PRINCE2 Foundation (PRINCE2F) — Questions 13511425

1731 questions total · 24pages · All types, answers revealed

Page 18

Page 19 of 24

Page 20
1351
MCQmedium

The Project Board is reviewing an Exception Report that recommends a change to the project's scope. Who on the Project Board is primarily responsible for deciding whether the change is justified?

A.Senior Supplier
B.Project Manager
C.Senior User
D.Senior Responsible Owner (SRO/Executive)
AnswerC

The Senior User is responsible for representing user requirements and benefits.

Why this answer

The Senior User is primarily responsible for defining the benefits and ensuring the project delivers a product that meets user needs. When an Exception Report recommends a scope change, the Senior User must assess whether the change is justified from a user-benefit perspective, as they represent the interests of those who will use the project's output. In PRINCE2, the Senior User's role includes approving changes that affect the project's scope, ensuring they align with the business case and user requirements.

Exam trap

PeopleCert often tests the distinction between the Executive's accountability for the business case and the Senior User's responsibility for user benefits, leading candidates to mistakenly choose the Executive when the question specifically asks about justification from a user perspective.

How to eliminate wrong answers

Option A is wrong because the Senior Supplier is responsible for providing the necessary resources and expertise to deliver the project's products, not for deciding whether a scope change is justified from a user-benefit standpoint. Option B is wrong because the Project Manager manages the project on a day-to-day basis and prepares the Exception Report, but they do not have the authority to approve scope changes; that decision rests with the Project Board. Option D is wrong because the Senior Responsible Owner (SRO/Executive) is accountable for the business case and overall project success, but the specific decision on whether a scope change is justified from a user perspective falls to the Senior User, who ensures the change delivers the required benefits.

1352
MCQhard

Why does PRINCE2 separate the Project Manager from Project Assurance?

A.To ensure independent oversight and avoid conflicts of interest
B.To reduce the workload of the Project Manager
C.To have a separate person to blame if something goes wrong
D.To allow the Project Manager to focus on technical tasks
AnswerA

This is the key reason for the separation.

Why this answer

PRINCE2 separates the Project Manager from Project Assurance to ensure independent oversight of the project's direction, progress, and compliance with standards. This separation prevents conflicts of interest that would arise if the same person were responsible for both managing the project and objectively assessing its health. Project Assurance provides an impartial check on the Project Manager's decisions, ensuring that the project remains viable and aligned with business, user, and supplier interests.

Exam trap

The trap here is that candidates may confuse role separation with workload management or blame allocation, rather than recognizing it as a governance mechanism to maintain objective oversight and prevent conflicts of interest.

How to eliminate wrong answers

Option B is wrong because reducing the Project Manager's workload is not the primary purpose of separating Project Assurance; PRINCE2 defines distinct roles to maintain objectivity, not to offload tasks. Option C is wrong because PRINCE2 does not design roles to allocate blame; the separation is about independent oversight and accountability, not scapegoating. Option D is wrong because the Project Manager's focus is on management and coordination, not technical tasks; technical tasks are handled by team managers or specialists, and Project Assurance is not intended to free the Project Manager for technical work.

1353
MCQmedium

Which report is prepared by the Team Manager and sent to the Project Manager at regular intervals?

A.End Stage Report
B.Exception Report
C.Highlight Report
D.Checkpoint Report
AnswerD

The Checkpoint Report provides progress information from the Team Manager to the Project Manager.

Why this answer

Option A is correct. The Checkpoint Report is a progress report prepared by the Team Manager and sent to the Project Manager. Option B is incorrect because the Highlight Report is prepared by the Project Manager for the Project Board.

Option C is incorrect because the Exception Report is prepared by the Project Manager when tolerances are forecast to be exceeded. Option D is incorrect because the End Stage Report is prepared by the Project Manager at stage boundaries.

1354
MCQmedium

A Work Package has been completed and the products have passed quality checks. What should the Team Manager do next in the Managing Product Delivery process?

A.Raise an Exception Report
B.Update the Project Plan
C.Close the project stage
D.Deliver the Work Package to the Project Manager
AnswerD

After completion, the Team Manager delivers the Work Package and obtains acceptance.

Why this answer

The final activity in MP is to 'Deliver a Work Package', which involves handing over the completed products to the Project Manager and obtaining formal acceptance.

1355
MCQhard

In the Closing a Project process, what is the Project Board's responsibility?

A.To produce the Lessons Report
B.To hand over the project products to the operational environment
C.To confirm the project has met its objectives and authorize closure
D.To release the project resources
AnswerC

In CP, the Project Board reviews the End Project Report and formally authorizes project closure.

Why this answer

The Project Board authorizes the closure of the project after reviewing the End Project Report and Lessons Report, ensuring all products are accepted and benefits review plans are in place.

1356
MCQmedium

Which document is the key output of the Initiating a Project process?

A.Exception Report
B.Project Brief
C.Project Initiation Documentation
D.End Stage Report
AnswerC

The PID is the key output of IP, providing the foundation for the project.

Why this answer

The Project Initiation Documentation (PID) is the definitive document that defines the project and forms the basis for its management. It is created during the Initiating a Project process.

1357
Multi-Selectmedium

Which TWO of the following are responsibilities of the Project Manager during the Controlling a Stage process?

Select 2 answers
A.Produce the End Stage Report
B.Authorize Work Packages
C.Review the Business Case for continued viability
D.Produce the Lessons Report
E.Authorize project closure
AnswersB, C

Done in CS.

Why this answer

During CS, the PM authorizes Work Packages and reviews the Business Case (if needed). Producing Highlight Reports is also a CS activity, but the question asks for two; authorizing Work Packages and reviewing the Business Case are both correct. Producing the End Stage Report is from SB.

1358
MCQeasy

Which document is the key output of the Initiating a Project process?

A.Project Initiation Documentation
B.Project Brief
C.Exception Report
D.End Project Report
AnswerA

The PID is the comprehensive document produced in IP.

Why this answer

The Initiating a Project process is where the project's baselines are established, and the key output is the Project Initiation Documentation (PID). The PID consolidates all the information needed to justify the project, define its scope, and provide a basis for decision-making. It is the definitive document that is approved by the project board to authorize the project to proceed.

Exam trap

The trap here is that candidates often confuse the Project Brief (created earlier) with the PID, or think that the End Project Report is a key output of initiation because it summarizes the project, but PRINCE2 specifically tests the sequence of processes and their distinct outputs.

How to eliminate wrong answers

Option B is wrong because the Project Brief is created during the Starting Up a Project process, not the Initiating a Project process; it provides initial high-level information but is not the comprehensive baseline document. Option C is wrong because an Exception Report is an issue management document produced during the Managing a Stage Boundary or Directing a Project process when a stage is forecast to exceed tolerance, not a key output of initiation. Option D is wrong because the End Project Report is produced during the Closing a Project process to evaluate project performance against the PID, not during initiation.

1359
MCQmedium

A project is in the Closing a Project process. What should the Project Manager produce to recommend project closure?

A.Exception Report
B.End Project Report
C.End Stage Report
D.Project Brief
AnswerB

The End Project Report is the key output that summarizes the project and recommends closure.

Why this answer

The Project Manager produces an End Project Report and a Lessons Report, and then recommends closure to the Project Board.

1360
MCQmedium

What is the purpose of the Quality Review technique?

A.To approve the project's quality management approach
B.To update the quality register
C.To assess the quality of a product and identify defects
D.To define quality criteria for products
AnswerC

The Quality Review technique is used to review products against their quality criteria.

Why this answer

The Quality Review technique is used to assess the quality of a product and identify defects. It is a form of quality control.

1361
Multi-Selecthard

Which THREE activities are part of the Controlling a Stage process?

Select 3 answers
A.Authorize Work Packages
B.Produce the Project Initiation Documentation (PID)
C.Review progress and update stage status
D.Approve the next Stage Plan
E.Escalate issues and risks that exceed stage tolerances
AnswersA, C, E

Correct: The PM authorizes Work Packages in CS.

Why this answer

Authorizing Work Packages, reviewing progress, and escalating exceptions are all activities in CS. Producing the PID is done in IP. Approving the next Stage Plan is done by the Project Board in DP.

1362
MCQmedium

Who receives Highlight Reports?

A.Project Board
B.Senior Supplier
C.Project Support
D.Team Manager
AnswerA

The Project Board receives Highlight Reports from the Project Manager.

Why this answer

Highlight Reports are prepared by the Project Manager and sent to the Project Board (and possibly stakeholders) at regular intervals.

1363
MCQmedium

In a large program, the project manager is struggling to get timely decisions from the project board due to conflicting priorities. What is the best PRINCE2 approach to address this?

A.Delay decisions until the board reaches consensus on their own
B.Escalate the issue to the program management for resolution
C.Request the project board to hold a facilitated session to align their priorities
D.Redefine the project management team roles to reduce board involvement
AnswerC

The board should provide unified direction.

Why this answer

Option C is correct because PRINCE2 emphasizes that the project board must provide unified direction and timely decisions. When conflicting priorities arise, a facilitated session is a recognized technique to align the board's priorities, ensuring effective governance without bypassing the board's authority. This approach directly addresses the root cause—misalignment—rather than delaying, escalating prematurely, or reducing board involvement.

Exam trap

The trap here is that candidates may confuse escalation (Option B) as the default PRINCE2 response to any issue, but PRINCE2 requires exhausting internal resolution mechanisms—like facilitated alignment—before escalating to program management.

How to eliminate wrong answers

Option A is wrong because delaying decisions until the board reaches consensus on their own violates the PRINCE2 principle of 'manage by stages' and can cause project delays, as the project manager should actively facilitate decision-making rather than passively wait. Option B is wrong because escalating to program management is premature; the project board is the decision-making body for the project, and the issue should first be resolved within the board before involving higher management. Option D is wrong because redefining roles to reduce board involvement undermines the PRINCE2 principle of 'defined roles and responsibilities' and the project board's accountability for key decisions, which cannot be delegated away.

1364
MCQmedium

A Team Manager completes a Work Package and requests formal acceptance of the product. Which process handles this?

A.Managing a Stage Boundary
B.Managing Product Delivery
C.Closing a Project
D.Controlling a Stage
AnswerB

MP includes delivering the completed product and obtaining acceptance.

Why this answer

Managing Product Delivery is the process where the Team Manager executes the work and delivers completed products to the Project Manager for acceptance. Controlling a Stage is the PM's process for managing the stage; Managing a Stage Boundary focuses on stage end and next stage planning; Closing a Project handles final project closure.

1365
Multi-Selecthard

Which THREE of the following are components of a Product Description?

Select 3 answers
A.Purpose
B.Derivation
C.Quality criteria
D.Benefits
E.Cost
AnswersA, B, C

Purpose is a component of a Product Description.

Why this answer

A Product Description includes purpose, composition, derivation, format, quality criteria, quality method, and quality tolerance. Cost and benefits are not part of a Product Description; they are in the Business Case.

1366
MCQmedium

Which document defines the quality criteria and acceptance methods for a project's products?

A.Product Description
B.Quality Management Approach
C.Business Case
D.Project Plan
AnswerA

Product Descriptions define quality criteria, acceptance methods, and other product-specific details.

Why this answer

Option C is correct. Product Descriptions define the quality criteria, acceptance methods, and other details for each product. The Quality Management Approach defines the overall quality strategy.

1367
MCQmedium

You are managing a construction project. During the Initiation Stage, you are developing the Project Plan. The senior supplier informs you that the required steel will be delayed by 3 months due to a global shortage. This delay will push the project completion beyond the board's deadline. The project has a fixed completion date due to regulatory requirements. The senior user is unwilling to accept a delay. You have identified that using an alternative material could save 2 months but would increase costs by 15%. The project budget has a 10% contingency. What is the most appropriate course of action?

A.Reduce the project scope to meet the deadline
B.Switch to the alternative material and use the contingency to cover the cost increase
C.Accept the delay and update the Project Plan accordingly
D.Inform the board that the project cannot meet the deadline and request guidance
AnswerD

The board must decide on options, as the issue impacts the project's viability.

Why this answer

Option D is correct because the project has a fixed completion date due to regulatory requirements, and the identified solution (alternative material) still results in a 1-month delay (3-month delay minus 2-month saving) and exceeds the 10% contingency (15% cost increase vs. 10% contingency). According to PRINCE2, when a stage plan or project plan cannot be achieved within agreed tolerances, the Project Manager must escalate the issue to the Project Board for a decision. The board is the only authority that can authorize a change to the project's scope, schedule, or budget beyond the delegated tolerances.

Exam trap

The trap here is that candidates may think the contingency is available to cover any cost overrun, but PRINCE2 requires that contingency use must be within agreed tolerances and that exceeding tolerances triggers escalation, not autonomous action.

How to eliminate wrong answers

Option A is wrong because reducing scope without board authorization violates PRINCE2's management by exception principle; the Project Manager does not have the authority to change scope beyond tolerances. Option B is wrong because the 15% cost increase exceeds the 10% contingency, meaning the budget tolerance would be breached, and the Project Manager must escalate rather than unilaterally use contingency funds. Option C is wrong because accepting the delay and updating the Project Plan without board approval would ignore the fixed regulatory deadline and the need for exception management; the board must decide whether to accept the delay or authorize a different approach.

1368
Multi-Selectmedium

Which TWO of the following are PRINCE2 principles?

Select 2 answers
A.Define deliverables
B.Manage by stages
C.Tailor to suit the project environment
D.Manage by objectives
E.Use product-based planning
AnswersB, C
1369
MCQmedium

The project's risk appetite has been defined as 'cautious'. A high-impact opportunity with low probability is identified. What is the most likely response?

A.Enhance
B.Share
C.Reject
D.Exploit
AnswerC

Reject is appropriate for cautious appetite when opportunity risk is not acceptable.

Why this answer

A cautious appetite means risk-averse; even low probability opportunities may be rejected if they carry risk.

1370
MCQmedium

What is the purpose of the Starting Up a Project process?

A.To appoint the Project Board
B.To decide whether to initiate the project
C.To produce the Project Initiation Documentation
D.To close the project
AnswerB

SU determines if there is sufficient justification and information to proceed to initiation.

Why this answer

SU ensures that the project has a viable business case and necessary foundation before committing to full initiation. It checks if the project is worthwhile and doable.

1371
MCQeasy

In the Directing a Project process, which of the following is a key responsibility of the Project Board?

A.Producing Highlight Reports
B.Authorizing the next Stage Plan
C.Managing day-to-day work within a stage
D.Accepting Work Packages
AnswerB

Correct. The Project Board authorizes stage plans.

Why this answer

In PRINCE2, the Directing a Project process is the decision-making layer where the Project Board exercises overall control. A key responsibility is authorizing the next Stage Plan, which formally approves the detailed plan for the upcoming management stage and commits the resources required to execute it. This ensures the project remains viable and aligned with business justification before proceeding.

Exam trap

PeopleCert often tests the distinction between the Project Board's strategic control (authorizing stages) and the Project Manager's tactical execution (producing reports, managing daily work), leading candidates to confuse the two roles.

How to eliminate wrong answers

Option A is wrong because producing Highlight Reports is a responsibility of the Project Manager, not the Project Board; the Project Board receives these reports to monitor progress. Option C is wrong because managing day-to-day work within a stage is the responsibility of the Project Manager, who coordinates the team and handles operational issues. Option D is wrong because accepting Work Packages is a task performed by the Team Manager or team members, not the Project Board; the Project Board authorizes the stage plan that contains the work packages.

1372
Multi-Selectmedium

Which TWO of the following are types of issues in PRINCE2?

Select 2 answers
A.Request for Change
B.Change
C.Risk
D.Off-specification
E.Opportunity
AnswersA, D

An RFC is a type of issue.

Why this answer

PRINCE2 defines three types of issues: Request for Change, Off-specification, and Problem/Concern. Risk and change are not types of issues.

1373
MCQmedium

During the Controlling a Stage process, who is responsible for producing Checkpoint Reports?

A.Team Manager
B.Project Manager
C.Project Board
D.Project Support
AnswerA

The Team Manager produces Checkpoint Reports as part of Managing Product Delivery.

Why this answer

Checkpoint Reports are produced by the Team Manager and sent to the Project Manager to inform about progress within a Work Package.

1374
MCQmedium

In PRINCE2, who is responsible for providing assurance that the project is being conducted properly?

A.Project Support
B.Project Manager
C.Project Board
D.Project Assurance
AnswerD

Project Assurance is independent and reports to the Project Board.

Why this answer

Project Assurance is an independent role that ensures the project remains aligned with business, user, and supplier interests.

1375
MCQhard

What is the difference between a Request for Change (RFC) and an Off-Specification (Off-spec)?

A.There is no difference; they are interchangeable terms
B.An RFC is a change to the project scope; an Off-spec is a change to the schedule
C.An RFC proposes a modification; an Off-spec identifies a deviation from specification
D.An RFC is raised by the Project Board; an Off-spec is raised by the Project Manager
AnswerC

This is the correct distinction: RFC is proactive change; Off-spec is a conformance issue.

Why this answer

An RFC proposes a change to baselined products, while an Off-spec identifies that a product does not meet its specification (a defect or non-conformance).

1376
MCQhard

In the risk management procedure, what is the difference between a risk owner and a risk actionee?

A.Risk owner identifies risks; risk actionee assesses them
B.Risk owner manages the risk overall; risk actionee performs specific actions
C.Risk owner is the same as risk actionee in PRINCE2
D.Risk owner is on the Project Board; risk actionee is a team member
AnswerB

Correct. The owner has overall accountability; the actionee executes tasks.

Why this answer

The risk owner is responsible for managing the risk and ensuring appropriate responses are implemented; the risk actionee is the person who carries out specific risk response actions.

1377
Multi-Selecthard

Which TWO of the following statements correctly describe the relationship between accountability and responsibility in PRINCE2?

Select 2 answers
A.The Project Manager is accountable for the project's success.
B.The Project Manager is accountable for the Business Case.
C.The SRO is accountable for the project's success.
D.Accountability can be delegated to the Project Manager.
E.Responsibility for tasks can be delegated.
AnswersC, E

The SRO is ultimately accountable.

Why this answer

In PRINCE2, the Senior Responsible Owner (SRO) is the single point of accountability for the project's success, as they own the Business Case and are ultimately responsible for ensuring the project delivers the expected benefits. The Project Manager is responsible for managing the project on a day-to-day basis but is not accountable for overall success. Option C correctly identifies the SRO's accountability, and option E correctly states that responsibility (for tasks) can be delegated, while accountability cannot.

Exam trap

The trap here is that candidates often confuse accountability with responsibility, assuming the Project Manager is accountable for project success because they manage the work, but PRINCE2 explicitly assigns accountability to the SRO and allows only responsibility to be delegated.

1378
MCQmedium

According to PRINCE2, which role is responsible for defining the project's tolerances?

A.Team Manager
B.Senior User
C.Project Manager
D.Project Board
AnswerD

The Board sets project-level tolerances.

Why this answer

The Project Board defines project-level tolerances; the Project Manager sets stage-level tolerances within them.

1379
MCQhard

During which process is the Project Plan created?

A.Initiating a Project
B.Managing a Stage Boundary
C.Starting Up a Project
D.Directing a Project
AnswerA

IP produces the PID, which includes the Project Plan.

Why this answer

The Project Plan is created during Initiating a Project.

1380
MCQmedium

What is the difference between a Highlight Report and a Checkpoint Report?

A.The Highlight Report is used to escalate exceptions, while the Checkpoint Report is for routine communication
B.The Highlight Report is produced only at stage boundaries, while the Checkpoint Report is produced weekly
C.The Highlight Report is from the Project Manager to the Project Board, while the Checkpoint Report is from the Team Manager to the Project Manager
D.The Highlight Report focuses on risks and issues, while the Checkpoint Report focuses on product quality
AnswerC

This correctly identifies the reporting hierarchy.

Why this answer

Option A is correct. The Highlight Report is sent by the Project Manager to the Project Board, while the Checkpoint Report is sent by the Team Manager to the Project Manager. Option B is wrong because both reports are regular.

Option C is wrong because both reports focus on progress. Option D is wrong because the Highlight Report is not a response to exceptions.

1381
MCQmedium

During the Initiating a Project process, which document is the key output that defines how the project will be managed?

A.Project Initiation Documentation
B.End Stage Report
C.Project Brief
D.Business Case
AnswerA

The PID is the definitive document produced in IP, containing plans, approaches, and baselines.

Why this answer

The Project Initiation Documentation (PID) is the key output of the Initiating a Project process. It consolidates all baselines for managing the project.

1382
MCQeasy

In PRINCE2, who is responsible for project assurance?

A.The Project Manager
B.The Senior Supplier
C.The Project Support
D.The Project Board
AnswerD

Correct. The Project Board is responsible for assurance.

Why this answer

Project assurance is the responsibility of the Project Board, which provides independent assurance.

1383
Multi-Selectmedium

Which TWO of the following are components of a Business Case?

Select 2 answers
A.Major risks
B.Project organization structure
C.Work Breakdown Structure
D.Expected benefits
E.Quality criteria
AnswersA, D

Risks are included.

Why this answer

Expected benefits and major risks are key components of a Business Case in PRINCE2.

1384
Multi-Selectmedium

Which TWO of the following are activities performed in the Directing a Project process?

Select 2 answers
A.Produce the Project Initiation Documentation
B.Take corrective action within stage tolerances
C.Manage day-to-day work of a stage
D.Authorize a stage or exception plan
E.Authorize initiation
AnswersD, E

The Board authorizes plans.

Why this answer

Directing a Project includes authorizing initiation and authorizing a stage or exception plan. Managing day-to-day work and producing the PID are not Board activities.

1385
MCQhard

What is the difference between a Request for Change (RFC) and an Off-specification?

A.There is no difference; they are the same thing
B.An RFC is raised by the Project Manager; an Off-specification is raised by the Team Manager
C.An RFC requires a change budget; an Off-specification does not
D.An RFC concerns a desired change to an approved specification; an Off-specification is a product that does not meet its specification
AnswerD

This is the correct distinction.

Why this answer

An RFC is a proposal for a modification to a product that has been baselined, while an Off-specification is a product that should be produced but is not meeting specifications.

1386
Multi-Selecthard

Which TWO of the following are responsibilities of the Project Manager during the Controlling a Stage process?

Select 2 answers
A.Review the Business Case and decide on stage tolerances
B.Escalate issues that cannot be resolved within stage tolerances
C.Approve the Project Plan
D.Produce Checkpoint Reports
E.Authorize Work Packages
AnswersB, E

The PM escalates issues to the Project Board via Exception Reports when tolerances are exceeded.

Why this answer

During CS, the Project Manager authorizes Work Packages, reviews progress, and reports to the Project Board. Producing Checkpoint Reports is a Team Manager responsibility, and making decisions on project tolerances is a Project Board responsibility.

1387
MCQmedium

In PRINCE2, who is responsible for preparing and updating the Highlight Report?

A.Team Manager
B.Project Support
C.Project Manager
D.Senior User
AnswerC

The Project Manager is responsible for the Highlight Report.

Why this answer

The Project Manager prepares the Highlight Report and sends it to the Project Board at regular intervals (e.g., weekly or monthly) to provide a summary of stage status.

1388
Multi-Selecteasy

Which TWO documents are produced during the Starting Up a Project process?

Select 2 answers
A.Project Initiation Documentation
B.End Stage Report
C.Stage Plan for the next stage
D.Initiation Stage Plan
E.Project Brief
AnswersD, E

The plan for the initiation stage is created in Starting Up a Project.

Why this answer

The Starting Up a Project (SU) process produces the Project Brief and the Initiation Stage Plan. The Project Brief provides a high-level overview of the project's justification, scope, and approach, while the Initiation Stage Plan details the activities, resources, and controls for the initiation stage. Both are mandatory outputs of SU, ensuring the project has a clear mandate and a plan for the next phase before committing to full initiation.

Exam trap

PeopleCert often tests the distinction between outputs of Starting Up a Project versus Initiating a Project, specifically confusing the Project Brief (SU) with the Project Initiation Documentation (IP) and the Initiation Stage Plan (SU) with a Stage Plan for a subsequent stage (SB).

1389
MCQhard

A risk has been identified that could cause a delay to the project. The project team decides to purchase insurance to cover the financial impact. Which risk response type is this?

A.Transfer
B.Avoid
C.Accept
D.Reduce
AnswerA

Insurance transfers the financial impact to an insurer.

Why this answer

Transferring the financial impact to a third party (insurance) is a 'transfer' response. 'Reduce' would involve actions to lower probability or impact. 'Accept' would be to take the risk without action.

1390
MCQeasy

Who is responsible for authorising the initiation of a project?

A.Project Manager
B.Project Board
C.Executive
D.Senior User
AnswerB

Correct. The Project Board authorises initiation via DP.

Why this answer

The Project Board authorises initiation as part of the Directing a Project process. The Executive is a member of the Project Board, but the decision is taken collectively by the Board.

1391
Multi-Selectmedium

Which TWO roles are optional in the PRINCE2 project management team?

Select 2 answers
A.Senior User
B.Project Manager
C.Team Manager
D.Project Support
E.Change Authority
AnswersD, E

Optional administrative support role.

Why this answer

Project Support and Change Authority are optional roles in PRINCE2. The other roles are mandatory.

1392
Multi-Selectmedium

Which TWO of the following are steps in the PRINCE2 risk management procedure?

Select 2 answers
A.Monitor
B.Implement
C.Assess
D.Control
E.Allocate
AnswersB, C

Implement involves executing the planned risk responses.

Why this answer

Options B and D are correct. The recommended risk management procedure steps are: Identify, Assess, Plan, Implement, Communicate. 'Assess' includes both probability and impact evaluation. 'Implement' involves executing the planned responses. 'Monitor' and 'Control' are not separate steps; they are part of Implement and Communicate.

1393
MCQhard

A project is using the PRINCE2 product-based planning technique. Which of the following describes the correct sequence of activities?

A.Create Product Breakdown Structure, then Product Flow Diagram, then Product Descriptions
B.Create Product Flow Diagram, then Product Descriptions, then Product Breakdown Structure
C.Write Project Product Description, create Product Descriptions, then Product Breakdown Structure
D.Write Project Product Description, create Product Breakdown Structure, create Product Flow Diagram, then produce Product Descriptions
AnswerD

This is the correct order per PRINCE2.

Why this answer

Product-based planning follows: write Project Product Description, create Product Breakdown Structure, create Product Flow Diagram, then produce Product Descriptions for each product.

1394
MCQmedium

A project is forecast to exceed its cost tolerance. What should the Project Manager do?

A.Close the project immediately as the Business Case is no longer viable
B.Continue and report the cost overrun in the next Highlight Report
C.Raise an Exception Report to the Project Board and await their direction
D.Increase the project budget to absorb the additional cost
AnswerC

Escalation via Exception Report is the correct response.

Why this answer

In PRINCE2, when a project is forecast to exceed its cost tolerance, the Project Manager must escalate the issue to the Project Board via an Exception Report. This is because the Project Manager does not have authority to exceed tolerances; the Project Board must decide whether to approve a revised Business Case, adjust tolerances, or terminate the project. Option C correctly follows the PRINCE2 principle of management by exception.

Exam trap

PeopleCert often tests the misconception that the Project Manager can handle tolerance breaches independently, but PRINCE2 strictly requires escalation to the Project Board via an Exception Report when any tolerance is forecast to be exceeded.

How to eliminate wrong answers

Option A is wrong because closing the project immediately is premature; the Business Case may still be viable if the Project Board approves a revised tolerance or budget. Option B is wrong because waiting for the next Highlight Report violates the PRINCE2 requirement to escalate forecast deviations immediately via an Exception Report, not defer reporting. Option D is wrong because the Project Manager lacks authority to increase the budget unilaterally; only the Project Board can authorize changes to tolerances or budget.

1395
MCQeasy

During the Initiating a Project process, the project manager is reviewing the Business Case. Which statement best describes the purpose of this review?

A.To confirm the project's scope and high-level risks before the project mandate is issued.
B.To authorize work packages for the first stage of the project.
C.To develop a detailed justification for the project and confirm it remains viable.
D.To obtain final approval from the project board before project execution begins.
AnswerC

Initiating a Project refines the Business Case to ensure the project is worthwhile.

Why this answer

Option C is correct because during the Initiating a Project process, the Business Case is reviewed to develop a detailed justification for the project and confirm it remains viable. This involves refining the outline Business Case from the Starting Up a Project process into a fully detailed document that justifies the project's continued existence based on costs, benefits, risks, and timescales. The review ensures the project is still aligned with corporate objectives and that the investment is worthwhile before proceeding to the next stage.

Exam trap

The trap here is that candidates often confuse the purpose of the Initiating a Project process with the Directing a Project process, mistakenly thinking that the Business Case review is for final approval rather than for developing and confirming viability.

How to eliminate wrong answers

Option A is wrong because the project scope and high-level risks are confirmed during the Starting Up a Project process, not during the Initiating a Project process, and the project mandate is issued before the Initiating a Project process begins. Option B is wrong because authorizing work packages for the first stage occurs during the Managing a Stage Boundary process or the Controlling a Stage process, not during the Initiating a Project process. Option D is wrong because obtaining final approval from the project board before project execution begins is the purpose of the Directing a Project process when the project board decides to authorize the project, not a review of the Business Case within the Initiating a Project process.

1396
MCQhard

During the Managing a Stage Boundary process, the Project Manager reviews the Business Case and finds that the expected benefits are no longer achievable. What should the Project Manager do?

A.Create an Exception Plan to revise the benefits
B.Continue with the next stage as planned and report the issue in the End Project Report
C.Recommend to the Project Board that the project should be closed as the Business Case is no longer viable
D.Close the project immediately without consulting the Project Board
AnswerC

The Project Manager should escalate to the Project Board, which may decide to close the project.

Why this answer

If the Business Case is no longer viable, the Project Manager should recommend to the Project Board that the project is not worthwhile. The Board decides whether to continue or close. Option A is wrong because continuing without addressing the issue is not acceptable.

Option C is wrong because the PM does not unilaterally close the project. Option D is wrong because an Exception Plan is for tolerance deviations, not for a failed Business Case.

1397
MCQmedium

A project is forecast to exceed its cost tolerance. What should the Project Manager do?

A.Continue with the current plan and report the cost overrun in the next Highlight Report
B.Raise an Exception Report to the Project Board and await their direction
C.Increase the project budget to absorb the additional cost and continue with the current plan
D.Close the project immediately as the Business Case is no longer viable
AnswerB

This is the correct escalation procedure.

Why this answer

When a tolerance is forecast to be exceeded, the Project Manager must escalate to the Project Board via an Exception Report. This is management by exception.

1398
Multi-Selectmedium

Which THREE of the following are typical response strategies for a threat (negative risk) in PRINCE2?

Select 3 answers
A.Share
B.Avoid
C.Reduce
D.Transfer
E.Exploit
AnswersB, C, D

Avoid is a valid threat response.

Why this answer

Threat response strategies include Avoid, Reduce (Mitigate), Fallback, Transfer, Accept, and Share. Exploit is an opportunity response, not a threat response.

1399
MCQeasy

Which document is the key output of the Initiating a Project process?

A.Project Initiation Documentation
B.End Stage Report
C.Project Brief
D.Exception Report
AnswerA

Correct. PID is the key output of Initiating a Project.

Why this answer

The Project Initiation Documentation (PID) is the key output of IP, consolidating all the information needed to decide whether to authorize the project.

1400
MCQmedium

A Project Manager receives a forecast that a Work Package will exceed its tolerance. What should the PM do?

A.Discuss with the Team Manager to understand the situation and consider options
B.Inform the Senior Supplier and request additional resources
C.Immediately raise an Exception Report to the Project Board
D.Update the Stage Plan with the new forecast
AnswerA

The PM should first understand the issue from the Team Manager.

Why this answer

In PRINCE2, when a Work Package is forecast to exceed its tolerance, the Project Manager must first discuss with the Team Manager to understand the situation and explore options. This aligns with the 'manage by exception' principle, where the PM is responsible for managing within stage tolerances and only escalates to the Project Board if the stage tolerance itself is threatened. The PM must gather detailed information before deciding on corrective actions or escalation.

Exam trap

The trap here is confusing Work Package tolerance with stage tolerance, leading candidates to immediately escalate to the Project Board (Option C) when the correct first step is to discuss with the Team Manager.

How to eliminate wrong answers

Option B is wrong because the PM should not directly inform the Senior Supplier or request additional resources without first understanding the situation and assessing options; the Senior Supplier is a Project Board role, and resource requests must be managed through the stage plan and exception process. Option C is wrong because an Exception Report is only raised when the stage tolerance is forecast to be exceeded, not a Work Package tolerance; the PM must first attempt to resolve within stage tolerance. Option D is wrong because updating the Stage Plan with the new forecast is premature and incorrect; the Stage Plan is a baseline that should only be changed via an approved Exception Plan.

1401
MCQmedium

During the Controlling a Stage process, the Project Manager identifies that the project is forecast to exceed the agreed cost tolerance for the current stage. What should the Project Manager do?

A.Raise an Exception Report to the Project Board and await their direction before proceeding
B.Continue with the current Stage Plan and report the cost overrun in the next Highlight Report
C.Increase the project budget to absorb the additional cost and continue with the current Stage Plan
D.Close the project immediately as the Business Case is no longer viable
AnswerA

When a stage tolerance is forecast to be exceeded, the Project Manager must escalate to the Project Board immediately via an Exception Report. This is management by exception.

Why this answer

Option C is correct. When a stage tolerance is forecast to be exceeded, the Project Manager must escalate to the Project Board immediately via an Exception Report — this is PRINCE2's management by exception principle. The Project Manager cannot unilaterally exceed tolerances (A), continue without escalation (B), or close the project without Board decision (D).

1402
Multi-Selecthard

Which THREE of the following are responsibilities of the Project Board?

Select 3 answers
A.Providing overall direction and control
B.Managing risks on a daily basis
C.Approving the Project Plan
D.Producing Highlight Reports
E.Ensuring project assurance is carried out
AnswersA, C, E

The Project Board provides overall direction.

Why this answer

The Project Board is responsible for providing overall direction, approving plans, and ensuring assurance. Producing Highlight Reports is the PM's responsibility; managing risks on a daily basis is the PM's role.

1403
Drag & Dropmedium

Drag and drop the steps to manage a stage boundary in PRINCE2 into the correct order.

Drag steps to the numbered slots on the right, or tap a step then tap a slot.

Steps
Order

Why this order

Managing a Stage Boundary: plan next stage, update project plan, update business case, report, and produce exception plan if required.

1404
MCQhard

What is the key difference between Project Assurance and quality review?

A.Project Assurance focuses on the Business Case; quality review focuses on the project plan
B.Project Assurance is a role; quality review is a technique
C.Project Assurance is performed by the Project Manager; quality review is performed by the team
D.Project Assurance is done at the end of a stage; quality review is done continuously
AnswerB

Correct: Project Assurance is a role defined in PRINCE2; quality review is a product-based technique.

Why this answer

Project Assurance is an independent, ongoing role providing objective oversight to the Project Board. Quality review is a specific technique for reviewing product quality at defined points.

1405
MCQmedium

Which document is the key output of the Initiating a Project process?

A.Business Case
B.Project Brief
C.Project Plan
D.Project Initiation Documentation
AnswerD

The PID is the definitive document produced during initiation.

Why this answer

The Project Initiation Documentation (PID) is the primary output of the Initiating a Project process. It provides the basis for the Project Board to decide whether to proceed.

1406
MCQhard

What is the difference between a Request for Change and an Off-specification?

A.A Request for Change is raised by the Project Manager; an Off-specification is raised by the Senior User
B.There is no difference; they are alternative terms for the same thing
C.A Request for Change seeks to modify a baselined product; an Off-specification identifies a failure to meet a specification
D.A Request for Change always requires a change budget; an Off-specification does not
AnswerC

Correct. RFC proposes a change to an agreed baseline; Off-specification is a deviation from the agreed specification.

Why this answer

A Request for Change is a proposal for a modification to a product that has been baselined, while an Off-specification is something that should be provided but is not (or is forecast not to be). The key difference is that RFC is about changing what was agreed, whereas Off-spec is about failing to deliver what was agreed.

1407
MCQmedium

Who produces Checkpoint Reports?

A.Project Board
B.Senior User
C.Project Manager
D.Team Manager
AnswerD

The Team Manager produces Checkpoint Reports to report progress on Work Packages.

Why this answer

Checkpoint Reports are produced by the Team Manager and sent to the Project Manager as part of Managing Product Delivery.

1408
MCQmedium

Which document is the key output of the Initiating a Project process?

A.Business Case
B.Project Brief
C.Stage Plan
D.Project Initiation Documentation
AnswerD

The PID is the main output of Initiating a Project.

Why this answer

The Project Initiation Documentation (PID) is the key output of the Initiating a Project process. It defines the project and forms the basis for its management. The Project Plan is part of the PID.

1409
MCQmedium

A project manager is reviewing the business case for a new product development project. The project board has expressed concern that the benefits may not be realized as planned. Which management product should the project manager update to address this concern?

A.Benefits Management Approach
B.Business Case
C.Project Plan
D.Risk Register
AnswerA

This approach defines how benefits will be measured and reviewed, addressing the board's concern.

Why this answer

The Benefits Management Approach defines how the project's benefits will be measured, tracked, and realized throughout the project and into operations. Since the project board is concerned about benefits realization, updating this approach with revised measurement criteria, review timing, or ownership details directly addresses their concern by providing a clear plan for ensuring benefits are achieved.

Exam trap

The trap here is that candidates often confuse the Business Case (which justifies the project) with the Benefits Management Approach (which manages how benefits are tracked and realized), leading them to incorrectly select the Business Case when the question specifically asks about addressing realization concerns.

How to eliminate wrong answers

Option B is wrong because the Business Case documents the justification for the project, including costs, benefits, and risks, but it does not detail the ongoing management and measurement of benefits realization; updating it would not provide the specific tracking plan needed. Option C is wrong because the Project Plan focuses on the schedule, resources, and activities to deliver the project's products, not on how benefits will be realized after delivery. Option D is wrong because the Risk Register captures individual risks and their responses, but benefits realization is a broader management concern that requires a dedicated approach document, not just a risk entry.

1410
MCQmedium

Which of the following distinguishes a Highlight Report from a Checkpoint Report?

A.The Checkpoint Report is produced by the Project Manager, while the Highlight Report is produced by the Team Manager
B.The Highlight Report is produced at the end of each stage, while the Checkpoint Report is produced monthly
C.The Highlight Report includes a summary of risks, while the Checkpoint Report does not
D.The Highlight Report is sent to the Project Board, while the Checkpoint Report is sent to the Project Manager
AnswerD

This is the main distinction in terms of audience.

Why this answer

Option D is correct because in PRINCE2, the Highlight Report is a formal report from the Project Manager to the Project Board, providing a summary of progress, risks, and issues at predefined intervals during a stage. The Checkpoint Report is produced by the Team Manager for the Project Manager, detailing progress against the Work Package. This distinction in audience and purpose is a core PRINCE2 principle.

Exam trap

PeopleCert often tests the confusion between the producer and recipient of these reports, especially the misconception that the Checkpoint Report goes to the Project Board or that the Highlight Report is produced by the Team Manager.

How to eliminate wrong answers

Option A is wrong because it reverses the roles: the Checkpoint Report is produced by the Team Manager, while the Highlight Report is produced by the Project Manager. Option B is wrong because the Highlight Report is produced at intervals defined in the stage plan (not necessarily at the end of each stage), and the Checkpoint Report frequency is also defined in the Work Package (not necessarily monthly). Option C is wrong because both reports can include a summary of risks and issues; the Highlight Report always includes a risk summary, but the Checkpoint Report may also include risks relevant to the Work Package.

1411
MCQeasy

A project team is working on a complex infrastructure project. The project manager wants to ensure that the project is tailored appropriately. According to PRINCE2, which principle addresses the need to adapt PRINCE2 to the project's specific context?

A.Continued business justification
B.Focus on products
C.Manage by stages
D.Tailor to suit the project environment
AnswerD

This principle ensures PRINCE2 is adapted appropriately.

Why this answer

The 'Tailor to suit the project environment' principle directly addresses the need to adapt PRINCE2 to the specific context of the project, including its size, complexity, importance, capability, and risk. For a complex infrastructure project, this means adjusting management products, roles, and processes (e.g., simplifying the Business Case or using a more detailed Risk Register) to fit the project's unique technical and organizational environment, ensuring the method remains effective without being overly burdensome.

Exam trap

PeopleCert often tests the distinction between the 'Tailor to suit the project environment' principle and the 'Manage by stages' principle, as candidates may confuse adapting the method's processes with the structural decision to break the project into stages.

How to eliminate wrong answers

Option A is wrong because 'Continued business justification' ensures the project remains viable and aligned with business objectives, but it does not address the adaptation of PRINCE2 to the project's specific context. Option B is wrong because 'Focus on products' emphasizes defining and delivering products with agreed quality criteria, not tailoring the method itself. Option C is wrong because 'Manage by stages' involves planning, monitoring, and controlling the project in stages, which is a structural element of PRINCE2, not a principle about adapting the method to the project environment.

1412
MCQhard

What is the difference between a Request for Change and an Off-specification?

A.A Request for Change is only used during delivery; an Off-specification is only used during closure
B.A Request for Change is proposed by the Project Board; an Off-specification is proposed by the Project Manager
C.A Request for Change seeks to modify a baselined product; an Off-specification identifies a product that does not meet its specification
D.There is no difference; the terms are interchangeable
AnswerC

Correct. RFC: change to specification; Off-spec: failure to meet specification.

Why this answer

A Request for Change is a proposal for a change, while an Off-specification is something that should be there but isn't.

1413
Multi-Selecthard

Which THREE of the following are types of issue defined in PRINCE2?

Select 3 answers
A.Request for Change
B.Problem/Concern
C.Risk
D.Off-specification
E.Change request
AnswersA, B, D

An RFC is a formal proposal for a change.

Why this answer

PRINCE2 defines three issue types: Request for Change, Off-specification, and Problem/Concern. Options A, B, and D are correct. Options C and E are not issue types.

1414
MCQmedium

During which process does the Project Board authorize the project to proceed?

A.Controlling a Stage
B.Starting Up a Project
C.Directing a Project
D.Initiating a Project
AnswerD

At the end of IP, the Project Board reviews the PID and authorizes the project to proceed.

Why this answer

The correct answer is D, Initiating a Project, because this process is where the Project Board reviews the Initiation Stage Plan and the Business Case, then formally authorizes the project to proceed by approving the project initiation. This authorization triggers the transition from planning to execution, giving the Project Manager authority to start the first delivery stage.

Exam trap

PeopleCert often tests the distinction between 'Directing a Project' (the overarching decision-making process) and 'Initiating a Project' (the specific process where authorization to proceed is given), leading candidates to mistakenly choose Directing a Project because it covers all board-level authorizations.

How to eliminate wrong answers

Option A is wrong because Controlling a Stage is the process for monitoring and managing work within an already-authorized stage, not for authorizing the project to start. Option B is wrong because Starting Up a Project is a pre-project process that only produces the Project Mandate and appoints the Executive and Project Manager, but does not include authorization to proceed; that occurs later. Option C is wrong because Directing a Project is the process that covers the Project Board's overall decision-making, including authorizations, but the specific authorization to proceed with the project happens during the Initiating a Project process, not as a standalone activity within Directing a Project.

1415
Multi-Selecthard

Which THREE of the following are components of the Project Initiation Documentation (PID)?

Select 3 answers
A.Risk Register
B.Project Plan
C.Lessons Log
D.Work Package
E.Business Case
AnswersA, B, E

Correct. The Risk Register is part of the PID.

Why this answer

The PID includes the Business Case, Project Plan, and Risk Register. The Lessons Log is separate; the Work Package is created later.

1416
MCQmedium

Based on the exhibit, what is the current risk exposure of risk R1?

A.Low
B.Very High
C.Medium
D.High
AnswerC

Low probability combined with High impact typically gives a Medium risk exposure.

Why this answer

Risk exposure is calculated as the product of probability and impact. In the exhibit, risk R1 has a probability of 'Medium' (0.3–0.7) and an impact of 'Medium' (0.3–0.7). Multiplying the midpoints (0.5 × 0.5 = 0.25) or using the ranges, the resulting exposure falls within the 'Medium' category on the PRINCE2 risk matrix.

Therefore, the current risk exposure is correctly identified as Medium.

Exam trap

The trap here is that candidates often confuse the individual probability or impact rating with the combined risk exposure, mistakenly selecting 'High' or 'Very High' when only one factor is elevated, or 'Low' when both are medium, instead of correctly calculating the product.

How to eliminate wrong answers

Option A is wrong because 'Low' would require both probability and impact to be low (e.g., 0.1–0.3 each), but R1 has medium probability and medium impact. Option B is wrong because 'Very High' requires both probability and impact to be very high (e.g., 0.9–1.0 each), which is not the case for R1. Option D is wrong because 'High' would require at least one factor to be high (e.g., 0.7–0.9) and the other medium or high, but R1 has both factors at medium, yielding a medium exposure.

1417
MCQmedium

What is the purpose of the Managing a Stage Boundary process?

A.To direct the work of the project team
B.To ensure that the project remains viable by reviewing the Business Case
C.To capture lessons throughout the project
D.To authorize the initiation of the project
AnswerB
1418
MCQmedium

During the Initiating a Project process, which document is created that defines how the project will be controlled?

A.Business Case
B.Project Brief
C.Stage Plan
D.Project Initiation Documentation (PID)
AnswerD

Correct. The PID defines the project and includes management controls.

Why this answer

The Project Initiation Documentation (PID) is the key document created during the Initiating a Project process that defines how the project will be controlled. It consolidates the project's scope, objectives, and controls, including the management stages, tolerances, and reporting arrangements, providing a baseline for decision-making and governance throughout the project.

Exam trap

The trap here is confusing the Project Brief (a high-level outline created in Starting Up a Project) with the PID (the detailed control document created in Initiating a Project), as both contain similar elements but serve different purposes and are created at different process stages.

How to eliminate wrong answers

Option A is wrong because the Business Case is created earlier in the Starting Up a Project process and justifies the project's viability, not how it will be controlled. Option B is wrong because the Project Brief is also created in Starting Up a Project and provides a high-level overview of the project, but it does not define the detailed control mechanisms. Option C is wrong because the Stage Plan is created during the Initiating a Project process for the first management stage, but it is a component of the PID, not the overarching document that defines overall project control.

1419
MCQmedium

The Project Board is meeting to authorize the start of a new stage. According to PRINCE2, how frequently should the Project Board meet?

A.At stage boundaries and when an exception is raised
B.Weekly
C.At the start and end of the project only
D.Monthly
AnswerA

PRINCE2 states the Board meets at key decision points, primarily stage boundaries and when exceptions occur.

Why this answer

The Project Board meets at key decision points, which are exception-driven (when tolerances are forecast to be exceeded) and at stage boundaries. Option D is correct.

1420
Multi-Selecthard

Which THREE of the following are valid threat responses in PRINCE2?

Select 3 answers
A.Enhance
B.Exploit
C.Reduce
D.Avoid
E.Transfer
AnswersC, D, E

Reduce is a threat response to lower the probability or impact.

Why this answer

In PRINCE2, threat responses are actions taken to address negative risks. 'Reduce' (also called 'Mitigate') is a valid response that aims to lower the probability and/or impact of a threat to an acceptable level. This is one of the five standard threat response categories defined in the PRINCE2 risk management practice.

Exam trap

PeopleCert often tests the confusion between threat and opportunity responses, where candidates mistakenly select 'Enhance' or 'Exploit' as valid threat responses because they sound like proactive actions, but PRINCE2 strictly reserves them for positive risks.

1421
Multi-Selectmedium

Which TWO of the following are components of a Business Case?

Select 2 answers
A.Product Description
B.Risk Register
C.Expected benefits
D.Configuration Item Records
E.Investment appraisal
AnswersC, E

Benefits are a key component justifying the project.

Why this answer

The Business Case includes expected benefits and costs (investment appraisal). Options A and B are correct. Options C, D, and E are not standard components.

1422
MCQhard

Which PRINCE2 principle is being applied when the Project Manager escalates a forecast tolerance deviation to the Project Board?

A.Defined Roles and Responsibilities
B.Learn from Experience
C.Manage by Exception
D.Continued Business Justification
AnswerC

This principle sets tolerances and escalates when they are forecast to be exceeded.

Why this answer

The 'Manage by Exception' principle is applied when the Project Manager escalates a forecast tolerance deviation to the Project Board. This principle delegates decision-making authority within defined tolerances; only when a deviation is forecast to exceed those tolerances does the Project Manager escalate to the Project Board for a decision. The escalation triggers exception management, ensuring the board retains control at key decision points without micromanaging day-to-day activities.

Exam trap

The trap here is that candidates confuse 'Manage by Exception' with 'Defined Roles and Responsibilities', because escalation involves roles, but the principle specifically governing tolerance-based escalation is 'Manage by Exception', not role definition.

How to eliminate wrong answers

Option A is wrong because 'Defined Roles and Responsibilities' ensures each team member knows their duties and authority levels, but it does not specifically address the escalation of tolerance deviations; that is the function of 'Manage by Exception'. Option B is wrong because 'Learn from Experience' focuses on capturing and applying lessons throughout the project, not on the escalation mechanism for tolerance breaches. Option D is wrong because 'Continued Business Justification' requires ongoing validation that the project remains viable, but it does not prescribe the escalation process for tolerance deviations; that is handled by 'Manage by Exception'.

1423
Multi-Selecteasy

Which TWO of the following are components of the Business Case?

Select 2 answers
A.Project Plan
B.Expected benefits
C.Product Breakdown Structure
D.Quality Register
E.Major risks
AnswersB, E

Benefits are a key component.

Why this answer

The Business Case includes expected benefits, costs, timescales, major risks, etc. Options, investment appraisal, and dis-benefits are also components.

1424
MCQmedium

What is the difference between Starting Up a Project and Initiating a Project?

A.SU initiates the project; IP plans the first stage
B.SU produces the Project Brief; IP produces the Project Initiation Documentation
C.SU is done by the Project Manager; IP is done by the Project Board
D.SU authorizes the project; IP manages the project
AnswerB

SU outputs the Project Brief; IP outputs the PID, which includes more detailed plans and approaches.

Why this answer

Starting Up a Project (SU) is the pre-project process that produces the Project Brief, which includes the outline business case and project approach. Initiating a Project (IP) is the second process that produces the Project Initiation Documentation (PID), which contains the detailed plans, business case, and risk register needed to justify proceeding with the project. The key distinction is that SU creates the high-level Project Brief, while IP creates the comprehensive PID.

Exam trap

The trap here is that candidates confuse the outputs of SU and IP, often thinking SU produces the PID or that IP produces the Project Brief, when in fact SU produces the Project Brief and IP produces the PID.

How to eliminate wrong answers

Option A is wrong because SU does not initiate the project; it is a pre-project process that prepares the groundwork, while IP plans the entire project, not just the first stage. Option C is wrong because SU is managed by the Executive (not the Project Manager) and involves the Project Board for approval, while IP is led by the Project Manager but still requires Project Board authorization. Option D is wrong because SU does not authorize the project; authorization occurs at the end of IP when the Project Board approves the PID, and IP does not manage the project—that is the role of the Managing a Stage Boundary and Controlling a Stage processes.

1425
MCQmedium

The Project Board has received an Exception Report from the Project Manager. What is the Project Board's next step?

A.Approve the Exception Report
B.Request a new Project Plan
C.Request an Exception Plan to assess options
D.Close the project
AnswerC

Why this answer

When the Project Board receives an Exception Report, they typically request an Exception Plan to evaluate options. They then decide whether to approve the plan, which may involve changes to the project. A new Project Plan may be part of the Exception Plan, but the immediate step is to request the plan.

Page 18

Page 19 of 24

Page 20