Question 353 of 503

Quick Answer

The answer is to request that the functional managers allocate dedicated resources to the project for its duration. This is the correct solution because in a strong matrix organization, functional managers retain authority over resource assignments, and the root cause of the resource contention is that the operations manager prioritizes urgent operational tasks over project work. The project manager has already attempted negotiation, but without changing the resource allocation model, the conflict will persist. On the CAPM exam, this scenario tests your understanding of how authority is distributed in a strong matrix versus a weak or balanced matrix, where the project manager has more or less control. A common trap is to choose escalation to the sponsor or further negotiation, but the most effective strong matrix resource contention solution is to secure full-time commitment from functional managers. Memory tip: in a strong matrix, think “strong functional manager, strong need for dedicated resources.”

CAPM Practice Question: Project Management Fundamentals and Core Concepts

This CAPM practice question tests your understanding of project management fundamentals and core concepts. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

A manufacturing company is implementing a new ERP system. The project team includes members from IT, finance, and operations. The organization uses a strong matrix structure. Recently, the project has been missing milestones because the operations manager frequently assigns urgent operational tasks to the operations team members, who are also assigned part-time to the project. The project manager has discussed this with the operations manager, but the situation continues. The project sponsor is concerned about the delays and wants a solution within two days. What should the project manager do?

Question 1easymultiple choice
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Request that the functional managers allocate dedicated resources to the project for its duration.

In a strong matrix organization, functional managers retain authority over their team members' assignments. Since the operations manager continues to pull operations staff for urgent tasks despite the project manager's discussion, the root cause is resource availability. The most effective solution is to request dedicated resources from the functional managers, ensuring the project has full-time commitment from key team members and eliminating the conflict that causes milestone delays.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Compress the project schedule by fast-tracking remaining activities.

    Why it's wrong here

    Fast-tracking increases risk and does not resolve the resource availability issue.

  • Request that the functional managers allocate dedicated resources to the project for its duration.

    Why this is correct

    In a strong matrix, the PM can negotiate for dedicated resources to eliminate the conflict.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Escalate the issue to the project sponsor and ask for intervention.

    Why it's wrong here

    Escalation should be a last resort; the PM should first use their authority to request dedicated resources.

  • Document the issue in the issue log and update the risk register.

    Why it's wrong here

    While documentation is important, it does not actively resolve the ongoing resource conflict.

Common exam traps

Common exam trap: answer the scenario, not the keyword

PMI often tests the distinction between passive documentation (issue log/risk register) and active resolution; the trap here is that candidates choose D because it seems like proper process, but it fails to address the immediate need for a solution within two days as requested by the sponsor.

Detailed technical explanation

How to think about this question

In a strong matrix structure, the project manager has significant authority but still relies on functional managers to assign personnel. The PMBOK Guide emphasizes that resource negotiation with functional managers is a key project manager responsibility, and if that fails, the next step is to request dedicated resources to ensure full-time commitment. This approach aligns with the resource management plan and avoids the common pitfall of treating symptoms (schedule delays) rather than the cause (resource contention).

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A small business has 20 workstations on the 192.168.1.0/24 network and one public IP from its ISP. The router uses PAT (NAT overload) so all 20 devices share one public address using different source ports. NAT questions test whether you understand the four address terms and which direction each translation applies.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related CAPM practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free CAPM practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this CAPM question test?

Project Management Fundamentals and Core Concepts — This question tests Project Management Fundamentals and Core Concepts — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Request that the functional managers allocate dedicated resources to the project for its duration. — In a strong matrix organization, functional managers retain authority over their team members' assignments. Since the operations manager continues to pull operations staff for urgent tasks despite the project manager's discussion, the root cause is resource availability. The most effective solution is to request dedicated resources from the functional managers, ensuring the project has full-time commitment from key team members and eliminating the conflict that causes milestone delays.

What should I do if I get this CAPM question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Last reviewed: Jun 30, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.