Project Management Fundamentals and Core ConceptsmediumMultiple SelectObjective-mapped

CAPM Practice Question: Project Management Fundamentals and Core Concepts

Which TWO of the following are outputs of the Identify Stakeholders process?

⚠ Common exam trap

PMI often tests the distinction between the Stakeholder Register (the output of Identify Stakeholders) and outputs of later planning or execution processes, such as the Stakeholder Engagement Plan. Stakeholder analysis is a tool and technique used within the process, not an output.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Stakeholder register

Among the listed options, only the Stakeholder Register is an output of the Identify Stakeholders process. Stakeholder analysis is a tool and technique, not an output. Stakeholder Management Plan, Issue Log, and Stakeholder Engagement Plan are outputs of other processes, not Identify Stakeholders.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Stakeholder analysis

    Why it's wrong here

    Incorrect. Stakeholder analysis is a tool and technique of the Identify Stakeholders process, not an output. The output is the Stakeholder Register that captures the analysis results.

  • Stakeholder management plan

    Why it's wrong here

    Incorrect. The Stakeholder Management Plan is an output of Plan Stakeholder Management (now under Planning process group).

  • Issue log

    Why it's wrong here

    Incorrect. The Issue Log is an output of Direct and Manage Project Work (Executing process group) and later updated in Manage Stakeholder Engagement.

  • Stakeholder register

    Why this is correct

    Correct. The Stakeholder Register is the primary output of Identify Stakeholders, listing all identified stakeholders and their key details.

  • Stakeholder engagement plan

    Why it's wrong here

    Incorrect. The Stakeholder Engagement Plan is an output of Plan Stakeholder Engagement (planning process), not Identify Stakeholders.

About these practice questions

This CAPM question is part of Courseiva's 487-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.