Courseiva
Knowledge + Practice
CertificationsVendorsCareer RoadmapsLabs & ToolsStudy GuidesGlossaryPractice Questions
C
Courseiva

Free IT certification practice questions with explained answers for CCNA, CompTIA, AWS, Azure, Google Cloud, and more.

Certification Practice Questions

CCNA practice questionsSecurity+ SY0-701 practice questionsAWS SAA-C03 practice questionsAZ-104 practice questionsAZ-900 practice questionsCLF-C02 practice questionsA+ Core 1 practice questionsGoogle Cloud ACE practice questionsCySA+ CS0-003 practice questionsNetwork+ N10-009 practice questions
View all certifications →

Product

CertificationsCertification PathsExam TopicsPractice TestsExam Dumps vs Practice TestsStudy HubComparisons

Company

AboutContactEditorial PolicyQuestion Writing PolicyTrust Center

Legal

Privacy PolicyTerms of Service

Courseiva is a free IT certification practice platform offering original exam-style practice questions, detailed explanations, topic-based practice, mock exams, readiness tracking, and study analytics for Cisco, CompTIA, Microsoft, AWS, and other technology certifications.

© 2026 Courseiva. Courseiva is operated by JTNetSolutions Ltd. All rights reserved.

Courseiva is an independent certification practice platform and is not affiliated with, endorsed by, or sponsored by Cisco, Microsoft, AWS, CompTIA, Google, ISC2, ISACA, or any other certification vendor. Vendor names and certification marks are used only to identify the exams learners are preparing for.

← Project Management Fundamentals and Core Concepts practice sets

CAPM Project Management Fundamentals and Core Concepts • Complete Question Bank

CAPM Project Management Fundamentals and Core Concepts — All Questions With Answers

Complete CAPM Project Management Fundamentals and Core Concepts question bank — all 0 questions with answers and detailed explanations.

118
Questions
Free
No signup
Certifications/CAPM/Practice Test/Project Management Fundamentals and Core Concepts/All Questions
Question 1mediummultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

A project manager is reviewing the project charter and notices that the business case includes a cost-benefit analysis with a Net Present Value (NPV) of $50,000 and an Internal Rate of Return (IRR) of 12%. The company's required rate of return is 10%. What should the project manager conclude about this project?

Question 2hardmultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

During project execution, a key stakeholder requests a significant change that will increase project scope. The project manager performs an impact analysis and determines that the change will delay the project by two weeks and increase costs by 10%. However, the change is critical for regulatory compliance. What should the project manager do first?

Question 3easymultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

A project manager is estimating the duration of an activity. The optimistic estimate is 4 days, the pessimistic is 12 days, and the most likely is 6 days. Using the PERT three-point estimate, what is the expected duration?

Question 4mediummultiple choice
Read the full NAT/PAT explanation →

A project team is working on a software development project. The project manager notices that the team is spending too much time on unplanned work, resulting in delays to the critical path. What technique should the project manager use to reduce unplanned work and improve focus?

Question 5hardmultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

A project manager is assigned to a project that is in the planning phase. The sponsor asks the project manager to include a 10% contingency reserve in the budget. The project manager knows that the project has a high degree of uncertainty. What should the project manager do?

Question 6mediummulti select
Read the full Project Management Fundamentals and Core Concepts explanation →

Which TWO of the following are outputs of the Identify Stakeholders process?

Question 7hardmulti select
Read the full Project Management Fundamentals and Core Concepts explanation →

Which THREE of the following are types of dependencies that can exist between project activities?

Question 8mediummultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

A project manager is leading a software development project. The sponsor has requested a new feature that was not part of the original scope. The project manager assesses that adding this feature will require additional resources and will extend the timeline by two weeks. What should the project manager do first?

Question 9easymultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

A project team is working on a construction project. The project manager notices that the actual cost is consistently higher than planned. Which project management process is most directly responsible for monitoring and controlling costs?

Question 10hardmultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

A project manager is assigned to a project that is in execution phase. The project has a cost performance index (CPI) of 0.8 and a schedule performance index (SPI) of 1.1. Which of the following best describes the current status of the project?

Question 11mediummultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

Refer to the exhibit. What is the total float of Task B?

Exhibit

Refer to the exhibit.

Task A: duration 5 days, predecessor: none
Task B: duration 3 days, predecessor: A
Task C: duration 4 days, predecessor: A
Task D: duration 2 days, predecessor: B, C
Question 12easymultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

During project planning, the project manager wants to ensure that all work required to complete the project is identified. Which document is the primary output of the process that defines and controls what is included in the project?

Question 13hardmulti select
Read the full Project Management Fundamentals and Core Concepts explanation →

Which TWO of the following are outputs of the Identify Risks process?

Question 14mediummulti select
Read the full Project Management Fundamentals and Core Concepts explanation →

Which THREE of the following are components of the project charter?

Question 15easymultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

A project team is experiencing frequent changes in requirements. The project manager wants to minimize disruptions. Which approach is best to manage changes effectively?

Question 16mediummultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

A project manager is leading a software development project. During the planning phase, the team identifies a significant risk that a key third-party API may be deprecated before the project completes. The project sponsor asks for a risk response strategy. Which strategy should the project manager recommend to best address this risk?

Question 17easymultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

A project team is struggling with unclear roles and responsibilities, leading to duplicated work and missed tasks. Which document should the project manager create or update to resolve this issue?

Question 18hardmultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

During project execution, a key stakeholder requests a change that would add a new feature. The project manager assesses the impact and finds that it will increase the project cost by 15% and extend the schedule by three weeks. The sponsor is concerned about the budget but sees the value. What should the project manager do next?

Question 19mediummulti select
Read the full Project Management Fundamentals and Core Concepts explanation →

Which TWO of the following are examples of project constraints? (Choose two.)

Question 20hardmultiple choice
Read the full NAT/PAT explanation →

You are a project manager for a construction project to build a new office wing. The project is in the execution phase. The team reports that the foundation work is behind schedule because of unexpected soil conditions that require additional stabilization. The project plan had a contingency reserve for such issues. The project sponsor is concerned about the delay and asks you to compress the schedule to recover. The project has a fixed completion date and cannot be delayed. After analyzing the schedule, you find that there is float on some non-critical paths, but critical path activities are already resource-loaded. What is the BEST course of action to address the delay while keeping the project on track?

Question 21mediummultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

You are managing a software upgrade project for a financial institution. The project involves upgrading the core banking system to a new version. During user acceptance testing (UAT), the testers find that the new system does not handle certain legacy data formats correctly, causing errors. The project schedule has no buffer left, and the go-live date is fixed due to regulatory compliance. The team estimates it will take two weeks to fix the issue, but the go-live is in one week. The project manager has already used the contingency reserve for other issues. What should the project manager do next?

Question 22mediummultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

A project manager is assigned to a new product development project. The project charter has been approved, and the team is preparing the project management plan. During the planning process, the project manager wants to ensure that all project work is aligned with the business objectives. Which document should the project manager review to confirm the alignment of the project with organizational strategy?

Question 23hardmultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

Refer to the exhibit. The project manager notices that the resource histogram shows a peak of 15 FTEs in Week 2, exceeding the available 12 FTEs. The project manager needs to bring the resource usage within the limit without increasing the project duration or budget. Which action should the project manager take?

Exhibit

Refer to the exhibit.

Resource Histogram:

Week 1: 10 FTEs
Week 2: 15 FTEs
Week 3: 12 FTEs
Week 4: 8 FTEs

Total available FTEs per week: 12

Cost per FTE: $1000/week

Project budget: $50,000
Question 24easymultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

A project manager is leading a software development project. The team has completed the first iteration and is reviewing the lessons learned. Which output of the Manage Project Knowledge process should the project manager update with the lessons learned from this iteration?

Question 25mediummultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

During project execution, a key stakeholder requests a change that would add a new feature to the product. The project manager evaluates the impact on scope, schedule, and cost. According to the change management plan, which step should the project manager take first?

Question 26mediumdrag order
Read the full Project Management Fundamentals and Core Concepts explanation →

Drag and drop the steps for performing risk management planning in the correct order.

Drag steps to the numbered slots on the right, or tap a step then tap a slot.

Steps
Order
1Step 1
2Step 2
3Step 3
4Step 4
5Step 5
Question 27mediumdrag order
Read the full Project Management Fundamentals and Core Concepts explanation →

Drag and drop the steps for developing a project schedule in the correct order.

Drag steps to the numbered slots on the right, or tap a step then tap a slot.

Steps
Order
1Step 1
2Step 2
3Step 3
4Step 4
5Step 5
Question 28mediummatching
Read the full Project Management Fundamentals and Core Concepts explanation →

Match each project document to its description.

Drag a concept onto its matching description — or click a concept then click the description.

Concepts
Matches

Authorizes the project and assigns PM

Comprehensive plan for execution

Hierarchical decomposition of work

List of identified risks and responses

Documents and tracks project issues

Question 29mediummatching
Read the full Project Management Fundamentals and Core Concepts explanation →

Match each project role to its responsibility.

Drag a concept onto its matching description — or click a concept then click the description.

Concepts
Matches

Leads project team and manages constraints

Provides resources and champions project

Defines product backlog and priorities

Facilitates Scrum process and removes impediments

Elicits and documents requirements

Question 30mediummultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

During the project kickoff meeting, a key stakeholder expresses concerns about the project scope. What should the project manager do first?

Question 31easymultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

Which of the following best defines a project?

Question 32hardmultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

What is the main advantage of a projectized organization structure?

Question 33mediummultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

A project manager notices that the project is behind schedule. Which of the following actions is most appropriate to bring the project back on track?

Question 34easymultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

Which of the following is NOT a purpose of the project charter?

Question 35hardmultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

In earned value management, if the Cost Performance Index (CPI) is 0.8 and the Schedule Performance Index (SPI) is 1.2, what does this indicate?

Question 36mediummultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

Which of the following is a key output of the Plan Risk Management process?

Question 37easymultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

A milestone in a project schedule is best described as:

Question 38hardmultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

In a predictive project life cycle, which of the following best describes the relationship between scope, time, and cost?

Question 39easymulti select
Read the full Project Management Fundamentals and Core Concepts explanation →

Which TWO of the following are project management process groups?

Question 40mediummulti select
Read the full Project Management Fundamentals and Core Concepts explanation →

Which THREE of the following are characteristics of a project?

Question 41hardmulti select
Read the full Project Management Fundamentals and Core Concepts explanation →

Which TWO of the following are outputs of the Plan Stakeholder Engagement process?

Question 42hardmultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

Refer to the exhibit. Based on the probability and impact values, which risk has the highest risk score?

Exhibit

{
  "risks": [
    {"id": "R1", "probability": 0.3, "impact": 0.5},
    {"id": "R2", "probability": 0.8, "impact": 0.2},
    {"id": "R3", "probability": 0.6, "impact": 0.9},
    {"id": "R4", "probability": 0.4, "impact": 0.7}
  ]
}
Question 43easymultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

Refer to the exhibit. How many work packages are at the lowest level of the WBS?

Exhibit

{
  "wbs": {
    "id": "1.0",
    "name": "Project",
    "children": [
      {"id": "1.1", "name": "Planning", "level": 2},
      {"id": "1.2", "name": "Execution", "level": 2, "children": [
        {"id": "1.2.1", "name": "Develop", "level": 3},
        {"id": "1.2.2", "name": "Test", "level": 3}
      ]},
      {"id": "1.3", "name": "Close", "level": 2}
    ]
  }
}
Question 44mediummultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

Refer to the exhibit. Based on the error log, which task has a dependency issue?

Exhibit

2023-05-10 14:22:33 ERROR: Task T2 - dependency not met: Predecessor task T1 not completed.
2023-05-10 14:25:12 WARN: Task T3 - resource overallocation detected.
2023-05-10 14:30:45 ERROR: Task T4 - schedule variance exceeded threshold.
Question 45easymultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

A project manager is defining success criteria for a new software development project. Which of the following is the most objective and measurable success criterion?

Question 46easymultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

A project team is working on a construction project. The project manager notices that the team is spending excessive time clarifying task responsibilities. Which project management artifact would most directly help assign clear ownership?

Question 47easymultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

During project planning, the team identifies that the project requires a specific vendor for a critical component. Which process group is being executed?

Question 48mediummultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

A project has a fixed deadline but flexible scope. The project manager receives a change request that would significantly increase scope. What should the project manager do first?

Question 49mediummultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

During project execution, a key team member leaves the company. The project manager needs to quickly reassign tasks to maintain progress. Which document should be consulted first to understand the team member's current responsibilities?

Question 50mediummultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

A project manager is leading a team that includes members from different cultures. Communication misunderstandings are causing delays. Which action best addresses the root cause?

Question 51hardmultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

A project manager is managing a complex IT project with many inter-dependencies. During execution, a key stakeholder requests a feature that will require rework of several completed deliverables. The project manager wants to minimize disruption to the project. What is the best course of action?

Question 52hardmultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

The sponsor is concerned about the accuracy of cost estimates prepared using analogous estimating. Which estimating technique should the project manager recommend to improve accuracy?

Question 53hardmultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

A project is in the executing phase, and the team is frequently reworking deliverables due to defects. Which process is most likely inadequate?

Question 54easymulti select
Read the full Project Management Fundamentals and Core Concepts explanation →

Which TWO of the following are typically outputs of the Initiating process group?

Question 55mediummulti select
Read the full Project Management Fundamentals and Core Concepts explanation →

Which TWO of the following are considered examples of enterprise environmental factors (EEFs)?

Question 56hardmulti select
Read the full Project Management Fundamentals and Core Concepts explanation →

Which THREE of the following are processes that belong to the Planning process group?

Question 57easymultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

Refer to the exhibit. The project manager is reviewing deployment logs. Which statement best describes the event?

Exhibit

Exhibit:
```
[2025-04-01 10:15:32] ERROR: Connection timeout to database 'sales_db' during query execution. Retry 1 of 3.
[2025-04-01 10:15:35] INFO: Retry successful.
```
Question 58mediummultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

Refer to the exhibit. The project manager needs to calculate the total hours assigned to each resource. Which resource has the highest total assigned hours?

Exhibit

Exhibit:
```json
{
  "ResourceAssignments": [
    {"Resource": "Alice", "Task": "Design", "Hours": 40},
    {"Resource": "Bob", "Task": "Development", "Hours": 80},
    {"Resource": "Charlie", "Task": "Testing", "Hours": 30},
    {"Resource": "Alice", "Task": "Documentation", "Hours": 20}
  ]
}
```
Question 59hardmultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

Refer to the exhibit. Which task has a dependency that requires two tasks to start at the same time with a 2-day delay?

Exhibit

Exhibit:
```
Task dependencies from project scheduling tool:
Task A - Start-to-Start with 2 days lag (SS+2d)
Task B - Finish-to-Finish with 3 days lead (FF-3d)
Task C - Finish-to-Start (FS)
Task D - Start-to-Start (SS)
```
Question 60easymultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

A project manager is leading a team in a matrix organization where team members report to both a functional manager and the project manager. The project is in the planning phase. What is the primary responsibility of the project manager during this phase?

Question 61mediummultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

A construction project is underway. The project manager receives a report that the concrete supplier will deliver late, causing a two-week delay. The project has no schedule reserve. What is the best course of action?

Question 62hardmultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

A project manager in a weak matrix organization is having difficulty getting team members to complete project tasks because they prioritize their functional work. Which type of power should the project manager primarily rely on to influence the team?

Question 63easymultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

Which of the following is a characteristic of the project life cycle?

Question 64mediummultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

A project manager is estimating activity durations. The team provides three estimates: optimistic 10 days, pessimistic 20 days, most likely 14 days. Using the PERT beta distribution, what is the expected duration?

Question 65hardmultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

During a project, the team identifies a risk that could cause a 20% increase in cost. The project manager decides to accept the risk because the probability is low. What risk response strategy is being used?

Question 66easymultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

A project has a cost baseline of $100,000. At the end of month 2, the planned value is $30,000, and the actual cost is $40,000. If the earned value is $25,000, what is the cost variance?

Question 67mediummultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

A project manager wants to ensure that all project documents are properly managed and approved. Which process group focuses on controlling changes to project documents?

Question 68hardmultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

A project is being executed in a highly regulated industry. The quality management plan requires extensive documentation. During a quality audit, the auditor finds that some test results are missing. What is the MOST appropriate action for the project manager?

Question 69easymulti select
Read the full Project Management Fundamentals and Core Concepts explanation →

Which TWO of the following are generally true about projects versus operations? (Choose two)

Question 70mediummulti select
Read the full Project Management Fundamentals and Core Concepts explanation →

Which THREE of the following are recognized process groups in the PMBOK Guide? (Choose three)

Question 71hardmulti select
Read the full Project Management Fundamentals and Core Concepts explanation →

Which TWO of the following are benefits of using a project management plan? (Choose two)

Question 72easymultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

Refer to the exhibit. What is the cost performance index (CPI)?

Exhibit

{
  "EV": 5000,
  "AC": 6000,
  "PV": 5500
}
Question 73mediummultiple choice
Read the full NAT/PAT explanation →

Refer to the exhibit. What is the duration of the critical path?

Exhibit

Activity A: Duration 5 days, Predecessor: None
Activity B: Duration 3 days, Predecessor: A
Activity C: Duration 4 days, Predecessor: A
Activity D: Duration 6 days, Predecessor: B, C
Question 74hardmultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

Refer to the exhibit. Which risk has the highest expected monetary value?

Exhibit

Risk ID: R1, Probability: 0.3, Impact: $40,000
Risk ID: R2, Probability: 0.6, Impact: $50,000
Risk ID: R3, Probability: 0.2, Impact: $100,000
Question 75easymultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

During project execution, a key stakeholder requests a new feature that was not included in the approved scope. What should the project manager do first?

Question 76mediummultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

A project manager is assigned to a cross-functional initiative in a matrix organization. The team members report to both the project manager and their functional managers. What is the primary challenge the project manager would face?

Question 77hardmultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

A software development project is facing high uncertainty in requirements. The team is experienced and prefers frequent feedback. Which project life cycle approach is most appropriate?

Question 78easymultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

Which document formally authorizes the project and provides the project manager with authority to apply organizational resources?

Question 79mediummultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

A project is behind schedule and over budget. The sponsor asks the project manager to reduce costs without affecting the end date. Which constraint should the project manager consider adjusting?

Question 80hardmultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

During a project, two team members have a conflict that is affecting progress. The project manager attempts to resolve it but fails. What is the next best action?

Question 81easymultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

Which of the following best describes a project versus ongoing operations?

Question 82mediummultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

A project manager is reviewing the business case for a new initiative. Which document should the project manager create to define how the project will deliver the expected benefits?

Question 83hardmultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

A project manager notices that the team is frequently redoing work because requirements were unclear. Which process group interaction would help address this issue?

Question 84mediummulti select
Read the full Project Management Fundamentals and Core Concepts explanation →

Which TWO are outputs of the Initiating process group?

Question 85mediummulti select
Read the full Project Management Fundamentals and Core Concepts explanation →

Which TWO are types of organizational structures commonly used in project management?

Question 86hardmulti select
Read the full Project Management Fundamentals and Core Concepts explanation →

Which THREE are common project constraints that must be balanced?

Question 87mediummultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

A project manager sees this JSON policy for cloud resources. Which project management process is being supported by enforcing these tags?

Exhibit

Refer to the exhibit.
{
  "policy": {
    "resourceTags": {
      "project": "alpha",
      "costCenter": "12345",
      "environment": "production"
    },
    "autoStop": true,
    "maxCost": 5000
  }
}
Question 88hardmultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

A project manager sees this git log output. The team is delivering features in small increments. Which project life cycle phase does the 'Fix login bug' commit represent?

Network Topology
$ git logonelineRefer to the exhibit.9e8f2a1 Add user authenticationf7d3b9c Initial commit$ git tag -lv1.0
Question 89easymultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

A project team encounters this error during deployment. Which project document should be updated first?

Exhibit

Refer to the exhibit.
ERROR 2025-03-10 14:32:01 Deployment script failed: Missing config file /etc/app/config.yaml
INFO  2025-03-10 14:32:02 Rollback initiated
Question 90easymultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

A project manager is assigned to a project in a matrix organization. Who typically has authority over resource assignment and prioritization?

Question 91mediummultiple choice
Read the full NAT/PAT explanation →

A project is behind schedule. Which schedule compression technique involves adding additional resources to critical path activities?

Question 92hardmultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

During project planning, the team identifies that a key component must be custom-built by a vendor with a long lead time. The project manager wants to avoid the risk of the vendor failing to deliver. Which risk response strategy is most appropriate?

Question 93mediummulti select
Read the full Project Management Fundamentals and Core Concepts explanation →

Which TWO are benefits of creating a Work Breakdown Structure (WBS)?

Question 94hardmulti select
Read the full Project Management Fundamentals and Core Concepts explanation →

Which THREE are techniques used for estimating activity durations?

Question 95easymulti select
Read the full Project Management Fundamentals and Core Concepts explanation →

Which THREE are components of the project management plan?

Question 96mediummultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

Refer to the exhibit. An administrator applies this IAM policy to a user. What is the effect on the user's access to the S3 bucket?

Exhibit

{ "Statement": [ { "Effect": "Deny", "Action": "s3:*", "Resource": "arn:aws:s3:::example-bucket", "Condition": { "BoolIfExists": { "aws:MultiFactorAuthPresent": "false" } } } ] }
Question 97easymultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

A project manager is assigned a project that has a very low tolerance for scope changes. Which development approach is most appropriate?

Question 98mediummultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

In project procurement management, what is the primary purpose of the procurement statement of work (SOW)?

Question 99hardmultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

A project team using a Kanban board wants to predict when all remaining backlog items will be completed. Which metric is most useful for this prediction?

Question 100mediummultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

A project sponsor asks the project manager to report on budget performance. Which metric best indicates whether the project is under or over budget?

Question 101hardmultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

A medium-sized software company is developing a new mobile application. The project manager, Alex, has a team of 10 developers and 2 testers. The organization uses a hybrid approach combining waterfall planning for the overall phases and agile for individual iterations. In the first iteration, the team committed to completing 20 user stories. During the sprint, two developers left the company, and the remaining team members had to pick up their tasks. The product owner is concerned about the delivery date. Alex needs to communicate the impact to stakeholders. What should Alex do first?

Question 102hardmultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

A construction project manager, Maria, is overseeing the building of a bridge. The project has a fixed budget and schedule. During the execution phase, the quality audit reveals that the concrete used does not meet the specified strength requirements. The concrete supplier insists that the concrete meets industry standards. However, the project specifications require a higher strength grade. Maria must decide on corrective action. What should she do?

Question 103easymultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

In which project management process group is the project charter developed?

Question 104easymultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

A project team is using a colocation (war room) technique. What is the primary benefit?

Question 105mediummultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

A project manager is evaluating two project proposals. Proposal A has a benefit-cost ratio (BCR) of 1.2 and a payback period of 3 years. Proposal B has a BCR of 1.5 and a payback period of 4 years. The organization has limited funds and wants to maximize return on investment. Which proposal should the project manager recommend?

Question 106easymultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

During the initiation phase of a project, the project manager needs to identify stakeholders. What is the primary purpose of stakeholder identification at this stage?

Question 107mediummulti select
Read the full Project Management Fundamentals and Core Concepts explanation →

Which TWO of the following are considered key constraints in project management that form the traditional 'triple constraint'?

Question 108hardmulti select
Read the full Project Management Fundamentals and Core Concepts explanation →

Which THREE of the following are characteristics of a matrix organizational structure that impact project management?

Question 109mediummultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

You are a project manager in a functional organization managing a software upgrade project. The functional managers control resources and priorities. Your project requires a senior developer from the IT department for two weeks starting next Monday. The IT functional manager informs you that the developer is assigned to an urgent operational issue and cannot be released until further notice. The project has a fixed deadline in four weeks, and any delay will impact the next phase. You have already used your influence and escalated to senior management, but the functional manager insists on keeping the developer. What should you do next?

Question 110hardmultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

You are a project manager working on a large infrastructure project under a strong matrix organization. The project charter has been signed, and you have been given authority to manage the project. However, the functional manager of the engineering department is refusing to assign the promised resources, claiming that another project has higher priority. You have already held a meeting with the sponsor and functional manager, but the functional manager remains uncooperative. The sponsor is concerned about the project's viability. What is the most effective course of action?

Question 111easymultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

Your organization is initiating a new mobile app development project. The product owner expects to release a minimum viable product (MVP) within three months, with subsequent iterations based on user feedback. The development team is experienced with agile methodologies. The project sponsor, however, is accustomed to traditional waterfall projects and insists on a detailed upfront plan covering all requirements and a fixed schedule. You need to select a project life cycle that balances the product owner's desire for iterative delivery with the sponsor's need for predictability. What is the most appropriate approach?

Question 112mediummultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

During project execution, you notice that a key stakeholder, the head of the legal department, has been disengaged from project reviews and has not responded to your emails requesting input on a regulatory compliance issue. The project is at risk of missing a legal requirement that could result in fines. You have classified this stakeholder as having high power and high interest. According to stakeholder engagement best practices, what should you do first?

Question 113hardmultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

You are managing a project to implement a new customer relationship management (CRM) system. The project management plan has been approved, and you are in the executing process group. A team member reports that a vendor has delivered a software module that does not meet the acceptance criteria specified in the procurement statement of work. The team member suggests modifying the acceptance criteria to accept the module as is, because returning it would cause a two-week delay. You review the project management plan and the requirements documentation. What should you do?

Question 114mediummultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

A project is in the monitoring and controlling phase. The project manager calculates the cost performance index (CPI) as 0.8 and the schedule performance index (SPI) as 1.0. The project budget is $500,000, and the actual costs to date are $200,000. The project is behind schedule? Actually SPI=1.0 means on schedule. But the question: What does this indicate about the project performance?

Question 115hardmultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

You are a project manager in a projectized organization. The project is nearing completion, but a key stakeholder has introduced several new requirements that were not in the original scope. The stakeholder insists these are critical for user acceptance. The project is already behind schedule and over budget. The change control board (CCB) has denied all previous change requests due to time and cost constraints. What is the best course of action?

Question 116mediummulti select
Read the full Project Management Fundamentals and Core Concepts explanation →

Which TWO of the following are true regarding a project's life cycle?

Question 117hardmultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

Refer to the exhibit. What is the total float of activity C?

Exhibit

Activity | Duration | Predecessors
A        | 5        | none
B        | 3        | A (FS)
C        | 4        | A (FS)
D        | 6        | B, C (FS)
E        | 2        | D (FS)
F        | 3        | C (FS)
G        | 4        | E, F (FS)
Question 118easymultiple choice
Read the full Project Management Fundamentals and Core Concepts explanation →

A manufacturing company is implementing a new ERP system. The project team includes members from IT, finance, and operations. The organization uses a strong matrix structure. Recently, the project has been missing milestones because the operations manager frequently assigns urgent operational tasks to the operations team members, who are also assigned part-time to the project. The project manager has discussed this with the operations manager, but the situation continues. The project sponsor is concerned about the delays and wants a solution within two days. What should the project manager do?

Practice tests

Scored 10-question sessions with instant feedback and explanations.

CAPM Practice Test 1 — 10 Questions→CAPM Practice Test 2 — 10 Questions→CAPM Practice Test 3 — 10 Questions→CAPM Practice Test 4 — 10 Questions→CAPM Practice Test 5 — 10 Questions→CAPM Practice Exam 1 — 20 Questions→CAPM Practice Exam 2 — 20 Questions→CAPM Practice Exam 3 — 20 Questions→CAPM Practice Exam 4 — 20 Questions→Free CAPM Practice Test 1 — 30 Questions→Free CAPM Practice Test 2 — 30 Questions→Free CAPM Practice Test 3 — 30 Questions→CAPM Practice Questions 1 — 50 Questions→CAPM Practice Questions 2 — 50 Questions→CAPM Exam Simulation 1 — 100 Questions→

Practice by domain

Each domain maps to a weighted exam section. Focus on the domain where you are weakest.

Agile Frameworks and MethodologiesProject Management Fundamentals and Core ConceptsPredictive Plan-Based MethodologiesBusiness Analysis Frameworks

Practice by scenario

Filter questions by type — troubleshooting, exhibit, drag-and-drop, PBQ, ACLs, OSPF, and more.

Browse scenarios→

Continue studying

All Project Management Fundamentals and Core Concepts setsAll Project Management Fundamentals and Core Concepts questionsCAPM Practice Hub