CAPM Practice Question: Project Management Fundamentals and Core Concepts
Exhibit
{
"wbs": {
"id": "1.0",
"name": "Project",
"children": [
{"id": "1.1", "name": "Planning", "level": 2},
{"id": "1.2", "name": "Execution", "level": 2, "children": [
{"id": "1.2.1", "name": "Develop", "level": 3},
{"id": "1.2.2", "name": "Test", "level": 3}
]},
{"id": "1.3", "name": "Close", "level": 2}
]
}
}Refer to the exhibit. How many work packages are at the lowest level of the WBS?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
2
2. The lowest level of the WBS (level 3) contains two work packages: Develop and Test. Options B, C, and D are incorrect as they do not reflect the actual count.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
2
Why this is correct
Develop and Test are the two work packages at level 3.
- ✗
3
Why it's wrong here
There are only two work packages at the lowest level.
- ✗
0
Why it's wrong here
There are work packages at the lowest level.
- ✗
1
Why it's wrong here
There are two work packages.
Go deeper
Related to this question
About these practice questions
Courseiva writes every CAPM question from scratch — 487 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.