PRINCE2 PracticesmediumMultiple ChoiceObjective-mapped

PRINCE2F PRINCE2 Practices Practice Question

During the Controlling a Stage process, the Project Manager identifies that the stage's cost tolerance is forecast to be exceeded. According to PRINCE2, what should the Project Manager do?

⚠ Common exam trap

Many exam-takers confuse an issue that is within tolerance (handled by the Project Manager) with one that is forecast to exceed tolerance (requiring escalation), or mistakenly think the change budget can be used to cover any cost overrun.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Raise an Exception Report to the Project Board and await their direction before proceeding

According to PRINCE2, when a stage's cost tolerance is forecast to be exceeded, the Project Manager must escalate the issue to the Project Board by raising an Exception Report. This is because the Project Manager does not have authority to exceed the agreed tolerance; the Project Board must decide whether to approve a revised Stage Plan or take other corrective action. Continuing without escalation or making unauthorized adjustments violates the management by exception principle.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Increase the stage budget using the change budget and continue with the current Stage Plan

    Why it's wrong here

    The Project Manager cannot unilaterally increase the stage budget; changes to tolerances require Project Board approval.

  • Close the project immediately as the Business Case is no longer viable

    Why it's wrong here

    A cost tolerance breach does not automatically mean the Business Case is unviable; the Project Board must assess the situation.

  • Raise an Exception Report to the Project Board and await their direction before proceeding

    Why this is correct

    When a stage tolerance is forecast to be exceeded, the Project Manager must escalate to the Project Board via an Exception Report.

  • Continue with the current Stage Plan and report the cost overrun in the next Highlight Report

    Why it's wrong here

    Continuing without escalation when a tolerance is forecast to be exceeded violates management by exception.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.