Courseiva
Project Management Fundamentals and Core ConceptsmediumMultiple ChoiceObjective-mapped

CAPM Practice Question: Project Management Fundamentals and Core Concepts

A project manager is estimating activity durations. The team provides three estimates: optimistic 10 days, pessimistic 20 days, most likely 14 days. Using the PERT beta distribution, what is the expected duration?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

14.33 days

PERT expected = (O + 4M + P)/6 = (10 + 4*14 + 20)/6 = (10 + 56 + 20)/6 = 86/6 = 14.33 days.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • 14 days

    Why it's wrong here

    This is the most likely estimate, not the PERT expected.

  • 14.67 days

    Why it's wrong here

    This would be (O+M+P)/3 = 44/3 = 14.67, but PERT uses weighted average.

  • 15 days

    Why it's wrong here

    Incorrect calculation.

  • 14.33 days

    Why this is correct

    Correct calculation using the PERT formula.

About these practice questions

Courseiva writes every CAPM question from scratch — 487 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.