Activity A: Duration 5 days, Predecessor: None
Activity B: Duration 3 days, Predecessor: A
Activity C: Duration 4 days, Predecessor: A
Activity D: Duration 6 days, Predecessor: B, C

Refer to the exhibit. What is the duration of the critical path?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

15 days

The critical path is A -> C -> D with a total duration of 5 + 4 + 6 = 15 days. The other path A -> B -> D is 5+3+6=14 days.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • 15 days

    Why this is correct

    Correct calculation of longest path.

  • 9 days

    Why it's wrong here

    Incorrect sum.

  • 14 days

    Why it's wrong here

    This is the duration of the non-critical path.

  • 12 days

    Why it's wrong here

    Incorrect sum of durations.

About these practice questions

Courseiva writes every CAPM question from scratch — 487 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.