Courseiva

PRINCE2F People: organizations, teams, and leadership Practice Question

Who is responsible for appointing the Project Manager?

⚠ Common exam trap

Test-takers frequently confuse the Project Board's collective responsibility with the individual roles of Senior User or Senior Supplier, or mistakenly think the Change Authority has broader management powers than it actually does.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

The Project Board

In PRINCE2, the Project Board is responsible for appointing the Project Manager. This is because the Project Board represents the business, user, and supplier interests and has the authority to delegate day-to-day management to the Project Manager. The Project Board's responsibility includes ensuring the right person is appointed to manage the project on their behalf.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    The Project Board

    Why this is correct

    The Project Board owns the project mandate and directs the project at its highest level, so appointing the Project Manager sits with it. The Project Manager then recruits the team, while Project Assurance monitors independently. This matches PRINCE2's accountability for the project management team structure.

  • ✗

    The Senior User

    Why it's wrong here

    The Senior User represents those who will use the project's outputs and specifies requirements; they hold no authority to appoint the Project Manager. Appointment sits with the Project Board, acting on the Project Manager's own recommendation. The Senior User role would be the right answer if the question instead asked who defines and monitors benefits realisation.

  • ✗

    The Senior Supplier

    Why it's wrong here

    The Senior Supplier represents those providing supplier resources and sits on the Project Board to advise on supplier interests; appointing the Project Manager is a Project Board action led by the Executive. It is tempting because supplier representation carries board-level authority, and it would be correct for decisions on supplier resource commitment.

  • ✗

    The Change Authority

    Why it's wrong here

    The Change Authority is delegated by the Project Board to approve or reject change requests within agreed tolerances; it holds no role in appointing the Project Manager. It is tempting because it is a formally appointed board-level role, and it would be correct where the question concerns authorising changes within a defined change budget.

About these practice questions

One of 1,189 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.