Courseiva
PRINCE2 ProcessesmediumMultiple ChoiceObjective-mapped

PRINCE2F PRINCE2 Processes Practice Question

A project is forecast to exceed its stage cost tolerance. What should the Project Manager do?

⚠ Common exam trap

Many candidates think the Project Manager can simply adjust the budget or continue reporting later, but PRINCE2 strictly requires immediate escalation via an Exception Report when tolerance is forecast to be exceeded, emphasizing the principle of management by exception.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Raise an Exception Report to the Project Board and await their direction

PRINCE2 mandates that when a project manager forecasts a deviation beyond the stage tolerance, they must escalate the issue to the Project Board via an Exception Report. The Project Board then decides whether to approve an exception plan, adjust tolerance, or close the project. This ensures governance and control over the project's budget and scope.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Continue with the current Stage Plan and report the overrun in the next Highlight Report

    Why it's wrong here

    Escalation must happen immediately, not wait for the next Highlight Report.

  • Increase the project budget and continue with the current Stage Plan

    Why it's wrong here

    The Project Manager cannot increase the budget without authorization.

  • Close the project as the Business Case is no longer viable

    Why it's wrong here

    A single stage tolerance breach does not necessarily invalidate the Business Case.

  • Raise an Exception Report to the Project Board and await their direction

    Why this is correct

    Correct: management by exception requires escalation when tolerances are forecast to be exceeded.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.