Question 251 of 503

Quick Answer

The correct action is to apply resource smoothing, which delays some activities in Week 2 to earlier or later weeks. This technique is the right choice because it adjusts non-critical activities within their available float to reduce a resource peak—here, from 15 FTEs down to the 12-FTE limit—without altering the critical path or extending project duration or budget. On the CAPM exam, this question tests your ability to distinguish resource smoothing from resource leveling; the key trap is that leveling would also fix the overload but would likely change the critical path and increase duration, which the scenario explicitly forbids. A strong memory tip is to think of smoothing as “shifting within slack” to stay on schedule, while leveling “levels the load” even if it lengthens the timeline.

CAPM Practice Question: Project Management Fundamentals and Core Concepts

This CAPM practice question tests your understanding of project management fundamentals and core concepts. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

Exhibit

Refer to the exhibit.

Resource Histogram:

Week 1: 10 FTEs
Week 2: 15 FTEs
Week 3: 12 FTEs
Week 4: 8 FTEs

Total available FTEs per week: 12

Cost per FTE: $1000/week

Project budget: $50,000

Refer to the exhibit. The project manager notices that the resource histogram shows a peak of 15 FTEs in Week 2, exceeding the available 12 FTEs. The project manager needs to bring the resource usage within the limit without increasing the project duration or budget. Which action should the project manager take?

Question 1hardmultiple choice
Full question →

Exhibit

Refer to the exhibit.

Resource Histogram:

Week 1: 10 FTEs
Week 2: 15 FTEs
Week 3: 12 FTEs
Week 4: 8 FTEs

Total available FTEs per week: 12

Cost per FTE: $1000/week

Project budget: $50,000

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Apply resource smoothing to delay some activities in Week 2 to earlier or later weeks

Resource smoothing is the correct technique because it adjusts the schedule of activities within their float to level the resource demand without changing the critical path or project duration. In this case, delaying some non-critical activities from Week 2 to earlier or later weeks reduces the peak from 15 FTEs to within the 12-FTE limit while keeping the project duration and budget unchanged.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Reduce the scope of work in Week 2

    Why it's wrong here

    Reducing scope changes the project deliverables and may not be acceptable.

  • Crash the project by adding overtime in Week 2

    Why it's wrong here

    Crashing increases cost, exceeding budget.

  • Add more resources to Week 2 to meet the demand

    Why it's wrong here

    Adding resources increases cost, exceeding budget.

  • Apply resource smoothing to delay some activities in Week 2 to earlier or later weeks

    Why this is correct

    Resource smoothing adjusts activities within their float to keep resource usage within limits without affecting the critical path or duration.

    Related concept

    Read the scenario before looking for a memorised answer.

Common exam traps

Common exam trap: answer the scenario, not the keyword

PMI often tests the distinction between resource smoothing (which does not change duration) and resource leveling (which can extend duration), leading candidates to confuse the two or incorrectly assume that any resource adjustment must increase time or cost.

Detailed technical explanation

How to think about this question

Resource smoothing is a technique in resource optimization that uses float (total or free) to shift activities without delaying the project's finish date. In practice, a project manager must first identify non-critical activities with available float in Week 2, then reschedule them to periods with lower demand, ensuring the critical path remains unchanged. This approach is often automated in tools like Microsoft Project or Primavera P6, where the resource leveling feature can be set to 'smooth' rather than 'level' to avoid extending the schedule.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A small business has 20 workstations on the 192.168.1.0/24 network and one public IP from its ISP. The router uses PAT (NAT overload) so all 20 devices share one public address using different source ports. NAT questions test whether you understand the four address terms and which direction each translation applies.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related CAPM practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free CAPM practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this CAPM question test?

Project Management Fundamentals and Core Concepts — This question tests Project Management Fundamentals and Core Concepts — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Apply resource smoothing to delay some activities in Week 2 to earlier or later weeks — Resource smoothing is the correct technique because it adjusts the schedule of activities within their float to level the resource demand without changing the critical path or project duration. In this case, delaying some non-critical activities from Week 2 to earlier or later weeks reduces the peak from 15 FTEs to within the 12-FTE limit while keeping the project duration and budget unchanged.

What should I do if I get this CAPM question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Last reviewed: Jun 30, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.