Risk ID: R1, Probability: 0.3, Impact: $40,000
Risk ID: R2, Probability: 0.6, Impact: $50,000
Risk ID: R3, Probability: 0.2, Impact: $100,000

Refer to the exhibit. Which risk has the highest expected monetary value?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

R2

EMV for R1 = 0.3 * $40,000 = $12,000; R2 = 0.6 * $50,000 = $30,000; R3 = 0.2 * $100,000 = $20,000. R2 has the highest EMV.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • R1

    Why it's wrong here

    EMV is $12,000, lower than R2 and R3.

  • R3

    Why it's wrong here

    EMV is $20,000, lower than R2.

  • All have equal EMV

    Why it's wrong here

    EMVs are different.

  • R2

    Why this is correct

    EMV is $30,000, the highest.

About these practice questions

Courseiva writes every CAPM question from scratch — 487 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.