Which role is responsible for managing the delivery of Work Packages and reporting progress to the Project Manager?

⚠ Common exam trap

Candidates often confuse the Team Manager with the Project Manager, assuming the Project Manager directly manages all work, but PRINCE2 explicitly separates these roles to enable delegation and management by exception.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Team Manager

In PRINCE2, the Team Manager is responsible for managing the delivery of Work Packages and reporting progress to the Project Manager. This role ensures that the products defined in the Work Package are created to the required quality, within time and cost constraints, and provides regular progress reports to the Project Manager.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Project Manager

    Why it's wrong here

    The Project Manager manages the project on a day-to-day basis, authorises Work Packages, and receives progress reports from Team Managers; they do not deliver the Work Packages themselves. It is tempting because the Project Manager owns overall progress reporting, and the role would be correct for escalating tolerances or authorising work.

  • ✗

    Senior Supplier

    Why it's wrong here

    The Senior Supplier represents the supplier's interests on the Project Board and provides resources and expertise; they do not manage Work Package delivery or report progress. This is tempting because suppliers do perform the work, and the role would be correct for agreeing supplier commitments and ensuring supplier resources are made available.

  • ✓

    Team Manager

    Why this is correct

    The Team Manager accepts Work Packages from the Project Manager, manages their day-to-day delivery, and reports progress, quality and issues back up. This directly satisfies the stem's requirement, since PRINCE2 assigns Work Package delivery and progress reporting to the Team Manager role, not the Project Manager or Project Board.

  • ✗

    Project Support

    Why it's wrong here

    Project Support provides administrative services such as maintaining the project filing structure, configuration management, and tooling; it does not manage Work Package delivery. It is tempting because support staff often collate progress data, and the role would be correct for administering change control, maintaining the lessons log, or assisting with reporting.

About these practice questions

One of 1,189 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.