PRINCE2 Foundation (PRINCE2F) — Questions 76150

1731 questions total · 24pages · All types, answers revealed

Page 1

Page 2 of 24

Page 3
76
MCQmedium

A project is using PRINCE2's product-based planning. What is the first step in this approach?

A.Create a product breakdown structure
B.Write a product description for each product
C.Estimate the effort and duration for each activity
D.Sequence the activities required to produce the products
AnswerA

This identifies all products needed before other planning steps.

Why this answer

Product-based planning starts with identifying the products (outputs) required, i.e., creating a Product Breakdown Structure.

77
MCQmedium

Which document describes the detailed activities, resources, and costs for a single management stage?

A.Stage Plan
B.Team Plan
C.Project Plan
D.Exception Plan
AnswerA

The Stage Plan details activities, resources, and costs for a specific stage.

Why this answer

The Stage Plan is the detailed plan for each management stage, created at the end of the previous stage.

78
MCQmedium

During which process is the End Project Report produced?

A.Closing a Project
B.Directing a Project
C.Managing a Stage Boundary
D.Initiating a Project
AnswerA

The End Project Report is a key output of Closing a Project.

Why this answer

The End Project Report is produced during Closing a Project. It reviews the project's overall performance and confirms the project has met its objectives.

79
MCQmedium

During a project, the Project Board is informed that a major change to the project scope is required. Which role is best placed to assess the impact on the Business Case?

A.Project Assurance
B.Senior User
C.Team Manager
D.Project Manager
AnswerA

Project Assurance independently assesses impacts on the Business Case and advises the Board.

Why this answer

Project Assurance provides independent assessment of project issues, including impact on the Business Case, to the Project Board.

80
Drag & Dropmedium

Drag and drop the steps to close a project in PRINCE2 into the correct order.

Drag steps to the numbered slots on the right, or tap a step then tap a slot.

Steps
Order

Why this order

Closing a Project involves preparing closure, handing over products, evaluating, recommending closure, and then formally closing.

81
MCQeasy

Which role is responsible for ensuring that the project continues to have business justification?

A.Senior Supplier
B.Senior User
C.Executive
D.Project Manager
AnswerC

The Executive is responsible for business justification.

Why this answer

The Executive (Senior Responsible Owner) is accountable for the Business Case and ensuring the project remains justified.

82
MCQmedium

What is the difference between a Highlight Report and a Checkpoint Report?

A.Highlight Report is from Project Manager to Project Board; Checkpoint Report is from Team Manager to Project Manager
B.Highlight Report is from Team Manager to Project Manager; Checkpoint Report is from Project Manager to Project Board
C.Both are from Project Manager to Project Board
D.Both are from Team Manager to Project Manager
AnswerA

Correct.

Why this answer

A Highlight Report is from the Project Manager to the Project Board; a Checkpoint Report is from the Team Manager to the Project Manager.

83
MCQeasy

A project manager is creating the Project Initiation Documentation. Which document must be produced before the Initiation Stage can be considered complete?

A.Business Case
B.Project Initiation Documentation
C.Project Plan
D.Risk Register
AnswerB

The PID is the main output of the Initiation Stage and must be approved to proceed.

Why this answer

In PRINCE2, the Project Initiation Documentation (PID) is the key deliverable of the Initiation Stage. The stage is not considered complete until the PID has been created and approved, as it provides the foundation for project governance and decision-making. The Business Case, Project Plan, and Risk Register are all components that are assembled into the PID, but the PID itself is the definitive document that marks stage completion.

Exam trap

PeopleCert often tests the misconception that individual components like the Business Case or Project Plan are the final deliverables of the Initiation Stage, when in fact the PID is the overarching document that must be completed and approved.

How to eliminate wrong answers

Option A is wrong because the Business Case is a component of the Project Initiation Documentation, not a separate document that must be produced before the PID; the PID includes the Business Case. Option C is wrong because the Project Plan is also a component within the PID, not a standalone document required to complete the Initiation Stage. Option D is wrong because the Risk Register is a management product that is part of the PID, but the PID as a whole must be completed to close the Initiation Stage.

84
MCQeasy

In PRINCE2, who is responsible for managing the delivery of a Work Package?

A.Team Manager
B.Senior Supplier
C.Project Manager
D.Project Assurance
AnswerA

The Team Manager manages the delivery of Work Packages.

Why this answer

The Team Manager is responsible for managing the delivery of one or more Work Packages as assigned by the Project Manager.

85
MCQhard

During the Managing a Stage Boundary process, the Project Manager produces an End Stage Report. What is the primary purpose of this report?

A.To record lessons learned for future projects
B.To summarize the progress of the current stage and request authorization for the next stage
C.To notify the Project Board of any issues that have occurred during the stage
D.To document the acceptance of all products delivered in the stage
AnswerB

Correct. The End Stage Report is used by the Project Board to decide whether to proceed.

Why this answer

The End Stage Report provides the Project Board with information on the performance of the current stage so they can decide whether to authorize the next stage.

86
MCQhard

During the Controlling a Stage process, the Team Manager reports that a work package is likely to be completed later than planned. The Project Manager assesses that stage tolerances will not be exceeded. What should the Project Manager do?

A.Request a change to the Work Package
B.Update the Project Plan to reflect the delay
C.Raise an Exception Report to the Project Board
D.Take corrective action within the stage tolerance
AnswerD

The PM can manage deviations within tolerance.

Why this answer

Since stage tolerances are not exceeded, the Project Manager can handle the deviation within the stage. Option A is correct.

87
MCQmedium

During the Controlling a Stage process, the Project Manager identifies that the stage's cost tolerance is forecast to be exceeded. According to PRINCE2, what should the Project Manager do?

A.Increase the stage budget using the change budget and continue with the current Stage Plan
B.Close the project immediately as the Business Case is no longer viable
C.Raise an Exception Report to the Project Board and await their direction before proceeding
D.Continue with the current Stage Plan and report the cost overrun in the next Highlight Report
AnswerC

When a stage tolerance is forecast to be exceeded, the Project Manager must escalate to the Project Board via an Exception Report.

Why this answer

When a stage tolerance is forecast to be exceeded, the Project Manager must escalate immediately to the Project Board via an Exception Report. This is the management by exception principle.

88
MCQmedium

During the Controlling a Stage process, the Project Manager identifies that the project is forecast to exceed the agreed cost tolerance for the current stage. What should the Project Manager do?

A.Raise an Exception Report to the Project Board and await their direction before proceeding
B.Close the project immediately as the Business Case is no longer viable
C.Continue with the current Stage Plan and report the cost overrun in the next Highlight Report
D.Increase the project budget to absorb the additional cost and continue with the current Stage Plan
AnswerA

This is the correct escalation procedure.

Why this answer

When a stage tolerance is forecast to be exceeded, the Project Manager must escalate to the Project Board via an Exception Report. This is management by exception.

89
MCQhard

During the Managing a Stage Boundary process, the Project Manager produces an Exception Plan. What triggers the creation of an Exception Plan?

A.The project is closed prematurely
B.The Project Board approves an Exception Report
C.The end of a stage is reached
D.The Project Manager identifies a new risk
AnswerB

An Exception Plan replaces the current stage plan following an Exception Report.

Why this answer

An Exception Plan is created when the Project Board approves an Exception Report, i.e., when a tolerance is forecast to be exceeded.

90
MCQeasy

In PRINCE2, how often does the Project Board typically meet?

A.Daily
B.Monthly
C.Exception-driven
D.Weekly
AnswerC

The Project Board meets when needed, typically at stage boundaries or for exceptions.

Why this answer

In PRINCE2, the Project Board is not a day-to-day management body; it meets only when decisions are needed outside the delegated authority of the Project Manager. The correct frequency is exception-driven, meaning the Board convenes when a stage boundary is reached, an exception report is raised, or the project is ready for closure. This aligns with PRINCE2's principle of management by exception, where the Board's involvement is triggered by specific events rather than a fixed schedule.

Exam trap

The trap here is that candidates often confuse the Project Board's meeting frequency with that of a daily stand-up or weekly team meeting, failing to recognize PRINCE2's core principle of management by exception, which dictates that the Board only convenes when triggered by specific events or stage boundaries.

How to eliminate wrong answers

Option A is wrong because daily meetings would imply hands-on, operational management, which contradicts the Project Board's strategic, governance role in PRINCE2. Option B is wrong because a fixed monthly schedule would force unnecessary meetings even when no decisions are required, violating the management-by-exception principle. Option D is wrong because weekly meetings are too frequent for a board that should only intervene when the Project Manager exceeds tolerances or a stage boundary is reached.

91
MCQhard

During Initiation, the project manager discovers that a key assumption in the Business Case is invalid. What should the PM do first?

A.Ignore the assumption
B.Stop the project
C.Inform the Project Board
D.Update the Business Case
AnswerD

The Business Case must be revised to reflect the reality.

Why this answer

The Business Case is the key driver for the project, and if a fundamental assumption is invalid, the project manager must first update the Business Case to reflect the new reality. This ensures that the project remains viable and that the Project Board can make an informed decision about whether to continue. Updating the Business Case is the correct first step because it provides the basis for any subsequent decisions, such as escalating to the Project Board.

Exam trap

PeopleCert often tests the misconception that the project manager should immediately escalate to the Project Board, but the correct first action is to update the Business Case to provide the Board with the necessary information for a decision.

How to eliminate wrong answers

Option A is wrong because ignoring a key assumption that invalidates the Business Case would be a serious breach of PRINCE2 principles, as the Business Case must remain valid throughout the project. Option B is wrong because stopping the project is a decision reserved for the Project Board, not the project manager, and should only occur after the Business Case has been updated and assessed. Option C is wrong because while informing the Project Board is necessary, the project manager must first update the Business Case to provide the Board with accurate information for their decision.

92
MCQeasy

Which role is responsible for maintaining the Business Case throughout the project?

A.Senior Supplier
B.Project Manager
C.Project Support
D.Executive
AnswerB

The Project Manager is responsible for maintaining the Business Case throughout the project.

Why this answer

The Project Manager maintains the Business Case on behalf of the Executive (Senior Responsible Owner). The Executive owns the Business Case and is accountable for the business justification, but the Project Manager is responsible for day-to-day maintenance.

93
Multi-Selectmedium

Which TWO of the following are acceptable responses to a threat (negative risk)?

Select 2 answers
A.Exploit
B.Avoid
C.Reject
D.Transfer
E.Enhance
AnswersB, D

Correct. Avoid is a threat response.

Why this answer

Avoid and Transfer are valid threat responses. Enhance is for opportunities; Reject is for opportunities.

94
MCQeasy

Who is responsible for maintaining the Business Case throughout the project?

A.Executive
B.Senior User
C.Project Support
D.Project Manager
AnswerD

Correct. The Project Manager maintains the Business Case.

Why this answer

The Project Manager maintains the Business Case on behalf of the Executive. The Executive owns it and ensures it remains viable.

95
MCQeasy

Who is responsible for maintaining the Business Case throughout the project?

A.Project Manager
B.Senior Responsible Owner (SRO/Executive)
C.Project Assurance
D.Senior User
AnswerB

The SRO owns the Business Case and ensures its viability.

Why this answer

The Senior Responsible Owner (SRO/Executive) owns the Business Case and is responsible for ensuring it remains viable throughout the project.

96
MCQeasy

Which role is responsible for managing the delivery of one or more Work Packages?

A.Project Assurance
B.Team Manager
C.Project Manager
D.Senior User
AnswerB

Correct: the Team Manager manages the team's work on Work Packages.

Why this answer

The Team Manager is responsible for coordinating the team to deliver Work Packages as defined by the Project Manager.

97
Multi-Selecthard

Which THREE of the following are true about the role of the Team Manager in PRINCE2?

Select 3 answers
A.Is accountable for the management of the entire stage
B.Manages the delivery of one or more Work Packages
C.Is an optional role in PRINCE2
D.Is a member of the Project Board
E.Reports to the Project Manager on progress
AnswersB, C, E

The Team Manager is responsible for Work Package delivery.

Why this answer

The Team Manager manages the delivery of one or more Work Packages (A), reports to the Project Manager (B), and is an optional role (C). They do not manage the entire stage (D) and are not part of the Project Board (E).

98
Multi-Selectmedium

Which TWO of the following are outputs of the Starting Up a Project process?

Select 2 answers
A.End Project Report
B.Project Brief
C.Project Initiation Documentation
D.Initiation Stage Plan
E.Benefits Management Approach
AnswersB, D

The Project Brief is an output of SU, providing the outline Business Case and project definition.

Why this answer

SU produces the Project Brief, Stage Plan for initiation, and Daily Log. The PID is produced in IP, and the End Project Report is produced in CP.

99
MCQeasy

Which role provides independent assurance to the Project Board that the project is being managed correctly?

A.Project Manager
B.Project Assurance
C.Project Support
D.Team Manager
AnswerB

Project Assurance provides independent oversight to the Project Board.

Why this answer

Project Assurance is independent of the Project Manager and reports to the Project Board.

100
MCQeasy

Which role is responsible for approving the Project Initiation Documentation?

A.Project Board
B.Senior User
C.Project Manager
D.Senior Supplier
AnswerA

The Board as a whole approves the PID.

Why this answer

The Project Board is responsible for approving the Project Initiation Documentation (PID) because it represents the collective authority of the business, user, and supplier interests. The PID formally authorizes the initiation of the project and commits resources, so only the Project Board has the necessary authority to approve it.

Exam trap

PeopleCert often tests the misconception that the Project Manager or a single board member (like the Senior User) can approve the PID, when in fact only the full Project Board has the authority to do so.

How to eliminate wrong answers

Option B (Senior User) is wrong because the Senior User represents the user interests on the Project Board but does not have sole authority to approve the PID; approval requires the full board. Option C (Project Manager) is wrong because the Project Manager creates the PID and presents it to the Project Board for approval, but does not have the authority to approve it themselves. Option D (Senior Supplier) is wrong because the Senior Supplier represents the supplier interests on the Project Board but, like the Senior User, cannot approve the PID alone; the decision is a collective board responsibility.

101
Multi-Selectmedium

Which TWO of the following are outputs of the Initiating a Project process?

Select 2 answers
A.Benefits Management Approach
B.Lessons Report
C.Project Initiation Documentation (PID)
D.Project Brief
E.End Stage Report
AnswersA, C

The Benefits Management Approach is part of the PID and is created during Initiating a Project.

Why this answer

The PID and the Benefits Management Approach are outputs of Initiating a Project. The Project Brief is from Starting Up a Project. The End Stage Report is from Managing a Stage Boundary.

The Lessons Report is from Closing a Project.

102
MCQmedium

A project is in the Initiating a Project process. Which document is the key output of this process?

A.Work Package
B.Project Brief
C.End Stage Report
D.Project Initiation Documentation
AnswerD

Why this answer

The Project Initiation Documentation (PID) is the key output of the Initiating a Project process, consolidating all the management approaches and plans.

103
MCQhard

In the Risk management procedure, what is the difference between a risk owner and a risk actionee?

A.The risk owner identifies the risk; the risk actionee assesses it
B.There is no difference
C.The risk owner is responsible for the budget; the risk actionee is responsible for the schedule
D.The risk owner is accountable for the risk; the risk actionee performs the response actions
AnswerD

Correct distinction.

Why this answer

The risk owner is accountable for managing the risk and ensuring appropriate responses are implemented; the risk actionee carries out specific actions.

104
MCQhard

A project is using the recommended risk management procedure. After identifying a risk, what is the next step?

A.Plan responses
B.Communicate the risk
C.Assess the risk
D.Implement responses
AnswerC

After identification, the risk is assessed in terms of probability and impact.

Why this answer

The recommended risk management procedure steps are: Identify, Assess, Plan, Implement, Communicate. So after Identify, the next step is Assess (evaluate probability and impact).

105
MCQmedium

Who is responsible for maintaining the Business Case throughout the project?

A.Project Manager
B.Senior User
C.Executive
D.Senior Supplier
AnswerC

The Executive is the Senior Responsible Owner and maintains the Business Case.

Why this answer

The Executive (Senior Responsible Owner) owns the Business Case and is responsible for its maintenance.

106
MCQeasy

Who is responsible for appointing the Project Manager?

A.The Project Board
B.The Senior User
C.The Senior Supplier
D.The Change Authority
AnswerA

The Project Board appoints the Project Manager, usually on the recommendation of the Executive.

Why this answer

In PRINCE2, the Project Board is responsible for appointing the Project Manager. This is because the Project Board represents the business, user, and supplier interests and has the authority to delegate day-to-day management to the Project Manager. The Project Board's responsibility includes ensuring the right person is appointed to manage the project on their behalf.

Exam trap

The trap here is that candidates may confuse the Project Board's collective responsibility with the individual roles of Senior User or Senior Supplier, or mistakenly think the Change Authority has broader management powers than it actually does.

How to eliminate wrong answers

Option B is wrong because the Senior User is a member of the Project Board and does not have sole authority to appoint the Project Manager; that responsibility lies with the Project Board as a whole. Option C is wrong because the Senior Supplier, like the Senior User, is a single role on the Project Board and cannot unilaterally appoint the Project Manager. Option D is wrong because the Change Authority is a role responsible for authorizing changes to project baselines, not for appointing the Project Manager.

107
Multi-Selectmedium

Which TWO of the following are types of issue in PRINCE2?

Select 2 answers
A.Threat
B.Request for Change
C.Off-specification
D.Risk
E.Opportunity
AnswersB, C

A Request for Change is a type of issue.

Why this answer

The PRINCE2 issue types are Request for Change, Off-specification, and Problem/Concern. Threat and opportunity are risk types.

108
MCQeasy

Which role chairs the Project Board?

A.Executive (SRO)
B.Project Manager
C.Senior User
D.Senior Supplier
AnswerA

The Executive chairs the Project Board.

Why this answer

The Executive (SRO) chairs the Project Board and is accountable for the project's success.

109
MCQmedium

Who is responsible for producing the Highlight Report?

A.The Team Manager
B.The Senior User
C.The Project Manager
D.The Project Board
AnswerC

The Project Manager produces the Highlight Report during CS to inform the Project Board of progress.

Why this answer

The Project Manager is responsible for producing the Highlight Report in PRINCE2. This report provides the Project Board with a summary of progress against the stage plan, including achievements, next steps, and any issues or risks. It is a key management product defined in the PRINCE2 manual, and its production is a specific responsibility of the Project Manager, not delegated to the Team Manager or others.

Exam trap

The trap here is that candidates often confuse the Highlight Report with the Checkpoint Report, incorrectly assigning the Highlight Report to the Team Manager, but PRINCE2 clearly distinguishes that the Team Manager produces Checkpoint Reports while the Project Manager produces Highlight Reports.

How to eliminate wrong answers

Option A is wrong because the Team Manager is responsible for producing the Checkpoint Reports, which provide detailed progress at the work package level, not the Highlight Report. Option B is wrong because the Senior User is a role on the Project Board responsible for specifying user needs and benefits, not for producing management reports like the Highlight Report. Option D is wrong because the Project Board is the recipient of the Highlight Report and provides direction and decisions; they do not produce it.

110
MCQmedium

Which PRINCE2 principle is being applied when the Project Manager escalates an issue that is outside the stage tolerance?

A.Manage by stages
B.Manage by exception
C.Tailor to suit the project environment
D.Continued business justification
AnswerB

Escalation when tolerances are exceeded is management by exception.

Why this answer

Management by exception means that tolerances are delegated; if they are forecast to be exceeded, the issue is escalated to the next management level.

111
MCQhard

A project is using the 'reduce' response for a threat. What does this mean?

A.The threat is accepted and no action is taken
B.The probability and/or impact of the threat is lowered
C.The threat is avoided by changing the plan
D.The threat is transferred to a third party
AnswerB

Reduce involves proactive measures to decrease probability or impact.

Why this answer

Reduce means taking action to lower the probability or impact of a threat to an acceptable level.

112
MCQeasy

What is the definition of quality in PRINCE2?

A.The highest possible standard achievable
B.Compliance with ISO 9001
C.Zero defects in all deliverables
D.Fit for purpose
AnswerD

Correct. PRINCE2's definition of quality is 'fit for purpose'.

Why this answer

PRINCE2 defines quality as 'fit for purpose', meaning the product meets the stated requirements and is suitable for its intended use, not necessarily the highest possible standard.

113
MCQmedium

Which role is responsible for managing the delivery of a Work Package?

A.Senior User
B.Project Support
C.Team Manager
D.Project Manager
AnswerC

The Team Manager manages the delivery of the Work Package.

Why this answer

The Team Manager is responsible for delivering the Work Package as defined by the Project Manager.

114
MCQmedium

What is the difference between a Request for Change and an Off-specification?

A.A Request for Change proposes a modification to a baselined product; an Off-specification identifies a failure to meet agreed requirements
B.A Request for Change requires approval from the Project Board; an Off-specification requires approval from the Change Authority
C.There is no difference; the terms are interchangeable
D.A Request for Change is always raised by the Project Manager; an Off-specification is raised by the Senior User
AnswerA

This is the correct distinction.

Why this answer

A Request for Change is a proposal for a change to a product that is already baselined, while an Off-specification is something that should have been provided but was not, or is faulty.

115
MCQmedium

The Project Board is considering whether to authorize the next stage. Which document provides the information needed for this decision?

A.End Stage Report
B.Highlight Report
C.Checkpoint Report
D.Exception Report
AnswerA

The End Stage Report is produced at the end of each stage and includes the next stage plan for approval.

Why this answer

The End Stage Report provides a summary of the current stage's performance and the next stage plan for the Board to decide on continuation.

116
MCQhard

A Project Manager is preparing the End Stage Report. The project has experienced a significant issue that required an Exception Plan. How should the End Stage Report reflect this?

A.It should not mention the Exception Plan because the stage completed successfully
B.It should be replaced by the Exception Report
C.It should only report the final budget and schedule, not the details of issues
D.It should include a summary of the issue and the impact of the Exception Plan on the stage
AnswerD

The End Stage Report provides a review of the stage, including any issues and their resolution.

Why this answer

The End Stage Report is a management product that provides a summary of the stage's performance against the plan. When an Exception Plan has been used, the End Stage Report must include a summary of the issue that triggered the exception and the impact of the Exception Plan on the stage's objectives, budget, and schedule. This ensures that the Project Board has a complete picture of the stage's actual performance, including any deviations from the original Stage Plan.

Exam trap

The trap here is that candidates may think an Exception Plan means the stage was 'off plan' and should be hidden, or that the Exception Report replaces the End Stage Report, when in fact the End Stage Report must transparently document the issue and the Exception Plan's impact.

How to eliminate wrong answers

Option A is wrong because the End Stage Report must reflect any significant deviations from the plan, including those that required an Exception Plan; omitting it would hide critical management information. Option B is wrong because the Exception Report is a separate product used to request approval for the Exception Plan, not a replacement for the End Stage Report, which is produced at the end of the stage. Option C is wrong because the End Stage Report must include a summary of issues and their impact, not just the final budget and schedule, to provide a complete performance review.

117
Multi-Selecteasy

Which TWO of the following are responsibilities of the Project Manager?

Select 2 answers
A.Preparing the Project Plan
B.Approving the Business Case
C.Providing independent assurance
D.Managing day-to-day project activities
E.Authorizing Work Packages
AnswersA, D

The PM creates the Project Plan.

Why this answer

The Project Manager is responsible for day-to-day management and preparing the Project Plan. Options A and D are correct. Options B, C, and E are not PM responsibilities.

118
MCQmedium

What is the purpose of the Managing a Stage Boundary process?

A.To plan the entire project before initiation
B.To control day-to-day work during a stage
C.To close the project and evaluate its performance
D.To review the progress of the current stage and request authorization to start the next stage
AnswerD

This is the correct purpose: the Project Board reviews the current stage's results and authorises the next.

Why this answer

Managing a Stage Boundary is the process where the Project Manager prepares the next Stage Plan and updates the Business Case for approval by the Project Board.

119
MCQhard

A project is in its Controlling a Stage process. The Team Manager reports that a Work Package is likely to be completed late. The Project Manager reviews the Stage Plan and sees that stage tolerance is not forecast to be exceeded. What should the Project Manager do?

A.Instruct the Team Manager to continue as planned.
B.Close the stage early.
C.Take corrective action within the tolerances delegated by the Project Board.
D.Escalate to the Project Board via an Exception Report.
AnswerC

The Project Manager can manage within tolerances without escalation.

Why this answer

Since stage tolerance is not threatened, the Project Manager can take corrective action within the delegated tolerances, such as re-planning or re-assigning resources, without escalating to the Project Board.

120
MCQmedium

During the Initiating a Project process, which document is created to define the project's scope, objectives, and how it will be managed?

A.Project Brief
B.Project Initiation Documentation (PID)
C.Business Case
D.Benefits Management Approach
AnswerB

The PID is the comprehensive document created during initiation.

Why this answer

The Project Initiation Documentation (PID) is the definitive document created during the Initiating a Project process. It consolidates the project's scope, objectives, and management controls, serving as the foundation for project governance and decision-making. PRINCE2 mandates the PID to ensure all stakeholders have a single source of truth for how the project will be managed.

Exam trap

PeopleCert often tests the distinction between the Project Brief (created in Starting Up a Project) and the PID (created in Initiating a Project), leading candidates to confuse the two documents and their respective purposes.

How to eliminate wrong answers

Option A is wrong because the Project Brief is created during the Starting Up a Project process, not Initiating a Project, and it provides initial context and justification but does not define detailed management approaches. Option C is wrong because the Business Case is a component of the PID, not a standalone document that defines scope and management; it focuses on justification and benefits. Option D is wrong because the Benefits Management Approach is a separate management product that details how benefits will be realized and measured, but it does not define the project's overall scope or management structure.

121
Multi-Selecthard

Which THREE of the following are activities performed during the Directing a Project process?

Select 3 answers
A.Authorise a Work Package
B.Produce the Highlight Report
C.Authorise a Stage Plan or Exception Plan
D.Authorise initiation
E.Authorise the project
AnswersC, D, E

Why this answer

Directing a Project includes authorising initiation, authorising the project, authorising stage/exception plans, giving ad-hoc direction, and authorising closure. Authorising a Work Package is done by the Project Manager in Controlling a Stage. Highlight Reports are produced by the Project Manager in Controlling a Stage.

122
MCQhard

During the Initiating a Project process, which document is developed as part of the Project Initiation Documentation?

A.Team Plan
B.Benefits Review Plan
C.Project Plan
D.Exception Plan
AnswerC

The Project Plan is a component of the PID.

Why this answer

The PID contains the Project Plan, which is a high-level plan for the entire project. Stage Plans are created in SB, not IP (except the first stage plan).

123
MCQeasy

Which process ensures that the project's products are delivered according to the agreed quality criteria?

A.Initiating a Project
B.Controlling a Stage
C.Directing a Project
D.Managing Product Delivery
AnswerD

MP is the process where teams deliver products according to the quality criteria defined in the Work Package.

Why this answer

Managing Product Delivery is the PRINCE2 process that focuses on the work required to create the project's products and ensures they are delivered according to the agreed quality criteria. It is the process where the team manager accepts work packages, executes the work, and delivers completed products that meet the defined quality standards.

Exam trap

The trap here is confusing the process that plans and monitors quality (Controlling a Stage) with the process that actually executes the work and delivers the product to those quality standards (Managing Product Delivery).

How to eliminate wrong answers

Option A is wrong because Initiating a Project is the process that establishes the project's foundation, including the business case and project plan, but does not directly manage the delivery of products against quality criteria. Option B is wrong because Controlling a Stage is the process that monitors progress and manages issues and risks within a stage, but the actual creation and quality-checking of products is delegated to the team via Managing Product Delivery. Option C is wrong because Directing a Project is the process for the Project Board to make key decisions and provide overall direction, not for the hands-on delivery of products to quality criteria.

124
MCQmedium

What is the purpose of the Quality Register?

A.To record all quality management activities and their results
B.To record all issues raised during the project
C.To record risks to quality
D.To record lessons learned about quality
AnswerA

Correct. It tracks quality checks and approvals.

Why this answer

The Quality Register records all planned quality activities and their results.

125
MCQmedium

During the Controlling a Stage process, the Project Manager identifies that the project is forecast to exceed the agreed cost tolerance for the current stage. What should the Project Manager do?

A.Continue with the current Stage Plan and report the cost overrun in the next Highlight Report
B.Close the project immediately as the Business Case is no longer viable
C.Raise an Exception Report to the Project Board and await their direction before proceeding
D.Increase the project budget to absorb the additional cost and continue with the current Stage Plan
AnswerC

Correct action when tolerance is forecast to be exceeded.

Why this answer

When a stage tolerance is forecast to be exceeded, the Project Manager must escalate to the Project Board via an Exception Report. This is management by exception.

126
Multi-Selectmedium

Which TWO of the following are outputs of the Starting up a Project process?

Select 2 answers
A.Exception Report
B.Project Brief
C.Business Case
D.Stage Plan for the initiation stage
E.Project Initiation Documentation
AnswersB, D

Correct output.

Why this answer

Starting up a Project produces the Project Brief and Stage Plan. The PID is produced in Initiating a Project.

127
MCQmedium

During which process are Work Packages authorised by the Project Manager?

A.Controlling a Stage
B.Managing Product Delivery
C.Managing a Stage Boundary
D.Directing a Project
AnswerA

CS includes authorising Work Packages.

Why this answer

In Controlling a Stage, the PM authorises Work Packages to Team Managers for execution.

128
Multi-Selectmedium

Which THREE of the following are roles that are appointed during the Starting Up a Project process?

Select 3 answers
A.Project Assurance
B.Project Board
C.Team Manager
D.Project Manager
E.Executive
AnswersB, D, E

The Project Board is appointed during Starting Up a Project.

Why this answer

The Executive and Project Manager are appointed during SU, along with the Project Board members. The Team Manager is appointed later.

129
MCQmedium

A project is forecast to exceed its stage cost tolerance. What should the Project Manager do?

A.Continue with the current Stage Plan and report the overrun in the next Highlight Report
B.Increase the project budget and continue with the current Stage Plan
C.Close the project as the Business Case is no longer viable
D.Raise an Exception Report to the Project Board and await their direction
AnswerD

Correct: management by exception requires escalation when tolerances are forecast to be exceeded.

Why this answer

Option D is correct because PRINCE2 mandates that when a project manager forecasts a deviation beyond the stage tolerance, they must escalate the issue to the Project Board via an Exception Report. The Project Board then decides whether to approve an exception plan, adjust tolerance, or close the project. This ensures governance and control over the project's budget and scope.

Exam trap

The trap here is that candidates may think the Project Manager can simply adjust the budget or continue reporting later, but PRINCE2 strictly requires immediate escalation via an Exception Report when tolerance is forecast to be exceeded, emphasizing the principle of management by exception.

How to eliminate wrong answers

Option A is wrong because continuing with the current Stage Plan and reporting the overrun in the next Highlight Report violates the principle of management by exception; the Project Manager must escalate immediately when tolerance is forecast to be exceeded, not wait for the next report. Option B is wrong because the Project Manager does not have authority to increase the project budget; only the Project Board can authorize budget changes, and doing so unilaterally bypasses the escalation process. Option C is wrong because closing the project is a decision reserved for the Project Board based on the Exception Report; the Project Manager cannot unilaterally close the project simply because the stage cost tolerance is forecast to be exceeded, as the Business Case may still be viable with an exception plan.

130
MCQeasy

Which process is responsible for appointing the Executive and the Project Manager?

A.Directing a Project
B.Starting Up a Project
C.Managing a Stage Boundary
D.Initiating a Project
AnswerB

Correct. The Executive and Project Manager are appointed during Starting Up a Project.

Why this answer

The Starting Up a Project (SU) process is the pre-project process where the Executive and Project Manager are appointed. This ensures the necessary roles are in place before the project is formally initiated.

131
MCQeasy

Who is responsible for ensuring that the project's business case remains viable throughout the project?

A.Project Manager
B.Executive
C.Senior User
D.Project Board
AnswerB

The Executive is responsible for the Business Case throughout the project.

Why this answer

The Executive (Senior Responsible Owner) is responsible for the Business Case. The Project Manager maintains it day-to-day, but the Executive owns it.

132
MCQmedium

Which level of plan in PRINCE2 is produced during the Initiating a Project process?

A.Exception Plan
B.Team Plan
C.Stage Plan
D.Project Plan
AnswerD

The Project Plan is created during Initiating a Project.

Why this answer

Option A is correct. The Project Plan is created during Initiating a Project. Stage Plans are created during Managing a Stage Boundary; Team Plans are created by the Team Manager; Exception Plans are created when tolerances are exceeded.

133
Matchingmedium

Match each PRINCE2 process to its purpose.

Drag a concept onto its matching description — or click a concept then click the description.

Concepts
Matches

Ensures that the prerequisites for initiating a project are in place.

Enables the Project Board to make key decisions and exercise overall control.

Establishes solid foundations for the project.

Assigns work to teams and monitors progress.

Controls the link between the project manager and the team managers.

Why these pairings

The seven processes are these five plus 'Managing a Stage Boundary' and 'Closing a Project'.

134
Multi-Selectmedium

Which TWO of the following are components of the Business Case?

Select 2 answers
A.Product descriptions
B.Expected benefits
C.Project plan
D.Risk register
E.Major risks
AnswersB, E

Expected benefits are a key component.

Why this answer

The Business Case includes reasons, options, expected benefits, dis-benefits, timescale, costs, investment appraisal, and major risks.

135
MCQeasy

Who chairs the Project Board in PRINCE2?

A.Senior Responsible Owner (Executive)
B.Senior Supplier
C.Senior User
D.Project Manager
AnswerA

The SRO/Executive chairs the Project Board.

Why this answer

In PRINCE2, the Project Board is chaired by the Executive (also known as the Senior Responsible Owner in many organizations). The Executive is ultimately accountable for the project's success, provides business justification, and ensures the project remains viable. The chairperson role is explicitly assigned to the Executive in the PRINCE2 management structure, not to the Senior Supplier, Senior User, or Project Manager.

Exam trap

The trap here is that candidates often confuse the Project Manager as the chair because they lead project meetings, but PRINCE2 explicitly assigns the Project Board chair to the Executive, not the Project Manager.

How to eliminate wrong answers

Option B (Senior Supplier) is wrong because the Senior Supplier represents the interests of those providing the project's products and resources, but does not chair the Project Board; they are a board member, not the chair. Option C (Senior User) is wrong because the Senior User represents the users' needs and operational requirements, but they are also a board member without the chairing authority. Option D (Project Manager) is wrong because the Project Manager is responsible for day-to-day management and reporting to the Project Board, but they are not a member of the board and certainly do not chair it.

136
MCQhard

What is the difference between a Request for Change (RFC) and an Off-specification (Off-spec)?

A.An RFC is raised by the Project Manager; an Off-spec is raised by the Project Board
B.An RFC affects the Business Case; an Off-spec does not
C.There is no difference; the terms are interchangeable
D.An RFC is a request for a change to an agreed product; an Off-spec is a product that does not meet its specification
AnswerD

This correctly distinguishes the two.

Why this answer

In PRINCE2, a Request for Change (RFC) is a formal proposal to change any baselined product, while an Off-specification (Off-spec) is a product that has been identified as not meeting its agreed specification. Option D correctly captures this distinction: an RFC seeks a change to an agreed product, whereas an Off-spec reports a deviation from the specification. This is a fundamental difference in issue handling within PRINCE2's change control approach.

Exam trap

The trap here is that candidates often assume RFCs and Off-specs are the same or that only certain roles can raise them, but PRINCE2 explicitly distinguishes them by purpose and allows any stakeholder to raise either type of issue.

How to eliminate wrong answers

Option A is wrong because both RFCs and Off-specs can be raised by any project stakeholder, not exclusively by the Project Manager or Project Board. Option B is wrong because an Off-spec can affect the Business Case if the deviation impacts costs, benefits, or risks, just as an RFC can. Option C is wrong because the terms are not interchangeable; they represent distinct types of issues with different purposes and handling procedures.

137
Multi-Selectmedium

Which TWO of the following are elements of a Work Package?

Select 2 answers
A.The product description(s) to be delivered
B.The Business Case
C.The reporting requirements for the Work Package
D.The project's risk register
E.The composition of the project team
AnswersA, C

Work Packages include the description of the products to be produced.

Why this answer

A Work Package includes the product description(s) to be produced and the reporting requirements (e.g., Checkpoint Reports). The Business Case is not part of a Work Package; it is a project-level document. The team's composition is defined in the Project Plan, not in the Work Package.

138
Multi-Selectmedium

Which THREE of the following are responsibilities of the Senior Supplier on the Project Board?

Select 3 answers
A.Providing the necessary resources and expertise for the project
B.Managing the project budget
C.Defining user acceptance criteria
D.Ensuring that the supplier's products meet the required quality standards
E.Advising on the design and feasibility of supplier solutions
AnswersA, D, E

The Senior Supplier secures supplier resources.

Why this answer

The Senior Supplier is responsible for providing supplier resources, ensuring the quality of supplier deliverables, and advising on design and feasibility. The Senior Supplier does not define user acceptance criteria (that's the Senior User) nor manage the project budget (that's the SRO/Executive).

139
MCQhard

During the Controlling a Stage process, a Team Manager reports that a Work Package is behind schedule. What should the Project Manager do first?

A.Raise an Exception Report to the Project Board
B.Issue a Change Request to modify the Work Package
C.Review the situation and, if within tolerance, approve corrective action
D.Approve an extension to the Work Package
AnswerC

Correct; the PM manages within tolerance.

Why this answer

The Project Manager should assess the situation and decide whether to escalate based on tolerance. If it's within tolerance, they can approve corrective action.

140
MCQhard

What is the difference between Starting Up a Project (SU) and Initiating a Project (IP)?

A.SU is performed by the Project Board, while IP is performed by the Project Manager
B.SU occurs after IP to close the project
C.SU produces the Project Initiation Documentation, while IP produces the Project Brief
D.SU is a pre-project process to determine viability, while IP formally establishes the project foundation
AnswerD

SU ensures prerequisites are in place; IP creates the PID and detailed plans.

Why this answer

SU is a pre-project process to determine if the project is viable before committing resources to full initiation. IP formally establishes the project with detailed plans and management approaches. Both produce documents, but SU produces the Project Brief, and IP produces the PID.

SU does not produce the PID.

141
MCQeasy

Which role is responsible for maintaining the Business Case throughout the project?

A.Project Assurance
B.Executive
C.Senior User
D.Project Manager
AnswerB

The Executive owns the Business Case and is responsible for its maintenance.

Why this answer

The Executive (Senior Responsible Owner) is responsible for the Business Case. The Project Manager develops and maintains it, but ultimately the Executive owns it.

142
Multi-Selectmedium

Which THREE of the following are responsibilities of the Project Manager?

Select 3 answers
A.Provide independent assurance to the Project Board
B.Set project tolerances
C.Prepare the Stage Plan for approval
D.Manage the project on a day-to-day basis
E.Manage risks and issues
AnswersC, D, E

The PM prepares stage plans.

Why this answer

Option C is correct because the Project Manager is responsible for preparing the Stage Plan for approval by the Project Board. This is a key task in the PRINCE2 'Planning' process, where the Project Manager develops detailed plans for each management stage based on the Project Plan and stage-level tolerances.

Exam trap

The trap here is confusing the Project Manager's role with that of the Project Board or Project Assurance, leading candidates to incorrectly select 'Set project tolerances' (a board responsibility) or 'Provide independent assurance' (an assurance responsibility) instead of focusing on the manager's operational duties.

143
MCQeasy

What is the purpose of the Highlight Report?

A.To report progress from Project Manager to Project Board
B.To close the project
C.To report progress from Team Manager to Project Manager
D.To escalate exceptions from Project Manager to Project Board
AnswerA

The Highlight Report is sent by the Project Manager to the Project Board.

Why this answer

The Highlight Report is a regular report from the Project Manager to the Project Board, providing a summary of progress and exceptions for the last reporting period.

144
Multi-Selectmedium

Which TWO of the following are responsibilities of the Project Board?

Select 2 answers
A.Approving the Stage Plan for the next stage
B.Preparing the Highlight Report
C.Maintaining the Business Case
D.Managing the delivery of Work Packages
E.Authorizing deviations from stage tolerances
AnswersA, E

The Board approves Stage Plans.

Why this answer

The Project Board is responsible for authorizing the project, providing direction, and making key decisions. Option A (approve stage plans) and Option C (authorize deviations from stage tolerances) are Board responsibilities. Option B (manage Work Packages) is Team Manager; Option D (prepare Highlight Reports) is PM; Option E (maintain the Business Case) is PM with SRO accountability.

145
MCQmedium

In PRINCE2, which document is used to record quality activities and their results?

A.Project Plan
B.Quality Register
C.Quality Management Strategy
D.Product Description
AnswerB

The Quality Register records quality activities and outcomes.

Why this answer

The Quality Register is a log of all planned quality checks and their results.

146
MCQmedium

During the Managing Product Delivery process, the Team Manager identifies a problem with the quality criteria for a work package. What should the Team Manager do?

A.Raise an issue to the Project Manager
B.Escalate directly to the Project Board
C.Reject the work package and stop work
D.Revise the quality criteria and continue
AnswerA

Correct: the Team Manager communicates issues to the Project Manager.

Why this answer

The Team Manager should raise an issue to the Project Manager, who then decides on the appropriate action (e.g., Request for Change or Off-specification).

147
MCQmedium

Which product is produced during the Starting Up a Project process?

A.End Stage Report
B.Exception Report
C.Project Initiation Documentation
D.Project Brief
AnswerD

The Project Brief is produced in Starting Up a Project.

Why this answer

The Project Brief is the key output of SU. The PID is produced during IP.

148
MCQeasy

In PRINCE2, what does 'fit for purpose' mean in the context of quality?

A.The product is suitable for its intended use
B.The product exceeds customer expectations
C.The product meets all specified requirements exactly
D.The product is free from defects
AnswerA

This is the definition of fit for purpose in PRINCE2.

Why this answer

PRINCE2 defines quality as 'fit for purpose', meaning the product meets its stated requirements and user needs, not necessarily perfection.

149
MCQmedium

What is the purpose of the Managing a Stage Boundary process?

A.To plan the next stage and review the Business Case
B.To close the project
C.To manage the day-to-day activities of a stage
D.To initiate the project
AnswerA

Correct. The process produces an End Stage Report, next Stage Plan, and updated Business Case.

Why this answer

Managing a Stage Boundary provides the Project Board with information to approve the next stage, review the Business Case, and update the project plan.

150
MCQmedium

Which role is responsible for managing the delivery of Work Packages and reporting progress to the Project Manager?

A.Project Manager
B.Senior Supplier
C.Team Manager
D.Project Support
AnswerC

Correct role.

Why this answer

In PRINCE2, the Team Manager is responsible for managing the delivery of Work Packages and reporting progress to the Project Manager. This role ensures that the products defined in the Work Package are created to the required quality, within time and cost constraints, and provides regular progress reports to the Project Manager.

Exam trap

The trap here is that candidates often confuse the Team Manager with the Project Manager, assuming the Project Manager directly manages all work, but PRINCE2 explicitly separates these roles to enable delegation and management by exception.

How to eliminate wrong answers

Option A is wrong because the Project Manager is responsible for overall project management, not for the direct delivery of Work Packages; they delegate that to the Team Manager. Option B is wrong because the Senior Supplier represents the supplier interests on the Project Board and is not involved in day-to-day Work Package delivery or progress reporting to the Project Manager. Option D is wrong because Project Support provides administrative and advisory services, such as maintaining registers and providing planning support, but does not manage Work Packages or report progress on their delivery.

Page 1

Page 2 of 24

Page 3