PRINCE2F PRINCE2 Practices Practice Question
A project is using the 'reduce' response for a threat. What does this mean?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
The probability and/or impact of the threat is lowered
Reduce means taking action to lower the probability or impact of a threat to an acceptable level.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
The threat is accepted and no action is taken
Why it's wrong here
Acceptance acknowledges the threat and deliberately takes no proactive action, logging it for contingency. Reduction requires active measures to lower probability or impact, so no action cannot satisfy it. Acceptance is tempting because it is a valid PRINCE2 response, but only when the risk is tolerable or cost of action outweighs benefit.
- ✓
The probability and/or impact of the threat is lowered
Why this is correct
The reduce response lowers the threat's probability, its impact, or both, typically through preventative or mitigating actions. This contrasts with avoid, which removes the threat entirely, and transfer, which shifts financial exposure to a third party.
- ✗
The threat is avoided by changing the plan
Why it's wrong here
Avoidance eliminates the threat by altering scope, requirements or approach so it can no longer occur; reduction instead lowers probability or impact while the threat remains. Avoidance is tempting because it sounds like a form of lessening, but it is the correct response when the threat can be designed out entirely.
- ✗
The threat is transferred to a third party
Why it's wrong here
Transfer shifts financial ownership of the threat to a third party, typically via insurance or a fixed-price contract, without changing its likelihood or impact. It is tempting because both responses involve other parties, but transfer is correct when the risk can be insured or contractually passed on.
About these practice questions
Courseiva writes every PRINCE2F question from scratch — 1,189 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.