Courseiva

PRINCE2F · domain

People: organizations, teams, and leadership

Practise PRINCE2 Foundation People: organizations, teams, and leadership practice questions — original exam-style scenarios with answer choices, explanations, and analysis of common mistakes.

312 questions79 easy148 medium85 hard

Focused practice

Practice People: organizations, teams, and leadership questions

Scored sessions drawing only from this domain — pick a length below.

Start 20-question practice test →

What this domain covers

What to know about People: organizations, teams, and leadership

People: organizations, teams, and leadership questions test whether you can apply the concept in context, not just recognise a definition.

How the topic appears in realistic exam-style scenarios.

Which detail in the question changes the correct answer.

How to eliminate plausible but wrong options.

How to connect the question back to the wider exam objective.

Watch out for

Common People: organizations, teams, and leadership exam traps

  • Answering from memory before reading the full scenario.
  • Missing a constraint such as cost, availability, security, scope or command context.
  • Choosing a broad answer when the question asks for the most specific fix.
  • Ignoring why the wrong options are tempting.

Question index

All People: organizations, teams, and leadership questions (312)

Click any question to see the full explanation, or start a practice session above.

1

In PRINCE2, who is responsible for day-to-day management of the project within tolerances?

Easy
2

Which TWO of the following are responsibilities of the Project Manager?

Medium
3

In PRINCE2, why is the Project Manager role separated from the Project Assurance role?

Hard
4

Who is responsible for providing independent assurance to the Project Board that the project is on track?

Easy
5

During the Managing a Stage Boundary process, the Project Manager prepares an Exception Plan. What is the trigger for this activity?

Medium
6

Which document is produced in the Initiating a Project process and defines how the project will be managed?

Medium
7

In PRINCE2, what is the difference between a Request for Change (RFC) and an Off-specification?

Hard
8

Who is responsible for maintaining the Business Case throughout the project?

Easy
9

Which TWO of the following are responsibilities of the Project Board?

Medium
10

Which THREE of the following are characteristics of Project Assurance?

Hard
11

Refer to the exhibit. According to PRINCE2, to whom should the Team Manager report the potential delay?

Hard
12

In PRINCE2, who is responsible for the day-to-day management of the project within the tolerances set by the Project Board?

Medium
13

Which document describes the detailed activities, resources, and costs for a single management stage?

Medium
14

During a project, the Project Board is informed that a major change to the project scope is required. Which role is best placed to assess the impact on the Business Case?

Medium
15

Drag and drop the steps to close a project in PRINCE2 into the correct order.

Medium
16

In PRINCE2, who is responsible for managing the delivery of a Work Package?

Easy
17

In PRINCE2, how often does the Project Board typically meet?

Easy
18

Who is responsible for maintaining the Business Case throughout the project?

Easy
19

Which role provides independent assurance to the Project Board that the project is being managed correctly?

Easy
20

Who is responsible for appointing the Project Manager?

Easy
21

Which role chairs the Project Board?

Easy
22

Which role is responsible for managing the delivery of a Work Package?

Medium
23

A project is in its Controlling a Stage process. The Team Manager reports that a Work Package is likely to be completed late. The Project Manager reviews the Stage Plan and sees that stage tolerance is not forecast to be exceeded. What should the Project Manager do?

Hard
24

During the Initiating a Project process, which document is created to define the project's scope, objectives, and how it will be managed?

Medium
25

Who chairs the Project Board in PRINCE2?

Easy
26

What is the difference between a Request for Change (RFC) and an Off-specification (Off-spec)?

Hard
27

Which TWO of the following are elements of a Work Package?

Medium
28

Which THREE of the following are responsibilities of the Senior Supplier on the Project Board?

Medium
29

Which THREE of the following are responsibilities of the Project Manager?

Medium
30

Which TWO of the following are responsibilities of the Project Board?

Medium
31

Which role is responsible for managing the delivery of Work Packages and reporting progress to the Project Manager?

Medium
32

In PRINCE2, what is the purpose of the 'Managing a Stage Boundary' process?

Hard
33

The Project Board consists of three roles. Which of the following is NOT a mandatory role on the Project Board?

Hard
34

In PRINCE2, what is the main reason for separating the Project Manager role from the Project Assurance role?

Medium
35

According to PRINCE2, who is responsible for authorizing the work packages to be executed by the team?

Medium
36

Which TWO of the following statements about the Project Board are correct?

Hard
37

What is the minimum frequency of Project Board meetings?

Medium
38

The Project Board has delegated authority for change control decisions to a separate body. What is this body called?

Medium
39

Which role is responsible for the day-to-day management of the project within the tolerances set by the Project Board?

Easy
40

In PRINCE2, what is the role of the Senior Supplier on the Project Board?

Medium
41

The Project Manager notes that a Work Package is at risk of being delivered late. What should the Project Manager do?

Medium
42

Which PRINCE2 role is optional and provides administrative support to the project?

Easy
43

Which of the following is an optional role in the PRINCE2 project management team?

Easy
44

During which process is the Project Initiation Documentation (PID) created?

Medium
45

Why does PRINCE2 separate the Project Manager role from Project Assurance?

Hard
46

A Project Manager is appointed to a project during the Starting Up a Project process. The project has a complex technical scope. The SRO wants to ensure that the Project Board receives independent assurance on technical decisions. Who should provide this assurance?

Hard
47

Which role is responsible for ensuring that the project is being managed correctly from the business perspective?

Medium
48

Which TWO of the following are true about Project Assurance?

Easy
49

Which TWO statements about the project board are correct? (Choose two.)

Medium
50

Why does PRINCE2 separate the Project Manager from Project Assurance?

Hard
51

In PRINCE2, what is the difference between a Request for Change (RFC) and an Off-specification?

Hard
52

In PRINCE2, who manages the delivery of Work Packages?

Medium
53

Which role delegates change control decisions to a Change Authority?

Easy
54

Which role is responsible for the independent assurance that the project remains on track?

Medium
55

Which THREE of the following are reasons why PRINCE2 recommends separating the Project Manager from Project Assurance?

Hard
56

Which TWO of the following are roles that are part of the Project Board?

Medium
57

A large IT project is implementing a new customer relationship management (CRM) system for a multinational corporation. The project is organized with a Project Board comprising the Executive (VP of Sales), Senior User (Regional Sales Director), and Senior Supplier (IT Director). The Project Manager is an experienced PMP-certified professional. The team includes several business analysts and developers from an external supplier. The project has just completed the Initiating a Project process and received authorization to proceed to the next stage. However, during the first week of the Delivery Stage, the Project Manager notices that the business analysts are not collaborating effectively with the developers, leading to misunderstandings about requirements. The Project Manager holds a meeting and discovers that the business analysts feel excluded from decision-making and the developers complain about unclear specifications. The Project Manager wants to resolve this using PRINCE2 principles and practices. Which of the following is the BEST course of action?

Medium
58

Who is responsible for managing the delivery of a Work Package?

Easy
59

Why does PRINCE2 separate the Project Manager from Project Assurance?

Hard
60

What is the difference between a Request for Change (RFC) and an Off-specification?

Medium
61

In PRINCE2, a Team Manager reports to the Project Manager. What is the primary responsibility of a Team Manager?

Medium
62

What is the key difference between Project Assurance and Project Support?

Hard
63

Which THREE of the following statements about the Project Board are correct?

Medium
64

What is the key difference between Project Assurance and a quality review?

Medium
65

Which THREE of the following are responsibilities of the Project Manager?

Medium
66

Which role is responsible for the day-to-day management of a Work Package?

Medium
67

Which TWO of the following are roles defined in PRINCE2?

Medium
68

In PRINCE2, what is the difference between accountability and responsibility?

Hard
69

Who is responsible for maintaining the Business Case throughout the project?

Easy
70

The Project Board is considering a Request for Change. Which role is authorized to approve changes within delegated limits?

Medium
71

Which role is optional in the PRINCE2 project management team?

Easy
72

Which TWO statements about the Project Board are true?

Medium
73

Which role is accountable for the project's Business Case throughout the project?

Easy
74

Which role is responsible for ensuring the project provides value for money and is aligned with business strategy?

Easy
75

Which document is the key output of the Initiating a Project process?

Easy
76

Which PRINCE2 principle is being applied when the Project Manager escalates a forecast tolerance deviation to the Project Board?

Hard
77

Which TWO of the following are roles in the PRINCE2 project management team?

Easy
78

Who chairs the Project Board meetings?

Easy
79

In PRINCE2, who is responsible for managing the delivery of a Work Package?

Medium
80

Which role is responsible for maintaining the Business Case throughout the project?

Easy
81

A project is in the Managing a Stage Boundary process. Which key document is produced during this process?

Medium
82

The Project Board has delegated change control decisions to a Change Authority. What is the key benefit of this delegation?

Hard
83

Which TWO of the following are members of the Project Board?

Medium
84

Which role is responsible for preparing the Highlight Report?

Easy
85

The Project Board has approved an Exception Plan to recover from a budget overrun. The Project Manager updates the Project Plan. What else must the Project Manager update?

Medium
86

Who is responsible for maintaining the Business Case throughout the project?

Easy
87

What is the difference between a Request for Change (RFC) and an Off-Specification (Off-Spec)?

Hard
88

Which role is responsible for the day-to-day management of a Work Package?

Easy
89

Which role is responsible for maintaining the Business Case throughout the project?

Easy
90

Who is responsible for the day-to-day management of a project within the tolerances set by the Project Board?

Easy
91

What is the difference between a Request for Change and an Off-specification?

Medium
92

What is the primary purpose of the Managing a Stage Boundary process?

Hard
93

What is the difference between a Request for Change (RFC) and an Off-Specification (Off-spec)?

Hard
94

A project is in the Initiating a Project process. Which document is the key output of this process?

Medium
95

What is the key difference between Project Assurance and Project Support?

Hard
96

Who is responsible for providing Project Support in PRINCE2?

Easy
97

Which TWO of the following are benefits of separating the Project Manager and Project Assurance roles?

Medium
98

Who is responsible for maintaining the Business Case throughout the project?

Easy
99

The Team Manager receives a Work Package and proceeds with the work. A product is found to be defective. What should the Team Manager do?

Medium
100

Which TWO of the following are differences between the Starting Up a Project (SU) and Initiating a Project (IP) processes?

Hard
101

Which THREE factors should be considered when designing the project management team structure? (Choose three.)

Hard
102

A team manager has completed a work package and is ready to hand over the deliverables. To whom should the team manager report the completion?

Medium
103

What is the main reason PRINCE2 separates the role of Project Manager from Project Assurance?

Hard
104

Why does PRINCE2 separate the Project Manager role from Project Assurance?

Hard
105

During project execution, a team member raises a concern that the project's objectives are not aligned with the organization's strategic goals. Which role is primarily responsible for ensuring alignment?

Easy
106

What is the purpose of the Managing a Stage Boundary process?

Easy
107

Which TWO of the following are responsibilities of the Project Manager?

Medium
108

In PRINCE2, which role is responsible for the day-to-day management of the project within the tolerances set by the Project Board?

Medium
109

Which role is responsible for providing administrative support to the project team?

Easy
110

In the PRINCE2 RACI model, what does 'Accountable' mean?

Medium
111

A project is forecast to exceed its stage cost tolerance. What should the Project Manager do?

Medium
112

What is the purpose of the Change Authority role in PRINCE2?

Medium
113

A project is forecast to exceed its cost tolerance. What should the Project Manager do?

Medium
114

Which TWO of the following are true about the Senior Responsible Owner (Executive) role?

Medium
115

Which THREE of the following are defined roles in PRINCE2?

Medium
116

Which THREE of the following are responsibilities of the Project Board in PRINCE2?

Hard
117

A project is being executed in a stage. The Team Manager reports that a Work Package is likely to exceed its tolerances. What should the Project Manager do first?

Medium
118

Why does PRINCE2 separate the Project Manager role from Project Assurance?

Medium
119

What is the main purpose of separating the Project Manager role from the Project Assurance role in PRINCE2?

Hard
120

Which TWO of the following are responsibilities of the Project Manager in PRINCE2?

Medium
121

Which THREE of the following are defined as PRINCE2 project management team roles?

Hard
122

Which role ensures that the project's products meet the needs of the users?

Easy
123

What is the difference between a Request for Change (RFC) and an Off-specification (Off-spec)?

Hard
124

In PRINCE2, who is accountable for the project's success and the realization of benefits?

Easy
125

During the Initiating a Project process, which document is created that defines how the project will be controlled and governed?

Medium
126

Which THREE of the following are roles on the Project Board?

Medium
127

In a PRINCE2 project, the Project Manager submits an Exception Report. What is the most likely trigger for this report?

Medium
128

Which document describes the user's needs and expectations for the project's products?

Medium
129

What is the key difference between Project Assurance and a quality review?

Hard
130

Who is responsible for maintaining the Business Case throughout the project?

Easy
131

What is the primary purpose of the Project Support role in PRINCE2?

Easy
132

Which TWO of the following are responsibilities of the Project Assurance role?

Medium
133

Who is responsible for maintaining the Business Case throughout the project?

Easy
134

Which TWO of the following are responsibilities of the Project Board?

Medium
135

A project is forecast to exceed its stage cost tolerance. What should the Project Manager do?

Medium
136

A project is forecast to exceed its cost tolerance for the current stage. What should the Project Manager do?

Medium
137

In PRINCE2, the Project Board should meet at which frequency?

Medium
138

Which TWO of the following are responsibilities of the Senior Responsible Owner (SRO)?

Medium
139

During the Managing a Stage Boundary process, the Project Manager creates the Stage Plan for the next stage. Who approves this Stage Plan?

Medium
140

Which TWO of the following statements correctly describe the relationship between the Project Manager and Project Assurance?

Medium
141

What is the key output of the 'Starting Up a Project' process?

Medium
142

Which THREE of the following are responsibilities of the Project Manager in PRINCE2?

Medium
143

During the Managing a Stage Boundary process, the Project Manager produces an Exception Plan. What triggers this?

Medium
144

A Project Manager delegates the management of a Work Package to a Team Manager. What is the Team Manager's responsibility?

Medium
145

Which document is the key output of the Initiating a Project process?

Medium
146

In PRINCE2, what is the primary difference between Project Assurance and a quality review?

Medium
147

A project is in the Initiating a Project process. Which document is the key output of this process?

Medium
148

Which role is responsible for maintaining the Business Case throughout the project?

Easy
149

During the Controlling a Stage process, the Project Manager identifies that the project is forecast to exceed the agreed cost tolerance for the current stage. What should the Project Manager do?

Medium
150

Which TWO of the following are true about Project Assurance?

Easy
151

What is the difference between a Request for Change and an Off-specification?

Hard
152

A project manager notices that team members from different departments are unclear about their roles and responsibilities. According to PRINCE2, which management product should be used to clarify this?

Easy
153

A project is in the Initiating a Project process. Which key document is produced as an output of this process?

Medium
154

What is the key difference between Project Assurance and a quality review?

Hard
155

Which TWO of the following are differences between Project Assurance and a quality review?

Medium
156

In the RACI model used in PRINCE2, what is the difference between accountability (A) and responsibility (R)?

Hard
157

In PRINCE2, which role provides independent assurance to the Project Board that the project is being conducted correctly?

Medium
158

Which of the following is NOT a responsibility of the Project Manager?

Medium
159

What is the key difference between Project Assurance and a quality review?

Hard
160

Which THREE of the following are responsibilities of the Project Manager?

Hard
161

A project is in the Initiating a Project process. Which role is responsible for preparing the Project Initiation Documentation (PID)?

Medium
162

Which statement correctly describes the relationship between Project Assurance and quality review?

Hard
163

Why does PRINCE2 separate the Project Manager role from Project Assurance?

Medium
164

What is the purpose of the Managing a Stage Boundary process?

Easy
165

Who is responsible for producing the Checkpoint Report?

Medium
166

In PRINCE2, why is the Project Assurance role separated from the Project Manager?

Hard
167

A stakeholder is concerned that the project is not delivering value for money. Which role should this concern be raised with?

Medium
168

What is the difference between a Request for Change and an Off-specification?

Hard
169

Which document is produced by the Team Manager to report progress on a Work Package?

Medium
170

A project is forecast to exceed its stage cost tolerance. What should the Project Manager do?

Medium
171

In PRINCE2, who is responsible for maintaining the Business Case throughout the project?

Easy
172

Which role is responsible for maintaining the Business Case throughout the project?

Easy
173

Which PRINCE2 principle ensures that the Project Board delegates decision-making to the Project Manager within defined tolerances?

Easy
174

Why does PRINCE2 recommend separating the role of Project Manager from Project Assurance?

Hard
175

Which TWO roles are part of the Project Board?

Medium
176

Which TWO of the following are characteristics of the Project Assurance role?

Medium
177

How often should the Project Board meet during a PRINCE2 project?

Easy
178

Which role is responsible for ensuring that the project's products meet specified quality criteria?

Medium
179

Which THREE of the following are roles on the PRINCE2 Project Board?

Medium
180

What is the purpose of the Managing a Stage Boundary process?

Medium
181

In PRINCE2, what is the key difference between the Project Assurance role and a quality review?

Hard
182

What is the purpose of the Managing a Stage Boundary process?

Easy
183

Which TWO of the following are responsibilities of the Project Manager?

Medium
184

A Team Manager receives a Work Package from the Project Manager. During delivery, the Team Manager identifies a potential issue that may cause a delay. What should the Team Manager do first?

Hard
185

Which THREE of the following are responsibilities of the Project Board?

Medium
186

Which role is responsible for managing the delivery of a Work Package?

Easy
187

Which THREE of the following are true about Project Assurance in PRINCE2?

Hard
188

Which report is produced by the Team Manager and used by the Project Manager to update the Project Board?

Medium
189

In a PRINCE2 project, the Project Manager has also been assigned the Project Assurance role. Which PRINCE2 principle is being violated?

Hard
190

Match each PRINCE2 role to its responsibility.

Medium
191

A Senior Supplier is concerned that a proposed change will impact the project's technical feasibility. What should the Senior Supplier do?

Medium
192

In PRINCE2, why is the Project Manager not allowed to also perform Project Assurance?

Hard
193

Which role is responsible for project assurance activities in a PRINCE2 project?

Easy
194

In a PRINCE2 project, the project board is concerned that the project manager is not effectively communicating with key stakeholders. The project manager recently presented a detailed risk report to the board, but several board members were unaware of the critical risks identified. Which communication management activity should the project manager have performed to ensure the board was properly informed?

Hard
195

Which THREE of the following are responsibilities of the Senior Supplier role on the Project Board?

Hard
196

Which role can delegate change control decisions to a Change Authority?

Hard
197

Which role manages the day-to-day execution of a Work Package?

Easy
198

A Team Manager receives a Work Package from the Project Manager. To whom should the Team Manager report progress?

Medium
199

Which TWO of the following statements about the Change Authority role are correct?

Hard
200

In PRINCE2, what is the difference between a Request for Change (RFC) and an Off-Specification (Off-spec)?

Hard
201

Who is responsible for managing the delivery of a Work Package?

Easy
202

Which of the following is NOT a role in the PRINCE2 project management team?

Medium
203

What is the difference between Project Assurance and a quality review?

Hard
204

A project is forecast to exceed its cost tolerance. What should the Project Manager do?

Medium
205

Which role is responsible for providing independent assurance to the Project Board that the project is on track?

Medium
206

Which role is accountable for the project's Business Case throughout the project?

Easy
207

Which TWO of the following statements about the Change Authority role are correct?

Medium
208

Which document is the key output of the Initiating a Project process?

Medium
209

Which of the following best describes the relationship between the Senior Responsible Owner (SRO) and the Project Sponsor in PRINCE2?

Hard
210

Who chairs the Project Board?

Easy
211

Who is responsible for ensuring that the project remains viable in terms of Business Case?

Easy
212

Why does PRINCE2 separate the Project Manager role from the Project Assurance role?

Hard
213

A project is in the Managing a Stage Boundary process. Which action should the Project Manager take?

Medium
214

What is the purpose of the Managing a Stage Boundary process?

Medium
215

Who is responsible for maintaining the Business Case throughout the project?

Easy
216

What is the purpose of the Directing a Project process?

Medium
217

Who chairs the Project Board meetings?

Easy
218

Which TWO of the following are responsibilities of the Senior Responsible Owner (SRO/Executive) on the Project Board?

Medium
219

What is the difference between a Request for Change and an Off-specification?

Hard
220

Which TWO of the following describe the role of Project Assurance?

Medium
221

Which TWO of the following are responsibilities of the Project Board?

Medium
222

Who is responsible for ensuring that Project Assurance is performed?

Medium
223

A project is forecast to exceed its stage cost tolerance. What should the Project Manager do?

Medium
224

The project board decides to use majority voting for all decisions. What is a potential issue with this decision-making process?

Hard
225

Who chairs the Project Board?

Easy
226

Who is responsible for managing the project's day-to-day activities within the tolerances set by the Project Board?

Medium
227

Which role is ultimately accountable for the project's Business Case throughout the project?

Easy
228

Which document is used by the Project Manager to capture lessons learned during a stage?

Easy
229

Which TWO of the following are responsibilities of the Project Manager?

Medium
230

Which THREE of the following are typical responsibilities of the Project Support role?

Hard
231

Which role is responsible for ensuring that the project's products meet their specified quality criteria?

Easy
232

What is the difference between Project Assurance and a quality review?

Hard
233

According to PRINCE2, when should the Project Board meet?

Medium
234

A project is forecast to exceed its stage cost tolerance. What should the Project Manager do?

Medium
235

What is the difference between a Request for Change (RFC) and an Off-Specification (Off-Spec)?

Easy
236

What is the difference between a Request for Change and an Off-specification?

Hard
237

The Project Board is meeting to make decisions when the project is not meeting its tolerances. What type of meeting is this?

Medium
238

Which TWO of the following are responsibilities of the Project Manager?

Medium
239

In which process does the Project Board authorize the next stage of a project?

Medium
240

The Project Board is reviewing an Exception Report that recommends a change to the project's scope. Who on the Project Board is primarily responsible for deciding whether the change is justified?

Medium
241

Why does PRINCE2 separate the Project Manager from Project Assurance?

Hard
242

In a large program, the project manager is struggling to get timely decisions from the project board due to conflicting priorities. What is the best PRINCE2 approach to address this?

Medium
243

What is the difference between a Request for Change (RFC) and an Off-Specification (Off-spec)?

Hard
244

Which TWO of the following statements correctly describe the relationship between accountability and responsibility in PRINCE2?

Hard
245

According to PRINCE2, which role is responsible for defining the project's tolerances?

Medium
246

In PRINCE2, who is responsible for preparing and updating the Highlight Report?

Medium
247

Which TWO roles are optional in the PRINCE2 project management team?

Medium
248

A project is forecast to exceed its cost tolerance. What should the Project Manager do?

Medium
249

A Project Manager receives a forecast that a Work Package will exceed its tolerance. What should the PM do?

Medium
250

What is the key difference between Project Assurance and quality review?

Hard
251

During the Initiating a Project process, which document is created that defines how the project will be controlled?

Medium
252

The Project Board is meeting to authorize the start of a new stage. According to PRINCE2, how frequently should the Project Board meet?

Medium
253

Which TWO of the following are types of roles defined in a PRINCE2 project management team?

Easy
254

Who is accountable for the success of the project in PRINCE2?

Easy
255

In PRINCE2, what is the difference between a Senior Responsible Owner (SRO) and a Project Sponsor?

Hard
256

The Project Manager has issued a Work Package to a Team Manager. The Team Manager realizes that the work cannot be completed within the agreed tolerances. What should the Team Manager do first?

Medium
257

Which TWO of the following are responsibilities of the Project Manager in PRINCE2?

Easy
258

Which PRINCE2 role is responsible for preparing the Project Plan?

Medium
259

What is the purpose of the Managing a Stage Boundary process?

Easy
260

Which TWO of the following are purposes of the Starting Up a Project process?

Easy
261

What is the key difference between Project Assurance and a quality review?

Hard
262

Which document is the key output of the Initiating a Project process?

Easy
263

Which role is ultimately accountable for the project's Business Case and its continued viability?

Easy
264

Which document is the key output of the Initiating a Project process?

Easy
265

During the Controlling a Stage process, the Project Manager receives a Checkpoint Report from a Team Manager indicating a delay in delivering a Work Package. What should the Project Manager do first?

Medium
266

What is the role of Project Assurance?

Easy
267

What is the difference between a Request for Change and an Off-specification?

Hard
268

A project team is distributed across three time zones, causing communication delays. The project manager wants to apply the 'manage by stages' principle effectively. What should the project manager do first?

Hard
269

A project is forecast to exceed its stage cost tolerance. What should the Project Manager do?

Medium
270

A project is running over time by 5% against the stage tolerance of 10%. The Project Manager expects this trend to continue. What should the Project Manager do?

Medium
271

What is the difference between Project Assurance and a quality review?

Hard
272

Which role is accountable for the project's success in PRINCE2?

Easy
273

A project has a strong matrix structure. The project manager finds that team members are more loyal to their functional managers than to the project. What is the best PRINCE2 practice to improve team commitment?

Medium
274

Which TWO statements correctly describe the role of the Senior User in PRINCE2?

Medium
275

When should the Project Board meet?

Easy
276

What is the purpose of the Starting up a Project process?

Easy
277

Who is responsible for maintaining the Business Case throughout the project?

Easy
278

Who is responsible for maintaining the Business Case throughout the project?

Easy
279

Which TWO of the following are responsibilities of the Project Manager?

Medium
280

What is the key difference between a Request for Change (RFC) and an Off-specification (Off-spec)?

Hard
281

In PRINCE2, what is the difference between a risk owner and a risk actionee?

Hard
282

Which THREE of the following are purposes of the Directing a Project process?

Hard
283

During the Controlling a Stage process, a Work Package is authorized by the Project Manager. Who is responsible for delivering the Work Package?

Medium
284

A project manager notices that team members are frequently bypassing the project's defined escalation paths and going directly to senior stakeholders with issues. This is causing confusion and undermining the project's governance. Which PRINCE2 principle is being violated?

Medium
285

Which of the following statements best describes the difference between a Request for Change (RFC) and an Off-Specification (Off-spec)?

Hard
286

In PRINCE2, what is the purpose of Project Support?

Easy
287

Which document is the key output of the Initiating a Project process?

Medium
288

In PRINCE2, what is the role of the Senior User?

Medium
289

Which THREE of the following are true regarding Project Assurance?

Hard
290

Which role is responsible for producing the Highlight Report?

Medium
291

A project is in the Managing a Stage Boundary process. The Project Manager discovers that the stage is likely to overrun its time tolerance. The Project Board has not yet approved the next Stage Plan. What should the Project Manager do?

Hard
292

Which THREE of the following are responsibilities of the Project Board?

Hard
293

Which TWO of the following are optional roles in the PRINCE2 project management team?

Medium
294

A project is forecast to exceed its stage cost tolerance. What should the Project Manager do?

Medium
295

Who chairs the Project Board meetings in PRINCE2?

Medium
296

Which THREE of the following are elements of the PRINCE2 project management team?

Medium
297

Why does PRINCE2 separate the role of Project Manager from Project Assurance?

Hard
298

What is the difference between Project Assurance and a quality review?

Hard
299

The Project Board has not met for several months. According to PRINCE2, when should the Project Board meet?

Medium
300

A project is forecast to exceed its cost tolerance. What should the Project Manager do?

Hard
301

Which THREE statements about the Project Board's responsibilities in PRINCE2 are correct?

Hard
302

Which THREE of the following are true about the role of the Change Authority?

Hard
303

In PRINCE2, what is the recommended leadership style for a Project Manager when dealing with a team that has high competence and low commitment?

Hard
304

Which THREE of the following are responsibilities of the Project Support role?

Hard
305

What is the difference between a Request for Change (RFC) and an Off-specification?

Hard
306

What is the difference between a Request for Change (RFC) and an Off-specification (Off-spec)?

Medium
307

What is the difference between a Request for Change and an Off-specification?

Medium
308

Which PRINCE2 role is responsible for ensuring that the project's products meet the required quality criteria?

Medium
309

Which role is responsible for maintaining the Business Case throughout the project?

Easy
310

In PRINCE2, which role is responsible for ensuring that the business case is maintained and that the project remains viable?

Easy
311

What is the difference between the Senior Responsible Owner (SRO/Executive) and a Project Sponsor?

Hard
312

In PRINCE2, what is the key difference between Project Assurance and a quality review?

Hard

Frequently asked questions

What does the People: organizations, teams, and leadership domain cover on the PRINCE2F exam?
People: organizations, teams, and leadership questions test whether you can apply the concept in context, not just recognise a definition.
How many questions are in this domain?
This page lists all 312 People: organizations, teams, and leadership questions in the PRINCE2F question bank. The actual exam draws from this domain proportionally to its weighting in the official exam blueprint.
What is the best way to practise this domain?
Start with a short focused session (10 questions) to identify gaps, then work through explanations. Repeat with a longer session once the weak areas feel solid.
Can I practise only People: organizations, teams, and leadership questions?
Yes — the session launcher on this page filters questions to this domain only. Choose any session length for inline explanations and scoring.
peoplecert-prince2-foundation PEOPLECERT-PRINCE2-FOUNDATION prince2 people Practice Questions