Which level of plan in PRINCE2 is produced during the Initiating a Project process?
⚠ Common exam trap
The trap is confusing the plan produced during Initiating a Project (Project Plan) with the plan produced at stage boundaries (Stage Plan) or the optional Team Plan; candidates who associate 'initiation' with 'stage' will pick Stage Plan.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Project Plan
In PRINCE2, the Project Plan is produced during the Initiating a Project process. It provides the overall project timeline, costs, and resource requirements at the project level, and it is a key output of the Initiating a Project process along with the business case and project initiation documentation.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Exception Plan
Why it's wrong here
An Exception Plan is produced during Managing a Stage Boundary when a stage or project is forecast to exceed its tolerances, replacing the current plan. It is tempting because it is a plan type, but Initiating a Project produces the Project Plan, which the Project Board approves to authorise the project.
- ✗
Team Plan
Why it's wrong here
Team Plans are produced by the Team Manager during Managing Product Delivery, covering a team's work package, not during Initiating a Project. The Project Plan is the plan created in that process. Team Plans are tempting because they are legitimate PRINCE2 plans, but they belong to the delivery layer, not initiation.
- ✗
Stage Plan
Why it's wrong here
The Stage Plan for the first delivery stage is produced during Managing a Stage Boundary, not Initiating a Project. It is tempting because initiating does establish the next stage's work, but Initiating a Project produces the Project Plan; the first Stage Plan follows at the boundary before the stage begins.
- ✓
Project Plan
Why this is correct
The Project Plan is created during Initiating a Project, establishing the project's products, timescales, costs and controls before the Project Board authorises it. Stage Plans come later, during Managing a Stage Boundary, so the Project Plan is the correct level here.
Go deeper
Related to this question
About these practice questions
This PRINCE2F question is part of Courseiva's 1,189-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written and reviewed by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
Last reviewed September 2026 · checked against the official PeopleCert exam blueprint
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.