A Team Manager identifies a quality problem in a product that is being delivered. What should the Team Manager do?
The Team Manager records the quality problem in the daily log and informs the Project Manager, since quality issues affecting a Work Package fall outside the Team Manager's authority and require Project Manager assessment against stage tolerances.
Why this answer
When a Team Manager identifies a quality problem, PRINCE2 requires them to record it (typically in the Quality Register) and inform the Project Manager, who owns the Quality Register and decides on corrective action. The Team Manager does not have authority to change scope, quality tolerances, or the product's specification unilaterally. Escalating ensures the issue is handled within the project's quality and change control framework.
Exam trap
The trap is assuming the Team Manager should 'just fix it' or 'reject the product' — PRINCE2 emphasizes escalation and formal recording over unilateral action, and candidates often pick the most decisive-sounding option rather than the role-appropriate one.
How to eliminate wrong answers
Option B is wrong because ignoring a quality problem is never acceptable; the Checkpoint Report may mention progress, but the issue must be formally recorded and escalated. Option C is wrong because rejecting the product and stopping all work exceeds the Team Manager's authority and would disrupt the stage without Project Manager or board involvement. Option D is wrong because fixing the product immediately may breach the agreed quality criteria or baseline, and any change must go through the Project Manager and, if necessary, change control.