Which process is responsible for creating the Project Brief?
⚠ Common exam trap
In PRINCE2, the trap here is that candidates mistakenly think the Project Brief is created during Initiating a Project, when in fact it is created earlier in Starting Up a Project.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Starting Up a Project
The Project Brief is created during the Starting Up a Project process. This process is triggered before the project is formally initiated and produces the Project Brief as a key output, which includes the project mandate, outline business case, and project approach. It provides the foundation for the Initiating a Project process.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Controlling a Stage
Why it's wrong here
CS manages work within a stage.
- ✓
Starting Up a Project
Why this is correct
The Project Brief is an output of SU.
- ✗
Directing a Project
Why it's wrong here
DP authorizes initiation but does not create the Project Brief.
- ✗
Initiating a Project
Why it's wrong here
IP produces the PID, not the Project Brief.
Go deeper
Related to this question
About these practice questions
This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
Same concept, more angles
2 more ways this is tested on PRINCE2F
These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.
Variation 1. Which process produces the Project Brief?
easy- A.Directing a Project
- B.Initiating a Project
- ✓ C.Starting Up a Project
- D.Managing a Stage Boundary
Why C: The Project Brief is produced during the 'Starting Up a Project' process. This process is triggered before the project is formally initiated, and its purpose is to create the Project Brief, which provides a high-level overview of the project's justification, scope, and approach, enabling the Project Board to decide whether to proceed to initiation.
Variation 2. Which process is responsible for producing the Project Brief?
easy- A.Directing a Project
- B.Initiating a Project
- ✓ C.Starting Up a Project
- D.Controlling a Stage
Why C: The Project Brief is produced during the Starting Up a Project process. This process ensures that the project has a viable business justification and that all necessary pre-project activities are completed before the project is formally initiated. The Project Brief is then used as input to the Initiating a Project process.
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.