Correct answer & explanation
✓Project Charter: Authorizes the project and identifies the project manager.
The correct matches are: Project Charter (authorization), Project Management Plan (execution approach), Scope Statement (detailed scope), and WBS (scope decomposition). Common confusions include swapping the charter with the management plan and equating the WBS to a risk register.
About these practice questions
Courseiva writes every CAPM question from scratch — 487 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
How Courseiva writes practice questions · Editorial policy