Which role is responsible for maintaining the Business Case throughout the project?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Executive
The Executive (Senior Responsible Owner) is responsible for the Business Case. The Project Manager develops and maintains it, but ultimately the Executive owns it.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Project Assurance
Why it's wrong here
Project Assurance reviews the Business Case but does not own it.
- ✓
Executive
Why this is correct
The Executive owns the Business Case and is responsible for its maintenance.
- ✗
Senior User
Why it's wrong here
The Senior User specifies the benefits but does not own the Business Case.
- ✗
Project Manager
Why it's wrong here
The Project Manager maintains the Business Case on behalf of the Executive.
Go deeper
Related to this question
About these practice questions
This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.