In PRINCE2, who is responsible for defining the change budget?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

The Project Board

The Project Board approves the change budget as part of the project's risk and change management approach.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • The Senior User

    Why it's wrong here

    The Senior User may request changes but does not set the budget.

  • The Change Authority

    Why it's wrong here

    The Change Authority uses the budget but does not define it.

  • The Project Manager

    Why it's wrong here

    The Project Manager recommends but does not define.

  • The Project Board

    Why this is correct

    The Project Board sets the change budget as part of project authorisation.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.