A Work Package is being executed. The Team Manager discovers a product cannot meet its quality criteria due to an unforeseen technical limitation. What should the Team Manager do?
Raising an issue to the Project Manager satisfies the PRINCE2 principle that the Team Manager escalates any forecast deviation from the Work Package's agreed tolerances, since the quality failure exceeds their authority to resolve. The Project Manager then assesses impact and decides the appropriate response.
Why this answer
In PRINCE2, the Team Manager works within the boundaries of an agreed Work Package and reports to the Project Manager, not directly to the Project Board. When a product cannot meet its quality criteria due to an unforeseen technical limitation, this is an issue that threatens the Work Package's tolerances and must be escalated to the Project Manager. The Project Manager then decides whether to resolve it at their level or escalate to the Project Board if project-level tolerances are threatened.
Exam trap
PRINCE2F often tests the misconception that the Team Manager can escalate directly to the Project Board, confusing the organizational hierarchy where the Project Manager is the sole conduit between the team and the Board.
How to eliminate wrong answers
Option A is wrong because the Team Manager has no direct reporting line to the Project Board; the Project Board only receives information via the Project Manager through Highlight Reports and Exception Reports. Option C is wrong because accepting lower quality without approval violates the Work Package's quality criteria and the agreed Product Description, and would constitute an unauthorized deviation. Option D is wrong because the Team Manager cannot unilaterally update the Work Package; any change to scope, quality, or tolerances must be authorized by the Project Manager.