Courseiva

CAPM Practice Question: Project Management Fundamentals and Core Concepts

Which TWO of the following are project management process groups?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Closing

The correct answers are B (Closing) and C (Initiating). These are two of the five project management process groups. Scheduling (A), Risk Management (D), and Budgeting (E) are not process groups; they are knowledge areas or other project management terms.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Scheduling

    Why it's wrong here

    Scheduling is a knowledge area, not a process group.

  • Closing

    Why this is correct

    Closing is one of the five process groups.

  • Initiating

    Why this is correct

    Initiating is one of the five process groups.

  • Risk Management

    Why it's wrong here

    Risk management is a knowledge area, not a process group.

  • Budgeting

    Why it's wrong here

    Budgeting is an activity, not a process group.

About these practice questions

Courseiva writes every CAPM question from scratch — 487 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.