Which role is responsible for maintaining the Business Case throughout the project?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Executive

The Executive (Senior Responsible Owner) is responsible for the Business Case. The Project Manager develops and maintains it, but ultimately the Executive owns it.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Project Assurance

    Why it's wrong here

    Project Assurance reviews the Business Case but does not own it.

  • Executive

    Why this is correct

    The Executive owns the Business Case and is responsible for its maintenance.

  • Senior User

    Why it's wrong here

    The Senior User specifies the benefits but does not own the Business Case.

  • Project Manager

    Why it's wrong here

    The Project Manager maintains the Business Case on behalf of the Executive.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.