CAPM Practice Question: Project Management Fundamentals and Core Concepts
Exhibit
{
"risks": [
{"id": "R1", "probability": 0.3, "impact": 0.5},
{"id": "R2", "probability": 0.8, "impact": 0.2},
{"id": "R3", "probability": 0.6, "impact": 0.9},
{"id": "R4", "probability": 0.4, "impact": 0.7}
]
}Refer to the exhibit. Based on the probability and impact values, which risk has the highest risk score?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
R3
R3 has a score of 0.54 (0.6*0.9), which is the highest. R1=0.15, R2=0.16, R4=0.28. Options A, B, and C have lower scores.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
R4
Why it's wrong here
R4 score is 0.28, lower than R3.
- ✗
R1
Why it's wrong here
R1 score is 0.15, lower than R3.
- ✗
R2
Why it's wrong here
R2 score is 0.16, lower than R3.
- ✓
R3
Why this is correct
R3 score is 0.54, the highest.
Go deeper
Related to this question
About these practice questions
One of 487 original CAPM practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.