PRINCE2 Foundation (PRINCE2F) — Questions 601675

1731 questions total · 24pages · All types, answers revealed

Page 8

Page 9 of 24

Page 10
601
MCQeasy

What is the purpose of the Business Case practice?

A.To define the project's scope and deliverables
B.To establish mechanisms to judge whether the project is desirable, viable, and achievable
C.To monitor and control project progress
D.To assign roles and responsibilities to the project team
AnswerB

This is the core purpose of the Business Case practice.

Why this answer

The Business Case practice in PRINCE2 provides a mechanism to judge whether the project is desirable (benefits outweigh costs), viable (achievable within constraints), and achievable (feasible with available resources). It is the central justification for initiating and continuing the project, ensuring ongoing business justification throughout the project lifecycle.

Exam trap

PeopleCert often tests the distinction between the Business Case practice (which justifies the project) and the Plans practice (which defines how the project will be executed), leading candidates to confuse scope definition with business justification.

How to eliminate wrong answers

Option A is wrong because defining the project's scope and deliverables is the purpose of the Product Description and Project Plan, not the Business Case practice. Option C is wrong because monitoring and controlling project progress is the role of the Progress practice, which uses tolerances and reporting. Option D is wrong because assigning roles and responsibilities is the function of the Organization practice, which defines the project management team structure.

602
MCQeasy

Which of the following is a characteristic of a project?

A.Ongoing operations
B.Unique output
C.Permanent team structure
D.Repetitive processes
AnswerB

Correct.

Why this answer

Projects are temporary, produce unique outputs, and require cross-functional teams.

603
MCQhard

What is the difference between a Request for Change (RFC) and an Off-specification (Off-spec)?

A.An RFC is a deviation from the original specification; an Off-spec is a suggestion for improvement
B.There is no difference; they are both types of issues
C.An RFC is a proposal for a change that would enhance a product; an Off-spec is a deviation from the specification
D.An RFC is used to update the Stage Plan; an Off-spec is used to update the Business Case
AnswerC

RFC proposes improvement; Off-spec identifies a failure to meet the specification.

Why this answer

An RFC is a proposal for a change to a baselined product that would improve it; an Off-spec is something that should be provided but is not, or is defective. Option A is correct. Option B reverses the definitions.

Option C is incorrect because neither is a stage plan. Option D is incorrect because both are issues.

604
MCQeasy

Which process is used by the Project Manager to assign work to the Team Manager?

A.Managing Product Delivery
B.Initiating a Project
C.Controlling a Stage
D.Directing a Project
AnswerC

Correct. The Project Manager authorises Work Packages in Controlling a Stage.

Why this answer

The Controlling a Stage process includes the activity of authorising Work Packages, which are formal agreements to produce products. The Project Manager assigns work packages to the Team Manager.

605
MCQeasy

What is the purpose of the Managing a Stage Boundary process?

A.To review the current stage and plan the next stage
B.To control the work within a stage
C.To close the project
D.To produce the Project Initiation Documentation
AnswerA

Managing a Stage Boundary prepares the End Stage Report and next Stage Plan for approval.

Why this answer

The purpose is to provide the Project Board with information to review current stage, approve next stage plan, and update the Business Case.

606
MCQmedium

Which document is the key output of the Initiating a Project process?

A.The Stage Plan
B.The Business Case
C.The Project Plan
D.The Project Initiation Documentation
AnswerD

The PID is the comprehensive document that defines the project and is the key output of Initiating a Project.

Why this answer

The Project Initiation Documentation (PID) is the key output of Initiating a Project. Option D is correct.

607
Multi-Selecteasy

Which TWO of the following are types of issue in PRINCE2?

Select 2 answers
A.Problem
B.Threat
C.Request for Change
D.Quality review
E.Off-specification
AnswersC, E

An RFC is a type of issue.

Why this answer

PRINCE2 defines three issue types: Request for Change, Off-specification, and Problem/Concern. Option B and D are correct. Option A is a risk type, not an issue.

Option C is a general term. Option E is a quality activity.

608
Multi-Selectmedium

Which TWO of the following are true about the Senior Responsible Owner (Executive) role?

Select 2 answers
A.Can be shared between two people
B.Accountable for the project's success
C.Is a member of the project team, not the Project Board
D.Owns the Business Case
E.Responsible for day-to-day management
AnswersB, D

The SRO has ultimate accountability.

Why this answer

The SRO is accountable for the project and owns the Business Case. Options A and C are correct. Option B is false; the SRO does not manage day-to-day.

Option D is false; the SRO is a single role. Option E is false; the SRO is a board member.

609
MCQeasy

Who is responsible for maintaining the Business Case throughout the project?

A.The Executive
B.The Senior User
C.The Project Manager
D.The Project Board
AnswerA

The Executive is the single point of accountability for the Business Case.

Why this answer

The Executive (Senior Responsible Owner) owns the Business Case and is ultimately responsible for its maintenance. The Project Manager may assist but is not the owner.

610
Multi-Selectmedium

Which TWO of the following are outputs of the Starting Up a Project process?

Select 2 answers
A.Benefits Management Approach
B.Project Brief
C.Project Initiation Documentation
D.Risk Management Approach
E.Daily Log
AnswersB, E

The Project Brief is created in SU to provide a foundation for the project.

Why this answer

The Starting Up a Project process outputs the Project Brief, Daily Log, initiation Stage Plan, and appoints the Executive and Project Manager. The Risk Management Approach is developed later in Initiating a Project.

611
MCQmedium

Which of the following is NOT a benefit of adopting PRINCE2?

A.Clear definition of roles and responsibilities
B.Automatic project success
C.Focus on business justification
D.Improved stakeholder communication
AnswerB
612
Multi-Selectmedium

Which THREE of the following are defined roles in PRINCE2?

Select 3 answers
A.Technical Lead
B.Team Manager
C.Project Manager
D.Senior User
E.Project Sponsor
AnswersB, C, D

Correct.

Why this answer

Option B (Team Manager) is correct because PRINCE2 defines the Team Manager role as the person responsible for the team's work and for delivering the products within the team plan. This role is distinct from the Project Manager and is formally defined in the PRINCE2 management structure.

Exam trap

PeopleCert often tests the distinction between PRINCE2's defined roles and common industry job titles, so candidates mistakenly select 'Technical Lead' or 'Project Sponsor' because they are familiar from other frameworks, but PRINCE2 does not include them.

613
Multi-Selecthard

Which THREE of the following are responsibilities of the Project Board in PRINCE2?

Select 3 answers
A.Authorizing the start of each stage
B.Approving the Stage Plans
C.Authorizing work packages
D.Providing overall direction and guidance
E.Day-to-day management of the project
AnswersA, B, D

The Board authorizes stage boundaries.

Why this answer

The Project Board provides overall direction, approves stage plans, and authorizes stage boundaries. Day-to-day management and work package authorization are PM responsibilities.

614
MCQhard

What is the difference between a Request for Change (RFC) and an Off-specification (Off-spec)?

A.An RFC is always approved; an Off-spec is always rejected
B.An RFC relates to cost; an Off-spec relates to quality
C.An RFC is initiated by the Project Manager; an Off-spec is initiated by the Team Manager
D.An RFC is a proposal for a change; an Off-spec is a deviation from specification
AnswerD

Correct.

Why this answer

An RFC is a proposal for a change to a baselined product, while an Off-spec is a deviation from the specification found during quality inspection.

615
MCQeasy

Which register records all identified risks and their status?

A.Issue Register
B.Lessons Log
C.Quality Register
D.Risk Register
AnswerD

The Risk Register is the correct register for risks.

Why this answer

The Risk Register is the repository for all risk management information throughout the project.

616
MCQeasy

Which PRINCE2 principle emphasizes that a project should have continued business justification?

A.Manage by Stages
B.Learn from Experience
C.Continued Business Justification
D.Focus on Products
AnswerC

This principle ensures the project remains justified.

Why this answer

Continued Business Justification is one of the seven PRINCE2 principles, ensuring the project remains viable throughout.

617
MCQmedium

A project is being executed in a stage. The Team Manager reports that a Work Package is likely to exceed its tolerances. What should the Project Manager do first?

A.Assess the situation and consider corrective actions within the stage tolerance
B.Immediately raise an Exception Report to the Project Board
C.Inform the Project Board at the next Highlight Report
D.Request the Team Manager to continue and monitor the situation
AnswerA

The Project Manager first tries to resolve within their delegated authority.

Why this answer

According to PRINCE2, when a Team Manager reports that a Work Package is likely to exceed its tolerances, the Project Manager must first assess the situation and consider corrective actions within the stage tolerance. This is because the Project Manager has delegated authority to manage the stage within the agreed stage tolerances, and only if the forecast exceeds those tolerances should an Exception Report be raised to the Project Board. The correct first step is always to evaluate whether the issue can be resolved within the existing tolerance limits before escalating.

Exam trap

PeopleCert often tests the misconception that any forecast deviation requires immediate escalation to the Project Board, when in fact the Project Manager must first assess whether the issue can be resolved within the existing stage tolerance.

How to eliminate wrong answers

Option B is wrong because immediately raising an Exception Report is premature; the Project Manager must first determine if the deviation can be managed within the stage tolerance. Option C is wrong because waiting for the next Highlight Report would delay necessary action and violates the principle of management by exception, which requires timely escalation when tolerances are forecast to be exceeded. Option D is wrong because simply asking the Team Manager to continue monitoring without assessment abdicates the Project Manager's responsibility to proactively manage deviations and take corrective action.

618
Multi-Selectmedium

Which THREE of the following are components of the Project Initiation Documentation (PID)?

Select 3 answers
A.Business Case
B.Risk Register
C.Benefits Review Plan
D.Project Plan
E.Project Brief
AnswersA, B, D

The Business Case is a key component of the PID.

Why this answer

The PID includes the Business Case, Project Plan, and Risk Register. The Project Brief is a predecessor document, and the Benefits Review Plan is a separate document.

619
MCQhard

What is the difference between Project Assurance and quality review?

A.There is no difference; they are synonymous terms
B.Project Assurance only occurs at the end of a stage, while quality review occurs continuously
C.Project Assurance is a role that provides independent oversight, while a quality review is a technique used to assess product quality
D.Project Assurance is performed by the Project Manager, while quality review is performed by the Team Manager
AnswerC

This correctly distinguishes the ongoing assurance role from the specific review technique.

Why this answer

Project Assurance is an independent role that provides ongoing assurance to the Project Board, while a quality review is a specific technique for reviewing products. Option B is correct.

620
MCQmedium

Which risk response is appropriate for a threat with high probability and high impact that cannot be reduced?

A.Accept
B.Avoid
C.Transfer
D.Fallback
AnswerD

Fallback provides a plan to deal with the risk if it occurs, suitable when reduction is not possible.

Why this answer

Fallback is used when a response plan is implemented only if the risk occurs, often after other responses have failed or are not feasible.

621
MCQmedium

What is the first step in the PRINCE2 recommended risk management procedure?

A.Plan
B.Assess
C.Implement
D.Identify
AnswerD

Identify is the first step.

Why this answer

The risk management procedure starts with 'Identify' risks, followed by Assess, Plan, Implement, and Communicate.

622
MCQeasy

Who is responsible for ensuring that the products are delivered in accordance with the Work Package?

A.The Team Manager
B.The Project Assurance
C.The Senior Supplier
D.The Project Manager
AnswerA

The Team Manager executes the Work Package and ensures products are delivered as defined.

Why this answer

The Team Manager is responsible for accepting and delivering Work Packages, ensuring that products meet quality criteria.

623
MCQmedium

What is the PRINCE2 definition of quality?

A.Customer satisfaction
B.Fit for purpose
C.Conformance to specification
D.Zero defects
AnswerB

PRINCE2 defines quality as fit for purpose.

Why this answer

PRINCE2 defines quality as 'fit for purpose', meaning the product must meet its stated requirements and satisfy user needs.

624
MCQhard

A project is in the Managing a Stage Boundary process. Which of the following is produced during this process?

A.Exception Report
B.End Stage Report
C.Highlight Report
D.Project Brief
AnswerB

End Stage Report is produced in SB.

Why this answer

The End Stage Report is produced to report on the current stage's performance.

625
MCQeasy

Who is responsible for maintaining the Business Case throughout the project?

A.Project Manager
B.Project Support
C.Senior User
D.Executive
AnswerA

The Project Manager maintains the Business Case under the direction of the Executive.

Why this answer

The Project Manager is responsible for maintaining the Business Case as part of day-to-day management. The Executive (SRO) owns and approves it.

626
MCQmedium

A Project Manager is planning the next stage. Which process provides the mechanism for the Project Board to review progress and authorize the next stage?

A.Managing a Stage Boundary
B.Initiating a Project
C.Directing a Project
D.Controlling a Stage
AnswerA

SB provides the report and plan for Board decision.

Why this answer

Managing a Stage Boundary is the process where the PM presents an End Stage Report and next Stage Plan to the Board for approval.

627
MCQmedium

Who is responsible for providing assurance that the project is being conducted properly?

A.Project Support
B.Team Manager
C.Project Board through Project Assurance
D.Project Manager
AnswerC

The Project Board delegates assurance to independent Project Assurance roles.

Why this answer

Project Assurance is an independent role from the Project Board, responsible for monitoring compliance with standards and providing objective oversight.

628
MCQmedium

What is the purpose of the Managing a Stage Boundary process?

A.To enable the Project Board to review the current stage and authorize the next
B.To close the project
C.To manage the day-to-day activities of a stage
D.To initiate the project
AnswerA

Correct.

Why this answer

The purpose is to provide the Project Board with information to review the current stage and authorize the next stage.

629
MCQmedium

Why does PRINCE2 separate the Project Manager role from Project Assurance?

A.To ensure independent oversight and avoid conflicts of interest
B.To allow the Project Manager to focus on team management
C.To comply with corporate governance regulations
D.To reduce the workload of the Project Manager
AnswerA

Correct. Independence is key.

Why this answer

PRINCE2 separates the Project Manager role from Project Assurance to ensure independent oversight and avoid conflicts of interest. The Project Manager is responsible for day-to-day management and decision-making, while Project Assurance provides an objective check that the project remains aligned with business, user, and supplier interests. This separation prevents the Project Manager from being the sole judge of their own work, which could compromise governance and control.

Exam trap

The trap here is that candidates often confuse role separation with workload management or team focus, but PRINCE2 specifically mandates independence to prevent the Project Manager from having unchecked authority over project governance.

How to eliminate wrong answers

Option B is wrong because PRINCE2 does not separate roles to allow the Project Manager to focus on team management; team management is a separate responsibility often delegated to Team Managers, and the separation is about independent oversight, not workload focus. Option C is wrong because while PRINCE2 supports corporate governance, the separation is a structural principle of the method itself, not a direct compliance requirement with external regulations. Option D is wrong because reducing the Project Manager's workload is not the primary reason; the separation is about ensuring objective assurance, not simply offloading tasks.

630
Multi-Selecthard

Which THREE of the following are components of the Project Initiation Documentation (PID)?

Select 3 answers
A.Highlight Report
B.Business Case
C.Risk Register
D.Project Plan
E.Checkpoint Report
AnswersB, C, D

The Business Case is a key component of the PID.

Why this answer

The PID includes the Project Plan, Business Case, and Risk Register (among others).

631
MCQmedium

In the Directing a Project process, when does the project board authorize the project?

A.At the end of the Starting Up a Project process
B.At the end of the Initiating a Project process
C.At the end of the Managing a Stage Boundary process
D.At the end of the first stage
AnswerB

Correct. The Board authorizes the project (full funding) based on the PID.

Why this answer

The Board authorizes the project after reviewing the PID, which is produced in IP. This is the 'authorize the project' activity in DP.

632
MCQhard

A project is in the Managing Product Delivery process. A team member identifies a quality issue with a product being developed. Who is responsible for producing a Checkpoint Report?

A.Team Manager
B.Senior User
C.Project Manager
D.Project Support
AnswerA

Team Manager is responsible for Checkpoint Reports in MP.

Why this answer

In the Managing Product Delivery process, the Team Manager is responsible for producing the Checkpoint Report. This report provides the Project Manager with progress information on the work packages assigned to the team, including any issues such as quality problems. The Checkpoint Report is a key control document that the Team Manager uses to communicate status at regular intervals, typically weekly.

Exam trap

PeopleCert often tests the distinction between who produces a report versus who receives it; the trap here is that candidates may incorrectly assign the Checkpoint Report to the Project Manager because they associate reporting with project-level control, but PRINCE2 explicitly assigns this to the Team Manager for work package-level reporting.

How to eliminate wrong answers

Option B (Senior User) is wrong because the Senior User is responsible for specifying the user requirements and ensuring the product meets those needs, not for producing operational progress reports like the Checkpoint Report. Option C (Project Manager) is wrong because the Project Manager receives the Checkpoint Report from the Team Manager to monitor stage progress, but does not produce it themselves. Option D (Project Support) is wrong because Project Support provides administrative and advisory services, such as maintaining registers or assisting with reports, but the responsibility for producing the Checkpoint Report lies with the Team Manager as part of their role in managing the work package.

633
MCQhard

During a quality review, it is discovered that the acceptance criterion 'The system shall be compatible with Windows 10 and macOS' has been classified as 'Should' (i.e., a desirable but not essential criterion). Which action should be taken?

A.Remove the criterion from the Project Product Description.
B.Ignore the issue because the criterion is already documented.
C.Reclassify it as 'Must' to ensure delivery.
D.Seek confirmation from the customer that the classification is acceptable.
AnswerD

The customer should agree on the priority of acceptance criteria.

Why this answer

In PRINCE2, the classification of acceptance criteria (e.g., 'Must', 'Should', 'Could') is a customer decision. When a criterion classified as 'Should' is discovered during a quality review, the correct action is to seek confirmation from the customer that the classification is acceptable, as only the customer can decide whether a desirable criterion can be downgraded or reclassified. This ensures the project remains aligned with customer expectations and avoids unauthorized changes to the Project Product Description.

Exam trap

The trap here is that candidates may assume the project manager or quality review team has the authority to reclassify criteria, but PRINCE2 emphasizes that acceptance criteria are customer-defined and any change must be formally agreed with the customer.

How to eliminate wrong answers

Option A is wrong because removing the criterion from the Project Product Description without customer approval would be an unauthorized change, violating the change control process. Option B is wrong because ignoring the issue fails to address the potential misclassification, which could lead to customer dissatisfaction if the criterion is later expected to be delivered. Option C is wrong because reclassifying it as 'Must' without customer confirmation would be a unilateral decision that could increase scope and cost without agreement, breaking the principle of continued business justification.

634
MCQmedium

Which PRINCE2 principle is applied when a Project Manager escalates a forecast tolerance deviation to the Project Board?

A.Manage by stages
B.Focus on products
C.Manage by exception
D.Continued business justification
AnswerC

Correct. Escalating when tolerances are breached is management by exception.

Why this answer

Management by Exception means that deviations within tolerance are handled by the PM, but deviations forecast to exceed tolerance are escalated to the Board.

635
MCQmedium

A project is forecast to exceed its stage cost tolerance. What should the Project Manager do?

A.Close the project immediately as the Business Case is no longer viable
B.Increase the project budget to absorb the additional cost and continue with the current Stage Plan
C.Raise an Exception Report to the Project Board and await their direction before proceeding
D.Continue with the current Stage Plan and report the cost overrun in the next Highlight Report
AnswerC

This is the correct action per PRINCE2's management by exception.

Why this answer

When a tolerance is forecast to be exceeded, the Project Manager must escalate to the Project Board via an Exception Report to seek direction.

636
MCQmedium

Which document describes the quality criteria and acceptance methods for a product in PRINCE2?

A.Product Description
B.Quality Management Strategy
C.Project Product Description
D.Work Package
AnswerA

Each product has a Product Description defining its quality criteria and acceptance methods.

Why this answer

The Product Description defines the product's purpose, composition, quality criteria, and acceptance methods.

637
MCQhard

What is the main purpose of separating the Project Manager role from the Project Assurance role in PRINCE2?

A.To allow the Project Manager to focus on team management
B.To reduce the workload of the Project Manager
C.To ensure independent oversight of the project
D.To provide administrative support to the Project Board
AnswerC

Independence is key; Project Assurance provides objective checks and balances.

Why this answer

Project Assurance provides independent oversight to the Project Board, ensuring the project is on track without being influenced by the Project Manager's day-to-day perspective.

638
Multi-Selecthard

Which THREE of the following are roles that are part of the Project Board?

Select 3 answers
A.Senior Supplier
B.Executive
C.Project Assurance
D.Senior User
E.Project Manager
AnswersA, B, D
639
MCQmedium

Which role is responsible for approving the Project Plan?

A.Project Board
B.Executive
C.Senior User
D.Project Manager
AnswerA

The Project Board collectively approves the Project Plan.

Why this answer

The Project Plan is approved by the Project Board, as it sets the baseline for the project's scope, schedule, and cost.

640
MCQmedium

Which document describes the quality methods and tools to be used on the project?

A.Quality Management Approach
B.Project Plan
C.Product Description
D.Project Product Description
AnswerA

This document defines the quality methods, tools, and responsibilities for the project.

Why this answer

The Quality Management Approach defines how quality will be managed, including quality methods, tools, and responsibilities.

641
MCQmedium

What is the purpose of the Managing a Stage Boundary process?

A.To provide the Project Board with information to review the current stage and plan the next
B.To plan the next stage and update the Business Case
C.To control the work of a stage and manage issues
D.To authorize the project and approve the Project Initiation Documentation
AnswerA

This is the core purpose of Managing a Stage Boundary.

Why this answer

Managing a Stage Boundary provides the Project Board with sufficient information to review the current stage and plan the next stage, and to decide whether to continue the project.

642
Multi-Selectmedium

Which THREE of the following are threat responses defined in PRINCE2?

Select 3 answers
A.Enhance
B.Accept
C.Transfer
D.Avoid
E.Exploit
AnswersB, C, D

Accept is a valid threat response.

Why this answer

PRINCE2 defines six threat responses: Avoid, Reduce, Fallback, Transfer, Accept, and Share. Options A, C, and D are correct; Exploit and Enhance are opportunity responses.

643
MCQeasy

Which process is responsible for authorising the project's closure?

A.Directing a Project
B.Closing a Project
C.Controlling a Stage
D.Managing a Stage Boundary
AnswerA

DP includes the decision to close the project.

Why this answer

Closure is authorised by the Project Board in the Directing a Project process, based on the End Project Report and closure recommendation from the PM.

644
MCQmedium

A project is in the Initiating a Project process and the Project Manager is preparing the Project Plan. Which technique is recommended by PRINCE2 for creating the Project Plan?

A.Work Breakdown Structure
B.Critical Path Analysis
C.Earned Value Management
D.Product-Based Planning
AnswerD

PRINCE2 recommends product-based planning, which starts with identifying products and dependencies.

Why this answer

PRINCE2 recommends product-based planning, which includes creating a Product Breakdown Structure (PBS) and Product Flow Diagram.

645
MCQeasy

Who is responsible for producing the Highlight Report during the Controlling a Stage process?

A.Senior User
B.Team Manager
C.Project Support
D.Project Manager
AnswerD

The Project Manager produces Highlight Reports during Controlling a Stage.

Why this answer

The Project Manager produces the Highlight Report during Controlling a Stage to inform the Project Board about progress. Team Managers produce Checkpoint Reports. Project Support may assist but not produce it.

The Senior User does not produce it.

646
Multi-Selecthard

Which THREE of the following are correct statements about Project Assurance?

Select 3 answers
A.It is performed by the Project Manager
B.It can be delegated to individuals outside the project management team
C.It focuses only on financial aspects
D.It provides independent oversight of the project's progress and quality
E.It is the responsibility of the Project Board
AnswersB, D, E

Assurance can be delegated to independent people.

Why this answer

Project Assurance is independent, performed by Project Board members or delegates, and covers all aspects of the project.

647
MCQeasy

Who is responsible for maintaining the Business Case throughout the project?

A.The Project Manager
B.The Executive
C.The Senior User
D.The Project Support
AnswerA

The Project Manager maintains the Business Case throughout the project.

Why this answer

In PRINCE2, the Project Manager is responsible for maintaining the Business Case throughout the project. This includes monitoring actual costs and benefits against the Business Case, updating it with any changes, and ensuring it remains viable. The Project Manager does not create the Business Case (that is the Executive's role) but is accountable for its ongoing maintenance and reporting.

Exam trap

PeopleCert often tests the distinction between 'owning' and 'maintaining' the Business Case, leading candidates to incorrectly select the Executive (who owns it) instead of the Project Manager (who maintains it).

How to eliminate wrong answers

Option B is wrong because the Executive is responsible for creating and approving the Business Case, not for its day-to-day maintenance; the Executive owns the Business Case at a strategic level but delegates maintenance to the Project Manager. Option C is wrong because the Senior User is responsible for specifying the benefits and ensuring the project delivers them, but does not maintain the Business Case document itself. Option D is wrong because Project Support provides administrative and advisory services to the Project Manager, but does not hold responsibility for maintaining the Business Case.

648
Multi-Selecthard

Which THREE of the following statements about the PRINCE2 principle 'Manage by Exception' are correct?

Select 3 answers
A.The Project Manager sets project tolerances for the Project Board
B.Tolerances are set for each management level
C.If a stage tolerance is forecast to be exceeded, the Project Manager must escalate to the Project Board
D.The Project Board sets stage tolerances for the Project Manager
E.Management by exception means that no reports are required unless a tolerance is exceeded
AnswersB, C, D

PRINCE2 defines tolerances at project, stage, and work package levels.

Why this answer

Options A, B, and D are correct. Manage by Exception means setting tolerances for each level and only escalating when they are exceeded. The Project Board sets stage tolerances for the PM.

The PM sets work package tolerances for team managers. Options C and E are false: the PM does not set project tolerances (Project Board does), and management by exception does not eliminate reporting — it defines when escalation is needed.

649
MCQeasy

What is the purpose of the Starting Up a Project process?

A.To check if the project is viable and worth initiating
B.To produce the Project Initiation Documentation
C.To authorize the project to proceed
D.To manage the delivery of products within a stage
AnswerA

SU ensures basic conditions exist before proceeding to initiation.

Why this answer

The Starting Up a Project process ensures that there is a viable and worthwhile project before the initiation stage begins.

650
Multi-Selectmedium

Which TWO of the following are outputs of the Managing a Stage Boundary process?

Select 2 answers
A.Work Package
B.Lessons Report
C.Project Brief
D.Highlight Report
E.End Stage Report
AnswersB, E

Correct. Lessons are captured in a Lessons Report during SB.

Why this answer

SB produces the End Stage Report, updated Project Plan, next Stage Plan (or Exception Plan), and Lessons Report. The Highlight Report is from CS, and the Project Brief is from SU.

651
MCQmedium

In PRINCE2, who is responsible for updating the Business Case during the project?

A.The Executive
B.The Project Manager
C.The Senior Supplier
D.The Senior User
AnswerA

The Executive is accountable for the Business Case.

Why this answer

The Executive is the single individual responsible for the Business Case throughout the project in PRINCE2. They own the Business Case and must ensure it remains viable, justified, and aligned with organizational strategy, approving any changes to it. The Project Manager only maintains the Business Case document but does not have authority to update its justification or approve changes.

Exam trap

PeopleCert often tests the distinction between 'maintaining' a document (Project Manager) and 'owning/updating' its content (Executive), causing candidates to incorrectly select the Project Manager as the one who updates the Business Case.

How to eliminate wrong answers

Option B is wrong because the Project Manager is responsible for creating and maintaining the Business Case document as a management product, but does not have the authority to update or approve changes to the Business Case itself—that authority rests solely with the Executive. Option C is wrong because the Senior Supplier represents the supplier interests and provides resources and expertise, but has no ownership or update authority over the Business Case. Option D is wrong because the Senior User represents the user community and specifies benefits, but the Business Case is owned and updated by the Executive, not the Senior User.

652
Multi-Selectmedium

Which TWO of the following are responsibilities of the Project Manager in PRINCE2?

Select 2 answers
A.Approve the Project Plan
B.Manage day-to-day project activities within tolerances
C.Provide independent assurance to the Project Board
D.Chair the Project Board meetings
E.Prepare the Stage Plan for the next stage
AnswersB, E

Correct: The Project Manager manages the project within agreed tolerances.

Why this answer

Option B is correct because the Project Manager is responsible for managing the day-to-day activities of the project within the tolerances set by the Project Board. This includes monitoring progress, resolving issues, and escalating deviations that exceed tolerances. PRINCE2 defines this as a core duty to ensure the project remains on track without requiring constant Board intervention.

Exam trap

The trap here is confusing the Project Manager's operational duties with the Project Board's strategic or assurance responsibilities, especially regarding plan approval and independent oversight.

653
Multi-Selectmedium

Which TWO of the following are outputs of the Managing a Stage Boundary process?

Select 2 answers
A.Project Brief
B.Checkpoint Report
C.Stage Plan for the next stage
D.End Stage Report
E.Lessons Log
AnswersC, D

The next Stage Plan is produced in SB.

Why this answer

Options B and D are correct. SB produces End Stage Report and next Stage Plan. Lessons Log is updated throughout, but the specific outputs are End Stage Report and Stage Plan.

Project Brief is from SU.

654
MCQeasy

You are the project manager for a construction project. The project is in the Initiating a Project process. The project board has approved the project brief, and you are now developing the project initiation documentation (PID). During this process, you identify that the project's business case is no longer viable due to a change in market conditions. What is the most appropriate action?

A.Continue developing the PID as planned and submit it to the project board.
B.Make the decision to close the project yourself and inform the team.
C.Advise the project board that the business case is no longer viable and recommend project closure.
D.Request additional time to find alternative justifications for the project.
AnswerC

The project board must be informed to decide on continuation.

Why this answer

In PRINCE2, the project board is responsible for making decisions about project viability, including closure. During the Initiating a Project process, if the business case becomes unviable, the project manager must escalate this to the project board, who then decides whether to close the project. Option C correctly reflects this by advising the board and recommending closure, aligning with the 'continued business justification' principle.

Exam trap

The trap here is that candidates may assume the project manager has the authority to close the project or continue without escalation, but PRINCE2 explicitly reserves closure decisions for the project board to maintain proper governance.

How to eliminate wrong answers

Option A is wrong because continuing to develop the PID despite a non-viable business case violates the PRINCE2 principle of continued business justification; the project should not proceed without a valid business case. Option B is wrong because the project manager does not have the authority to close the project unilaterally; only the project board can authorize closure. Option D is wrong because requesting additional time to find alternative justifications is not the prescribed action; the project manager should escalate the issue to the project board for a decision, not delay the process.

655
Multi-Selecthard

Which TWO of the following statements about the Quality Review technique are correct?

Select 2 answers
A.It is performed by the Project Board
B.It is a form of quality control
C.It assesses the viability of the Business Case
D.It is a structured review to identify defects in a product
E.It is used to test the product against its specification
AnswersB, D

Correct. Quality Review is a quality control technique.

Why this answer

The Quality Review technique involves a structured review of a product against its quality criteria. Option A is correct: the review identifies defects. Option D is correct: it is a form of quality control.

Option B is false: the review does not test; it is a review. Option C is false: it is not performed by the Project Board; it involves subject matter experts. Option E is false: the review is not about the Business Case; it's about products.

656
MCQhard

What is the difference between a risk owner and a risk actionee?

A.There is no difference; the terms are interchangeable
B.The risk owner is responsible for identifying the risk, while the risk actionee implements the response
C.The risk owner is accountable for the management of the risk, while the risk actionee performs specific actions
D.The risk owner is always a member of the Project Board, while the risk actionee is a team member
AnswerC

This correctly distinguishes accountability from execution.

Why this answer

In PRINCE2, the risk owner is accountable for the overall management of a risk, including monitoring and ensuring that appropriate responses are implemented. The risk actionee, on the other hand, is responsible for performing specific actions or tasks assigned as part of the risk response plan. Option C correctly captures this distinction between accountability and execution.

Exam trap

The trap here is that candidates confuse accountability with responsibility, assuming the risk owner does all the work, when in fact PRINCE2 separates these roles to ensure clear ownership and execution.

How to eliminate wrong answers

Option A is wrong because the terms are not interchangeable; PRINCE2 explicitly differentiates between the risk owner (accountable) and the risk actionee (responsible for specific actions). Option B is wrong because the risk owner is not responsible for identifying the risk (that is the risk identifier's role), and the risk actionee does not implement the entire response but only specific assigned actions. Option D is wrong because the risk owner is not always a member of the Project Board; they can be any individual with the authority to manage the risk, while the risk actionee is not limited to team members.

657
Multi-Selectmedium

Which TWO of the following are threat responses in PRINCE2?

Select 2 answers
A.Avoid
B.Exploit
C.Reduce
D.Share
E.Reject
AnswersA, C

Avoid is a threat response to eliminate the threat.

Why this answer

Avoid and Reduce are threat responses. Exploit and Share are opportunity responses, and Reject is also an opportunity response.

658
MCQeasy

What is the purpose of the Directing a Project process?

A.To manage the day-to-day work of the project
B.To enable the Project Board to make key decisions and exercise overall control
C.To deliver the project's products
D.To plan the project in detail
AnswerB

This is the purpose of Directing a Project.

Why this answer

Directing a Project is the process used by the Project Board to make key decisions and provide overall direction and control, including authorization of stages and closure.

659
Multi-Selecthard

Which THREE of the following are defined as PRINCE2 project management team roles?

Select 3 answers
A.Quality Manager
B.Project Manager
C.Risk Manager
D.Project Support
E.Project Assurance
AnswersB, D, E

A core role in the management team.

Why this answer

PRINCE2 defines specific roles: Project Manager, Team Manager, Project Assurance, Project Support, and the Project Board (Executive, Senior User, Senior Supplier). 'Risk Manager' and 'Quality Manager' are not standard roles in PRINCE2; their responsibilities are typically covered by Project Assurance or delegated within the team.

660
Multi-Selecthard

Which THREE of the following are characteristics of PRINCE2's product-based planning approach?

Select 3 answers
A.It uses a Product Breakdown Structure
B.It prioritises products based on their quality criteria
C.It creates a Product Flow Diagram
D.It creates Product Descriptions for each product
E.It starts by identifying activities and then determines products
AnswersA, C, D

PBS is a key technique.

Why this answer

Product-based planning focuses on defining products first, then activities. It includes Product Breakdown Structure, Product Flow Diagram, and Product Descriptions.

661
MCQeasy

Which role ensures that the project's products meet the needs of the users?

A.Senior User
B.Project Assurance
C.Senior Supplier
D.Project Manager
AnswerA

The Senior User ensures that the products meet user requirements.

Why this answer

The Senior User represents the users and ensures that the products meet their needs. The PM manages delivery but the Senior User defines requirements.

662
Multi-Selecteasy

Which TWO of the following are typical activities in the Closing a Project process?

Select 2 answers
A.Update the Project Brief
B.Produce the End Stage Report
C.Authorize the next stage
D.Hand over the project's products to the operational environment
E.Produce the Lessons Report
AnswersD, E

Product handover is a key activity in Closing a Project.

Why this answer

Closing a Project includes handing over products and producing the Lessons Report. The End Stage Report is from SB, and the Project Brief is from SU.

663
MCQmedium

Which document describes the quality management approach for the project, including the procedures to be used for quality assurance and quality control?

A.Project Product Description
B.Quality Management Approach
C.Quality Register
D.Product Description
AnswerB

This defines the project's approach to quality, including quality assurance and quality control procedures.

Why this answer

Option C is correct. The Quality Management Approach defines the project's approach to quality, including quality assurance and quality control procedures. Option A is incorrect because the Project Product Description describes the final product.

Option B is incorrect because the Product Description describes individual products. Option D is incorrect because the Quality Register records quality review results, not the approach.

664
Multi-Selecthard

Which THREE of the following are roles in the Project Management Team according to PRINCE2?

Select 3 answers
A.Steering Committee
B.Project Sponsor
C.Team Manager
D.Senior User
E.Project Manager
AnswersC, D, E

The Team Manager is a role within the project management team.

Why this answer

The PRINCE2 project management team includes the Executive, Senior User, Senior Supplier, Project Manager, Team Manager, Project Assurance, and Project Support. The Project Board consists of the Executive, Senior User, and Senior Supplier. 'Project Sponsor' is not a PRINCE2 role; 'Steering Committee' is not a PRINCE2 term.

665
MCQmedium

What is the purpose of the Closing a Project process?

A.To manage the benefits realization after the project
B.To approve the next stage
C.To provide a controlled closure of the project
D.To produce the Project Initiation Documentation
AnswerC

Closing a Project ensures all products are handed over, resources are released, and lessons are captured.

Why this answer

Closing a Project ensures controlled closure, handover of products, and confirmation that the project is complete. It does not manage benefits realization; that happens post-project.

666
MCQmedium

A project manager is planning the next stage. Which process should they use to produce the next Stage Plan and an End Stage Report?

A.Managing a Stage Boundary
B.Controlling a Stage
C.Initiating a Project
D.Directing a Project
AnswerA

SB is specifically designed to manage the transition between stages.

Why this answer

Managing a Stage Boundary (SB) is the process for reporting on the current stage and planning the next stage, producing both the End Stage Report and the next Stage Plan.

667
Multi-Selectmedium

Which TWO of the following are purposes of the Directing a Project process?

Select 2 answers
A.Produce the Project Plan
B.Authorise the project's initiation
C.Authorise the project closure
D.Deliver work packages
E.Manage day-to-day work of the project
AnswersB, C

Correct. The Board authorises initiation.

Why this answer

Directing a Project ensures the Project Board provides direction and makes key decisions, including authorising initiation, stage plans, and closure.

668
MCQhard

Which of the following statements best describes the PRINCE2 principle 'Manage by stages'?

A.The project plan is updated at the end of each stage to reflect actual progress
B.The project is divided into a number of phases, each with its own plan and tolerances
C.Stages are defined by the Project Manager to facilitate team management
D.Each stage must have a fixed duration and budget
AnswerB

Correct. Stages are sequential, each with a plan and tolerances.

Why this answer

The PRINCE2 principle 'Manage by stages' requires that the project be divided into management stages, each with its own plan and tolerances. This allows the Project Board to review progress and viability at key decision points before committing further resources, ensuring ongoing business justification and control.

Exam trap

PeopleCert often tests the misconception that stages are defined by the Project Manager for team management, but in PRINCE2, stages are management control points set by the Project Board, and their purpose is to enable go/no-go decisions, not to facilitate team organization.

How to eliminate wrong answers

Option A is wrong because the project plan is not updated at the end of each stage; instead, the stage plan is updated, and the project plan is revised only if the stage plan reveals a deviation that affects the overall project tolerances. Option C is wrong because stages are defined by the Project Board, not the Project Manager, to provide management control points and are not primarily for team management. Option D is wrong because stages do not have a fixed duration or budget; they have tolerances that allow for flexibility within agreed limits, and the duration and budget can vary as long as they stay within those tolerances.

669
MCQhard

Which of the following is a key difference between a Request for Change and an Off-specification?

A.A Request for Change proposes a modification to an agreed product, while an Off-specification identifies a product that does not meet its specification.
B.A Request for Change always has a cost and time impact, while an Off-specification never does.
C.A Request for Change is recorded in the Issue Register, while an Off-specification is recorded in the Risk Register.
D.A Request for Change does not require authorization, while an Off-specification does.
AnswerA

This correctly distinguishes the two types of issue.

Why this answer

Option D is correct. A Request for Change proposes a modification to an agreed product, while an Off-specification identifies that a product does not meet its specification. Option A is incorrect because both require authorization.

Option B is incorrect because both may involve cost and time impacts. Option C is incorrect because both are recorded in the Issue Register.

670
MCQmedium

The Project Board has set a cost tolerance of +/- 10% for a stage. The Project Manager forecasts that the stage will be completed 15% under budget. What should the Project Manager do?

A.Report the underrun in the next Highlight Report
B.Reallocate the surplus to other activities without informing the Project Board
C.Continue as planned since being under budget is beneficial
D.Raise an Exception Report to the Project Board
AnswerD

When a tolerance is forecast to be exceeded (even beneficial), an Exception Report is required.

Why this answer

If a forecast is within tolerance (under budget but within 10%?), actually 15% under is within the -10%? Wait: 15% under is outside the -10% tolerance. So it is an exception. The Project Manager must raise an Exception Report.

Option B is wrong because a Highlight Report is for regular reporting, not for exceptions. Option C is wrong because the PM cannot reallocate without authorization. Option D is wrong because exceeding tolerance requires escalation.

671
MCQhard

A project manager discovers that a product expected to be completed in the current stage does not meet its product description quality criteria. The project manager has already used the stage's change budget to address a similar issue. What should the project manager do?

A.Update the product description to match the delivered product
B.Request additional budget from the Project Board via an Exception Report
C.Accept the product as delivered and proceed to the next stage
D.Approve the rework using the remaining risk budget
AnswerB

When the change budget is exhausted, the project manager must escalate to the Project Board.

Why this answer

Since the change budget is exhausted, the project manager cannot approve further changes within their delegated authority. Therefore, they must escalate to the Project Board via an Exception Report.

672
MCQhard

A project manager is closing a project using the Closing a Project process. The project has delivered all products, but the business case has not been fully realized because the expected benefits will take longer to materialize. What should the project manager do with the Benefits Management Approach?

A.Discard the Benefits Management Approach as it is no longer needed
B.Update the Benefits Management Approach with actual results and recommend a follow-on action plan
C.Pass the Benefits Management Approach to the project board for ongoing management
D.Confirm that all benefits have been realized and close the project
AnswerB

This ensures benefits are tracked after project closure.

Why this answer

In PRINCE2, the Benefits Management Approach is a living document that must be updated with actual results during the Closing a Project process, even if benefits are not yet fully realized. Since the business case has not been fully realized, the project manager should record the actual benefits achieved and recommend a follow-on action plan for the remaining benefits to be managed post-project. This ensures that the expected benefits are not lost and that the organization can continue to pursue them.

Exam trap

PeopleCert often tests the misconception that the Benefits Management Approach is only relevant during project execution and can be discarded at closure, but PRINCE2 requires it to be updated and handed over for ongoing benefit management.

How to eliminate wrong answers

Option A is wrong because discarding the Benefits Management Approach would lose the documented plan for realizing benefits, which is still needed for the unachieved benefits. Option C is wrong because the project board does not manage the Benefits Management Approach operationally; it is typically handed over to the corporate or programme management for ongoing benefit realization. Option D is wrong because confirming all benefits have been realized is false—the question states the expected benefits will take longer to materialize, so the project cannot claim full realization.

673
MCQmedium

Which document is the key output of the Initiating a Project process?

A.Business Case
B.Project Brief
C.Project Plan
D.Project Initiation Documentation
AnswerD

Correct.

Why this answer

The Project Initiation Documentation (PID) is the key output of the Initiating a Project process, providing a baseline for the project.

674
MCQeasy

Which process is responsible for appointing the Executive and the Project Manager?

A.Starting Up a Project
B.Controlling a Stage
C.Directing a Project
D.Initiating a Project
AnswerA

In SU, the Executive is appointed by corporate management, and the Executive appoints the Project Manager.

Why this answer

The Starting Up a Project process is responsible for appointing the Executive and the Project Manager because it occurs before the project is formally initiated. During this process, the project mandate is reviewed, and key roles are assigned to ensure the project has the necessary leadership to proceed to the initiation stage. This is defined in PRINCE2 as the point where the project board is established and the Project Manager is selected.

Exam trap

The trap here is that candidates often confuse the Directing a Project process with the appointment of roles, but Directing a Project is about ongoing oversight and decision-making by the Project Board, not the initial appointment of the Executive and Project Manager.

How to eliminate wrong answers

Option B (Controlling a Stage) is wrong because this process focuses on day-to-day management of work within a stage, not on appointing senior roles like the Executive or Project Manager. Option C (Directing a Project) is wrong because this process is performed by the Project Board to make key decisions and provide overall direction, but the actual appointment of the Executive and Project Manager occurs in Starting Up a Project, not here. Option D (Initiating a Project) is wrong because this process develops the Project Initiation Documentation and plans for the next stage, but the Executive and Project Manager have already been appointed in the preceding Starting Up a Project process.

675
MCQeasy

Which practice describes why the project is being done and ensures continued business justification?

A.Business Case
B.Progress
C.Plans
D.Risk
AnswerA

The Business Case practice provides the business justification for the project.

Why this answer

The Business Case practice is the correct answer because it is the PRINCE2 practice that specifically defines the reasons for initiating a project and ensures that the project remains desirable, viable, and achievable throughout its lifecycle. It provides the justification for continued investment by requiring regular review and update of the business justification, which is documented in the Business Case. Without a valid Business Case, the project should be stopped.

Exam trap

PeopleCert often tests the distinction between the Business Case practice and the Plans practice, as candidates may mistakenly think that the project's justification is derived from the project plan rather than from the Business Case document.

How to eliminate wrong answers

Option B (Progress) is wrong because the Progress practice focuses on monitoring and controlling the project's performance against plans, not on defining or justifying why the project is being done. Option C (Plans) is wrong because the Plans practice deals with defining the steps to deliver the project's products, not with providing the business justification for the project itself. Option D (Risk) is wrong because the Risk practice is concerned with identifying, assessing, and controlling uncertainties that could affect the project, not with establishing or maintaining the business case.

Page 8

Page 9 of 24

Page 10