsCLF-C02 practice questionsA+ Core 1 practice questionsGoogle Cloud ACE practice questionsCySA+ CS0-003 practice questionsNetwork+ N10-009 practice questions
View all certifications →

Product

CertificationsCertification PathsExam TopicsPractice TestsExam Dumps vs Practice TestsStudy HubComparisons

Free Resources

Difficulty IndexLearn — Free ChaptersIT GlossaryFree Tools & LabsStudy GuidesCareer RoadmapsBrowse by VendorCisco Command ReferenceCCNA Scenarios

Company

AboutContactEditorial PolicyQuestion Writing PolicyTrust Center

Legal

Privacy PolicyTerms of Service

Courseiva is a free IT certification practice platform offering original exam-style practice questions, detailed explanations, topic-based practice, mock exams, readiness tracking, and study analytics for Cisco, CompTIA, Microsoft, AWS, and other technology certifications.

© 2026 Courseiva. Courseiva is operated by JTNetSolutions Ltd. All rights reserved.

Courseiva is an independent certification practice platform and is not affiliated with, endorsed by, or sponsored by Cisco, Microsoft, AWS, CompTIA, Google, ISC2, ISACA, or any other certification vendor. Vendor names and certification marks are used only to identify the exams learners are preparing for.

HomeCertificationsPK0-005DomainsTools and Documentation
PK0-005Free — No Signup

Tools and Documentation

Practice PK0-005 Tools and Documentation questions with full explanations on every answer.

125questions

Start practicing

Tools and Documentation — choose a session length

10 questions~10 min20 questions~20 min30 questions~30 min50 questions~50 min

Free · No account required

PK0-005 Domains

Project Management ConceptsProject Life CycleConstraints and ChangesTools and DocumentationProject Life Cycle PhasesBasics of IT Infrastructure and IT Project Management

Practice Tools and Documentation questions

10Q20Q30Q50Q

All PK0-005 Tools and Documentation questions (125)

Start session

Click any question to see the full explanation and answer options, or start a focused practice session above.

1

A project manager wants to visualize the sequence of project activities and their dependencies to identify the critical path. Which tool should be used?

2

During a sprint review, the product owner notices that the team completed 30 story points in the previous sprint and 25 in the current sprint. The project manager wants to track the average story points completed per sprint to predict future performance. Which metric should be used?

3

A project has a budget at completion (BAC) of $200,000. The earned value (EV) is $90,000, and the actual cost (AC) is $100,000. What is the estimate at completion (EAC) if the project is expected to continue at the same cost performance?

4

Which document formally authorizes a project and provides the project manager with the authority to apply organizational resources?

5

A project manager notices that a task is taking longer than planned and the project is falling behind schedule. The project manager wants to identify the root cause of the delay. Which quality tool would be most appropriate?

6

In an agile project, the team is using user stories to capture requirements. Which of the following is the correct format for a user story?

7

Which document is used to track and manage changes to the project baseline?

8

A project manager is using earned value management. The project has a schedule variance (SV) of -$5,000. What does this indicate?

9

A project manager creates a visual representation that shows the 20% of causes contributing to 80% of the problems in a project. Which tool is being used?

10

In an agile project using Jira, the team creates a board that visualizes the workflow with columns such as 'To Do', 'In Progress', and 'Done'. Which type of board is this?

11

Which document defines the communication requirements, including who needs what information, when, and how?

12

A project has a cost performance index (CPI) of 1.2 and a schedule performance index (SPI) of 0.9. Which of the following best describes the project's status?

13

A project manager is creating the project management plan. Which TWO subsidiary plans should be included? (Select TWO.)

14

Which THREE of the following are key elements of a user story? (Select THREE.)

15

A project manager is analyzing quality issues and wants to use tools that help identify and prioritize problems. Which TWO tools are appropriate for this purpose? (Select TWO.)

16

A project manager is tracking the completion of key deliverables against the project schedule. Which tool should they use to display only major milestones without showing detailed dependencies or tasks?

17

During a sprint planning meeting, the development team estimates user stories using story points. They each have a set of cards with values like 1, 2, 3, 5, 8, 13. After discussing a story, all team members simultaneously reveal their chosen card. What technique are they using?

18

A project has a budget at completion (BAC) of $200,000. After five months, the earned value (EV) is $90,000 and the actual cost (AC) is $100,000. The project manager needs to calculate the estimate at completion (EAC) assuming current cost performance will continue. What is the EAC?

19

In a RACI matrix, the person who is ultimately accountable for the completion of a task is denoted by which letter?

20

A project manager is using a quality tool that displays data points over time with upper and lower control limits. The tool helps distinguish between common cause and special cause variation. Which tool is this?

21

An agile team uses a tool where they maintain a list of features, enhancements, and bug fixes that are not yet scheduled for a sprint. This list is prioritized by the product owner. What is this list called?

22

A project manager notices that the project is behind schedule. The planned value (PV) is $50,000, earned value (EV) is $40,000, and actual cost (AC) is $45,000. What is the schedule performance index (SPI) and what does it indicate?

23

Which project document formally authorizes the project and identifies the project manager?

24

A project manager needs to show the sequence of project activities and their dependencies to identify the critical path. Which tool should they use?

25

In a user story, which component describes the benefit or value that the feature will provide?

26

A project team uses a tool that displays columns such as 'To Do', 'In Progress', and 'Done' to visualize workflow. This is an example of which type of board?

27

A project manager is reviewing a control chart and notices several data points outside the upper control limit (UCL). Which type of variation do these points indicate?

28

A project manager is selecting tools for agile project management. Which TWO tools are specifically designed for agile methodologies?

29

A project manager is analyzing project performance using earned value management. Which THREE metrics are used to calculate the estimate at completion (EAC)?

30

Which TWO documents are typically created during project initiation?

31

Which project scheduling tool depicts activities as bars on a timeline, showing dependencies and milestones?

32

A project manager is creating a document that formally authorizes the project and assigns the project manager. Which document is being created?

33

During a sprint review, the product owner notices that the team has completed 30 story points, but the burndown chart shows an upward trend. What is the most likely cause?

34

A project manager is analyzing quality data and wants to identify the most frequently occurring defects to prioritize corrective actions. Which quality tool should be used?

35

An agile team uses story points to estimate user stories. During planning poker, one developer consistently gives much higher estimates than the rest of the team. What is the best action for the team?

36

A project has a planned value (PV) of $50,000, earned value (EV) of $40,000, and actual cost (AC) of $45,000. What is the schedule variance (SV) and cost variance (CV)?

37

A project is 60% complete. The original budget (BAC) is $200,000. Actual costs to date are $130,000, and the earned value is $120,000. What is the estimate at completion (EAC) if the project will continue to perform at the current cost efficiency?

38

Which agile artifact contains the prioritized list of all desired work for a product?

39

A project team is using Jira for an agile project. The product owner wants to see the total amount of work completed each sprint and the remaining work. Which two charts should the project manager use? (Choose two, but this is a multiple-choice single select for the best pair. Actually, this is a multiple-choice question asking for a single best tool.)

40

A project manager is using a control chart to monitor the number of defects per day. The chart shows 10 data points within the control limits, but all 10 points are above the mean. What does this indicate?

41

Which document defines the roles and responsibilities of stakeholders in a project and is often presented as a matrix?

42

A project manager is reviewing the risk register and sees that a high-impact risk has a probability of 0.3 and an impact of $50,000. The team implements a response that reduces the probability to 0.1 and the impact remains $50,000. The response cost is $5,000. What is the net expected monetary value (EMV) of implementing the response?

43

A project manager is using a network diagram to identify the critical path. Which TWO statements are true about the critical path?

44

A project team is transitioning from a traditional to an agile approach. The project manager wants to adopt agile artifacts. Which THREE artifacts are commonly used in agile projects to track progress and manage work?

45

A project manager is evaluating earned value metrics for a project. The CPI is 0.8 and the SPI is 0.9. Which TWO conclusions can the project manager draw?

46

A project manager is creating a visual timeline that displays tasks as horizontal bars, shows dependencies between tasks, and highlights the critical path. Which tool should the manager use?

47

During a sprint review, the team shows that they completed 30 story points this sprint, which is consistent with their average velocity. The product owner asks how much work the team can likely complete in the next two sprints. Using velocity, what is the best estimate?

48

A project has a budget at completion (BAC) of $500,000. After 3 months, the earned value (EV) is $200,000, the actual cost (AC) is $250,000, and the planned value (PV) is $180,000. What is the cost performance index (CPI) and what does it indicate?

49

Which document formally authorizes a project and assigns the project manager?

50

A project team is using Jira for agile development. They have a list of features to be developed over multiple sprints. What is the term for this list, which represents all the work planned for the project?

51

A control chart shows a process with data points fluctuating within the upper and lower control limits, but 8 consecutive points appear on one side of the mean. What does this indicate?

52

A project manager needs to identify the root cause of a recurring defect. Which quality tool uses a fishbone diagram to categorize potential causes?

53

In a RACI matrix, which role is ultimately accountable for the successful completion of a task?

54

A project has a BAC of $100,000. The earned value is $40,000, actual cost is $50,000, and planned value is $30,000. What is the estimate at completion (EAC) assuming the current cost performance is expected to continue?

55

A project team uses planning poker to estimate user stories. What is the purpose of this technique?

56

A project manager is tracking issues and their resolution status. Which document should the manager use to record and monitor these issues?

57

Which diagram is used in quality management to prioritize the most significant causes of a problem, based on the 80/20 rule?

58

Which TWO documents should be included in the procurement management plan? (Select TWO).

59

Which THREE items are typically found in a project management plan? (Select THREE).

60

An agile team is reviewing their work. Which TWO metrics can be used to track progress within a sprint? (Select TWO).

61

A project manager is creating a visual representation of the project schedule that shows tasks as horizontal bars along a timeline, including dependencies and milestones. Which tool is being used?

62

During a sprint review, the team notes that the remaining work is not decreasing as expected. Which agile artefact would best help visualize the trend of remaining work over the sprint duration?

63

A project has a budget at completion (BAC) of $200,000. The earned value (EV) is $120,000 and the actual cost (AC) is $150,000. What is the estimate at completion (EAC) using the typical cost performance index (CPI) assumption?

64

A project manager wants to identify the most significant causes of delays in a software development project. Which quality tool should she use to prioritize the causes based on the Pareto principle?

65

In an Agile project, the team uses a tool to manage user stories and tasks. Which tool is specifically designed for Agile project management, supporting Scrum and Kanban boards?

66

A project manager is reviewing the schedule performance and finds that the earned value (EV) is $50,000 and the planned value (PV) is $60,000. What does this indicate?

67

Which document formally authorizes the project and assigns the project manager?

68

In a network diagram, the critical path is the longest path through the project. What does it determine?

69

Which document describes the roles and responsibilities in a project using the categories Responsible, Accountable, Consulted, and Informed?

70

A project manager is using a control chart to monitor quality. The data points fall within the control limits but show a run of seven points above the mean. What does this indicate?

71

A project team is using planning poker to estimate user stories. What is the purpose of this technique?

72

Which document contains the subsidiary plans for scope, schedule, cost, quality, resources, communication, risk, and procurement?

73

A project manager is selecting tools for an Agile project. Which TWO tools are commonly used for Agile project management? (Select two.)

74

A project is experiencing cost overruns. The project manager wants to calculate key earned value metrics. Which THREE metrics are needed to compute the cost performance index (CPI) and schedule performance index (SPI)? (Select three.)

75

A project manager is creating documents for procurement. Which TWO documents are typically used in procurement processes? (Select two.)

76

A project manager is tracking remaining work over the course of a sprint to see if the team is on pace to complete all committed stories. Which agile artifact should the project manager use?

77

During project execution, a team discovers that the actual cost of work performed is $45,000, the planned value is $50,000, and the earned value is $40,000. Which statement is correct?

78

A project team uses planning poker to estimate user stories. The product owner describes a story that involves integrating with a third-party API. The team discusses unknowns and then votes. The estimates are 5, 8, 13, and 20 story points. What should the team do next?

79

Which document formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities?

80

A project manager is creating a RACI matrix for the project. One activity involves conducting security testing. The security lead will perform the testing, the project manager is responsible for ensuring it happens, and the compliance officer needs to be informed of the results. Which assignment is correct?

81

Which project scheduling tool shows activities as bars on a timeline, including dependencies and milestones?

82

A project manager needs to identify which tasks are critical to the project's completion date. After creating the project schedule, which tool should be used to visualize the critical path?

83

During a quality audit, the project team discovers that 80% of customer complaints are caused by 20% of the defect types. Which quality tool should the project manager use to present this data and prioritize corrective actions?

84

An agile team uses story points for estimating effort. During sprint planning, the team's average velocity is 30 story points per sprint. The product owner wants to commit to 35 story points for the upcoming sprint. What should the team do?

85

A project team is using Jira for agile project management. They want to visualize the flow of work across columns such as 'To Do', 'In Progress', and 'Done'. Which board type should they use?

86

Which document contains the subsidiary plans for scope, schedule, cost, quality, resources, communication, risk, and procurement?

87

A project has a budget at completion (BAC) of $200,000. The earned value (EV) is $100,000, and the actual cost (AC) is $120,000. What is the estimate at completion (EAC) assuming the current cost performance index (CPI) will remain the same?

88

Which TWO documents are typically found in a project's procurement management plan?

89

Which THREE items are considered agile artefacts?

90

A project manager is analyzing quality control data and wants to identify whether process variation is due to special causes or common causes. Which TWO tools would be most helpful?

91

A project manager wants to visualize task dependencies and the critical path for a construction project. Which tool should they use?

92

In an agile project using Jira, the product owner wants to prioritize the work for the next iteration. Which document or artefact should they refer to?

93

A project manager is creating a document that formally authorizes the project and assigns the project manager. Which document is this?

94

During a software development project, the team estimates story points using planning poker. A story is estimated at 8 points, while a similar story was previously estimated at 5 points. What is the primary reason for using relative sizing with story points?

95

A project has a BAC of $200,000. After three months, the earned value (EV) is $80,000 and the actual cost (AC) is $90,000. What is the cost variance (CV) and what does it indicate?

96

A project manager uses a control chart to monitor the number of defects found during testing. The chart shows one data point above the upper control limit (UCL). What action should the project manager take?

97

A project manager is reviewing the communication plan and notices that stakeholder A is listed as 'Responsible' for a task in the RACI matrix. According to RACI, what does 'Responsible' mean?

98

In a manufacturing project, the team uses a Pareto chart to analyze defects. The chart shows that 80% of defects come from 20% of the causes. Which principle does this illustrate?

99

An agile team has a velocity of 30 story points per sprint. The product backlog contains 120 story points of work. How many sprints are needed to complete the backlog assuming no changes?

100

A project manager is evaluating the project's performance using EVM. PV = $50,000, EV = $45,000, AC = $55,000. Which of the following is true?

101

A project manager is creating a risk register. One risk has a probability of 0.3 and an impact of $50,000. What is the expected monetary value (EMV) of this risk?

102

A project has a BAC of $500,000 and a CPI of 0.8. What is the estimate at completion (EAC) assuming the current cost performance will continue?

103

A project manager is selecting a project management tool for a hybrid project that requires both a Gantt chart view for waterfall tasks and a Kanban board for agile tasks. Which TWO tools would best meet these requirements?

104

A project manager is reviewing quality control results and sees a pattern of increasing defects over time. Which THREE quality tools would be most appropriate to analyze this situation?

105

In an agile project, the team is defining the 'Definition of Done' (DoD). Which TWO statements are typically included in a good DoD?

106

Which project scheduling tool displays tasks as horizontal bars on a timeline, shows dependencies between tasks, and can highlight the critical path?

107

A project team uses a tool that shows only major events or deadlines, such as the start and end of phases. Which type of chart are they using?

108

During sprint planning, the team uses a technique where each member privately selects a card representing a number of story points for a user story. After revealing, they discuss discrepancies. This technique is known as:

109

A project manager notices that the actual cost (AC) is $50,000, the earned value (EV) is $45,000, and the planned value (PV) is $55,000. Which statement is true regarding schedule and cost performance?

110

A project manager uses a diagram to identify the most frequent causes of defects in a process. The diagram displays bars in descending order and a cumulative line. Which quality tool is being used?

111

A project team is using a tool to track user stories, epics, and bugs within sprints. The tool allows the team to view work in columns such as 'To Do', 'In Progress', and 'Done'. Which tool feature is being described?

112

A project has a budget at completion (BAC) of $200,000. After 3 months, the earned value (EV) is $80,000, and the actual cost (AC) is $100,000. What is the estimate at completion (EAC) assuming the cost performance index (CPI) will remain the same for the remainder of the project?

113

Which project document formally authorizes the project and provides the project manager with the authority to apply organizational resources?

114

A project manager is creating a document that identifies all project stakeholders and their interests, influence, and expectations regarding the project. This document is the:

115

A project manager is reviewing a control chart for a manufacturing process. Several data points fall outside the upper control limit (UCL). What type of variation do these points indicate?

116

A project manager is selecting two documents that are essential for defining project scope. Which TWO documents should they choose?

117

During a quality audit, the team identifies that defects are concentrated in a few areas. The project manager decides to use a Pareto chart. Which TWO statements are true about Pareto charts?

118

An agile team uses a burnup chart to track progress. Which THREE pieces of information are typically shown on a burnup chart?

119

A project manager is reviewing earned value data: PV = $150,000, EV = $120,000, AC = $130,000. Which THREE statements are correct?

120

A project manager needs to create a RACI matrix for a project. Which THREE roles should be included in the matrix?

121

A project manager needs to communicate the project schedule to senior management, highlighting only key events such as the start and end of phases and major deliverables. Which type of chart is most appropriate?

122

During a project, the project manager calculates the following: Earned Value (EV) = $50,000, Planned Value (PV) = $60,000, Actual Cost (AC) = $55,000. Which statement accurately describes the project's performance?

123

In an Agile project, the team uses story points to estimate effort. During sprint planning, they select user stories from the product backlog and assign them to the sprint. What is the resulting list of items committed for the sprint called?

124

A project team is using Jira for an Agile project. Which TWO artefacts are typically managed within Jira for sprint planning and tracking? (Choose two.)

125

A project manager is reviewing quality control results. Which THREE tools are commonly used to identify the root causes of defects or to prioritize improvement efforts? (Choose three.)

Practice all 125 Tools and Documentation questions

Other PK0-005 exam domains

Project Management ConceptsProject Life CycleConstraints and ChangesProject Life Cycle PhasesBasics of IT Infrastructure and IT Project Management

Frequently asked questions

What does the Tools and Documentation domain cover on the PK0-005 exam?

The Tools and Documentation domain covers the key concepts tested in this area of the PK0-005 exam blueprint published by CompTIA. Courseiva provides free domain-focused practice, mock exams, missed-question review, and readiness tracking across all PK0-005 domains — no account required.

How many Tools and Documentation questions are in the PK0-005 question bank?

The Courseiva PK0-005 question bank contains 125 questions in the Tools and Documentation domain. Click any question to see the full explanation and answer breakdown.

What is the best way to practice Tools and Documentation for PK0-005?

Start with a 10-question focused session to identify your baseline accuracy in this domain. Read every explanation — even for questions you answer correctly — to understand the reasoning. Once you score consistently above 80%, move to a 20–30 question session to confirm depth before moving to the next domain.

Can I practice only Tools and Documentation questions for PK0-005?

Yes — the session launcher on this page draws questions exclusively from the Tools and Documentation domain. Choose 10, 20, 30, or 50 questions for a focused session, or click individual questions to review them one by one.

Free forever · No credit card required

Track your PK0-005 domain progress

Save your results, see per-domain analytics, and get readiness scores — free, for every certification.

Sign Up Free

Free forever · Every certification included

Practice Session

10 questions20 questions30 questions50 questions

Study Resources

All DomainsPractice TestMock ExamFlashcardsStudy Guide