Drag and drop the steps for developing a project schedule in the correct order.

Drag steps to the numbered slots on the right, or tap a step then tap a slot.

Steps
Order
1Step 1
2Step 2
3Step 3
4Step 4
5Step 5

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

1. Define activities, 2. Sequence activities, 3. Estimate activity resources, 4. Estimate activity durations, 5. Develop schedule

Schedule development follows: define, sequence, estimate resources and durations, then develop the schedule.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • 1. Define activities, 2. Sequence activities, 3. Estimate activity resources, 4. Estimate activity durations, 5. Develop schedule

    Why this is correct

    This is the correct order according to the PMBOK Guide: first define the activities, then sequence them, estimate the resources needed, estimate the durations for each activity, and finally develop the schedule.

  • 1. Define activities, 2. Sequence activities, 3. Estimate activity durations, 4. Estimate activity resources, 5. Develop schedule

    Why it's wrong here

    This order is incorrect because estimating durations before estimating resources can lead to inaccurate durations, as resource availability affects how long an activity takes. Resources should be estimated first.

  • 1. Define activities, 2. Estimate activity resources, 3. Sequence activities, 4. Estimate activity durations, 5. Develop schedule

    Why it's wrong here

    This order is incorrect because sequencing activities must be done before estimating resources, as the sequence affects resource needs (e.g., resource leveling). Also, estimating durations before sequencing is not logical.

  • 1. Sequence activities, 2. Define activities, 3. Estimate activity resources, 4. Estimate activity durations, 5. Develop schedule

    Why it's wrong here

    This order is incorrect because activities must be defined before they can be sequenced. Defining activities is the first step in the process.

About these practice questions

Courseiva writes every CAPM question from scratch — 487 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.