Courseiva
PRINCE2 PracticesmediumMultiple ChoiceObjective-mapped

PRINCE2F PRINCE2 Practices Practice Question

During the Controlling a Stage process, the Project Manager identifies that the project is forecast to exceed the agreed cost tolerance for the current stage. What should the Project Manager do?

⚠ Common exam trap

It's easy for candidates to assume the Project Manager can absorb small cost overruns within their delegated authority, but PRINCE2 strictly requires escalation whenever forecast costs exceed the agreed stage tolerance, regardless of the amount.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Raise an Exception Report to the Project Board and await their direction before proceeding

In PRINCE2, when a Project Manager forecasts that stage tolerances will be exceeded, they must escalate the issue to the Project Board via an Exception Report. This triggers an Exception Plan process, allowing the Board to decide whether to approve revised tolerances or take corrective action. The Project Manager cannot proceed without direction, as tolerances are a delegated authority limit.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Raise an Exception Report to the Project Board and await their direction before proceeding

    Why this is correct

    This is the correct escalation procedure.

  • Close the project immediately as the Business Case is no longer viable

    Why it's wrong here

    The Project Board decides on viability, not the Project Manager.

  • Continue with the current Stage Plan and report the cost overrun in the next Highlight Report

    Why it's wrong here

    Continuing without escalation violates management by exception.

  • Increase the project budget to absorb the additional cost and continue with the current Stage Plan

    Why it's wrong here

    The Project Manager cannot unilaterally increase the budget.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

3 more ways this is tested on PRINCE2F

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. During the Controlling a Stage process, the Project Manager identifies that the project is forecast to exceed the agreed cost tolerance for the current stage. What should the Project Manager do?

medium
  • A.Continue with the current Stage Plan and report the cost overrun in the next Highlight Report
  • B.Close the project immediately as the Business Case is no longer viable
  • C.Raise an Exception Report to the Project Board and await their direction before proceeding
  • D.Increase the project budget to absorb the additional cost and continue with the current Stage Plan

Why C: When a stage tolerance is forecast to be exceeded, the Project Manager must escalate to the Project Board via an Exception Report. This is management by exception.

Variation 2. During the Controlling a Stage process, the Project Manager identifies that the project is forecast to exceed the agreed cost tolerance for the current stage. What should the Project Manager do?

medium
  • A.Increase the project budget to absorb the additional cost and continue with the current Stage Plan
  • B.Raise an Exception Report to the Project Board and await their direction before proceeding
  • C.Close the project immediately as the Business Case is no longer viable
  • D.Continue with the current Stage Plan and report the cost overrun in the next Highlight Report

Why B: When a stage is forecast to exceed its cost tolerance, the Project Manager must escalate the issue to the Project Board via an Exception Report. This is the embodiment of PRINCE2's management by exception principle. The Project Board then decides whether to approve a revised Stage Plan or take other action. Option A is incorrect because the Project Manager cannot increase the budget without Project Board approval. Option C is incorrect because viability of the Business Case is assessed by the Project Board, not unilaterally by the Project Manager. Option D is incorrect because escalating via a Highlight Report only reports progress, not exceptions; exceptions require an Exception Report.

Variation 3. During the Controlling a Stage process, the Project Manager identifies that the project is forecast to exceed the agreed cost tolerance for the current stage. What should the Project Manager do?

medium
  • A.Continue with the current Stage Plan and report the cost overrun in the next Highlight Report
  • B.Close the project immediately as the Business Case is no longer viable
  • C.Raise an Exception Report to the Project Board and await their direction before proceeding
  • D.Increase the project budget to absorb the additional cost and continue with the current Stage Plan

Why C: According to the management by exception principle, when a stage tolerance is forecast to be exceeded, the Project Manager must escalate to the Project Board via an Exception Report. The Project Manager cannot unilaterally increase the budget or ignore the breach.

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.