PRINCE2 Foundation (PRINCE2F) — Questions 676750

1731 questions total · 24pages · All types, answers revealed

Page 9

Page 10 of 24

Page 11
676
MCQhard

A project has identified a risk that could impact the project's schedule. The team decides to allocate extra resources to ensure the schedule is met despite the risk. Which risk response is being applied?

A.Reduce
B.Transfer
C.Accept
D.Avoid
AnswerA

Reduce involves actions to lower the probability or impact of a threat. Allocating extra resources reduces the impact on the schedule.

Why this answer

Allocating extra resources to ensure an opportunity is realized (or a threat is mitigated) is an 'enhance' response for opportunities. However, for threats, 'reduce' involves actions to lower probability or impact. The scenario describes a threat (schedule impact), and allocating extra resources reduces the impact; thus it is 'reduce'.

The question might be ambiguous, but the correct PRINCE2 term for threat is 'reduce'.

677
MCQeasy

Who is responsible for producing Highlight Reports?

A.Project Manager
B.Team Manager
C.Project Board
D.Senior User
AnswerA

The Project Manager produces Highlight Reports to inform the Project Board of stage progress.

Why this answer

Highlight Reports are produced by the Project Manager and sent to the Project Board during the Controlling a Stage process. Checkpoint Reports are produced by Team Managers.

678
MCQhard

What is the difference between a Highlight Report and an Exception Report?

A.Highlight Reports are produced by the Team Manager; Exception Reports by the Project Manager
B.Highlight Reports are periodic; Exception Reports are triggered by a tolerance deviation
C.Highlight Reports contain financial information; Exception Reports contain schedule information
D.Highlight Reports are for the Project Board; Exception Reports are for the Project Manager
AnswerB

The key difference is the trigger: periodic vs. exception.

Why this answer

A Highlight Report is periodic and reports progress within tolerances; an Exception Report is triggered when a tolerance is forecast to be exceeded.

679
MCQeasy

What is the purpose of the Starting Up a Project process?

A.To decide whether it is worthwhile to initiate the project
B.To close the project in a controlled manner
C.To assign work packages to the Team Manager
D.To produce a detailed Project Plan for the entire project
AnswerA

Correct. SU determines if the project is viable before moving to initiation.

Why this answer

Starting Up a Project is a pre-project process to ensure that there is a viable and worthwhile project before committing to significant resources. It creates the Project Brief and Initiation Stage Plan.

680
MCQhard

What is the difference between a Request for Change (RFC) and an Off-specification (Off-spec)?

A.Both are the same
B.An Off-spec is to change something; an RFC is a product not meeting specification
C.Both are handled only by the Project Board
D.An RFC is to change something; an Off-spec is a product not meeting specification
AnswerD

Correct distinction.

Why this answer

An RFC proposes a change to agreed baselines; an Off-spec is a product that does not meet its specification.

681
Multi-Selecthard

Which THREE of the following are elements of the PRINCE2 quality practice?

Select 3 answers
A.Quality Assurance
B.Configuration Management
C.Risk Management
D.Quality Control
E.Quality Planning
AnswersA, D, E

Quality Assurance ensures processes are followed.

Why this answer

The quality practice includes Quality Planning, Quality Control, and Quality Assurance. Configuration Management is part of the Change practice.

682
MCQeasy

In PRINCE2, who is accountable for the project's success and the realization of benefits?

A.Senior Responsible Owner (SRO)
B.Project Manager
C.Senior User
D.Senior Supplier
AnswerA

The SRO is the single point of accountability for the project and its benefits.

Why this answer

The Senior Responsible Owner (SRO) is the single person accountable for the project's success and the realization of benefits.

683
MCQmedium

During the Initiating a Project process, which document is created that defines how the project will be controlled and governed?

A.Project Initiation Documentation (PID)
B.Project Brief
C.Project Plan
D.Business Case
AnswerA

The PID is the comprehensive document that defines how the project will be controlled.

Why this answer

The Project Initiation Documentation (PID) is the key output of the Initiating a Project process. It provides the foundation for project governance and control.

684
MCQhard

What is the difference between Project Assurance and Project Support?

A.Project Assurance provides independent oversight, while Project Support provides administrative services
B.Project Assurance is part of the Project Manager's team, while Project Support is independent
C.Project Assurance manages quality control, while Project Support manages the Risk Register
D.Project Assurance is only required for large projects, while Project Support is always required
AnswerA

This correctly distinguishes the two roles.

Why this answer

Option B is correct. Project Assurance provides independent oversight and is accountable to the Project Board, while Project Support provides administrative services to the Project Manager and team. Option A is wrong because Project Assurance is not part of the Project Manager's team.

Option C is wrong because both roles can exist in any project. Option D is wrong because Project Support is not responsible for quality control.

685
Multi-Selectmedium

Which THREE of the following are roles on the Project Board?

Select 3 answers
A.Project Manager
B.Senior User
C.Senior Supplier
D.Project Assurance
E.Senior Responsible Owner (Executive)
AnswersB, C, E

The Senior User represents users on the Board.

Why this answer

The PRINCE2 Project Board is the decision-making body responsible for overall project governance. It comprises three roles: the Executive (Senior Responsible Owner), the Senior User, and the Senior Supplier. The Senior User represents the interests of those who will use the project's outputs and is essential for defining requirements and benefits.

Exam trap

The trap here is that candidates often confuse the Project Manager (a management role) with a Project Board role, or mistakenly think Project Assurance is a board role rather than a separate oversight function.

686
MCQmedium

In a PRINCE2 project, the Project Manager submits an Exception Report. What is the most likely trigger for this report?

A.The Project Manager needs to request additional resources within the current stage tolerance
B.A team member reports a minor delay that can be accommodated within tolerance
C.The project is forecast to exceed the stage cost tolerance
D.The Senior User requests a change that does not affect the Business Case
AnswerC

A forecast tolerance breach triggers an Exception Report to the Project Board.

Why this answer

In PRINCE2, an Exception Report is triggered when a forecast indicates that a stage will exceed its agreed tolerance (e.g., cost or time). Option C is correct because exceeding stage cost tolerance is a formal deviation that requires escalation to the Project Board via an Exception Report, as the Project Manager cannot authorize changes beyond tolerance.

Exam trap

The trap here is confusing an Exception Report (triggered by tolerance breach) with an Issue Report or Change Request (triggered by problems or changes within tolerance).

How to eliminate wrong answers

Option A is wrong because requesting additional resources within the current stage tolerance does not require an Exception Report; the Project Manager can handle this within delegated authority. Option B is wrong because a minor delay accommodated within tolerance is managed within the stage plan and does not trigger an Exception Report. Option D is wrong because a change requested by the Senior User that does not affect the Business Case is typically handled via a Change Request or Issue Report, not an Exception Report, as it does not breach tolerance.

687
Multi-Selectmedium

Which TWO of the following are outputs of the Initiating a Project process?

Select 2 answers
A.Project Plan
B.Project Initiation Documentation
C.Risk Register
D.Project Brief
E.Business Case
AnswersB, E

The PID is the key output.

Why this answer

The PID and Business Case are refined and approved during Initiating a Project. The Project Brief is from Starting Up a Project, and the Risk Register is created during this process but not listed as a key output; it's part of the PID. However, the question asks for outputs, and both PID and Business Case are key outputs.

688
MCQhard

What is the difference between a Request for Change and an Off-specification?

A.An Off-specification is something that should be provided but is not, while a Request for Change is a proposal to change a baseline
B.A Request for Change always requires a change budget, while an Off-specification does not
C.A Request for Change is raised by the Project Board, while an Off-specification is raised by the Project Manager
D.An Off-specification is recorded in the Risk Register, while a Request for Change is in the Issue Register
AnswerA

This correctly distinguishes the two.

Why this answer

A Request for Change is a proposed modification to a baseline, while an Off-specification is a failure to meet a requirement. Option B is correct.

689
Multi-Selectmedium

Which TWO statements about the Risk practice are correct?

Select 2 answers
A.The risk budget is used to fund the project's activities.
B.A risk owner must be identified for each risk.
C.Only threats are considered as risks.
D.The risk register is optional if the project is small.
E.The risk management approach defines how risks will be managed.
AnswersB, E

Each risk must have a risk owner who is responsible for managing the risk.

Why this answer

Option B is correct because PRINCE2 requires that each risk has a named risk owner who is accountable for managing that risk and implementing the planned responses. This ensures clear accountability and proactive risk management throughout the project lifecycle.

Exam trap

PeopleCert often tests the misconception that the risk budget can be used for general project activities, but PRINCE2 strictly reserves it for funding risk responses, not operational tasks.

690
MCQmedium

Which role is responsible for securing project funding and for the Business Case?

A.Executive
B.Project Manager
C.Senior User
D.Senior Supplier
AnswerA

The Executive is the single point of accountability for the Business Case.

Why this answer

The Executive (also known as Senior Responsible Owner) is accountable for the Business Case and securing funding.

691
MCQmedium

Which document describes the user's needs and expectations for the project's products?

A.Stage Plan
B.Project Brief
C.Project Product Description
D.Business Case
AnswerC

This describes the final product, including user expectations and acceptance criteria.

Why this answer

The Project Product Description defines the overall product and its expectations, including user needs, but the User Requirements document captures detailed user needs. However, in PRINCE2, the Project Product Description is the key document for defining what the user expects.

692
Multi-Selectmedium

Which THREE of the following are activities performed in the Controlling a Stage process?

Select 3 answers
A.Report highlights to the Project Board
B.Produce End Stage Report
C.Deliver work packages
D.Authorize Work Packages
E.Review progress and update the stage plan
AnswersA, D, E

Highlight Reports are sent to the Project Board during CS.

Why this answer

CS includes authorizing Work Packages, reviewing progress, and reporting highlights. Producing the End Stage Report is done in SB.

693
Multi-Selectmedium

Which TWO of the following are aspects of project performance that PRINCE2 considers?

Select 2 answers
A.Resources
B.Risk
C.Time
D.Value
E.Customer satisfaction
AnswersB, C

Risk is one of the six performance aspects.

Why this answer

PRINCE2 defines six aspects of project performance that must be managed: Costs, Time, Quality, Scope, Risk, and Benefits. Risk (Option B) and Time (Option C) are explicitly included in this set. These aspects are used to measure and control project success throughout the lifecycle.

Exam trap

The trap here is that candidates often confuse 'Resources' (a common project management term) with the PRINCE2-specific 'Costs' aspect, or they mistakenly think 'Value' is a direct aspect when it is actually a subset of 'Benefits'.

694
MCQhard

What is the key difference between Project Assurance and a quality review?

A.There is no difference; they are synonymous
B.Project Assurance is a one-time activity, while quality reviews are continuous
C.Project Assurance is performed by the Project Manager, while a quality review is performed by the team
D.Project Assurance focuses on the project's compliance with PRINCE2, while a quality review focuses on product quality
AnswerD

Project Assurance checks adherence to standards and processes; quality review checks product fitness for purpose.

Why this answer

Project Assurance is an independent oversight role ensuring the project stays on track, while a quality review is a specific technique to assess the quality of products.

695
MCQhard

During the Managing Product Delivery process, the Team Manager completes a product. What should happen next?

A.The Team Manager delivers the product to the customer directly
B.The Project Board approves the product immediately
C.The product is automatically accepted and the Work Package is closed
D.The Team Manager updates the Quality Register and informs the Project Manager
AnswerD

The Team Manager records completion and informs the PM.

Why this answer

The Team Manager should notify the Project Manager that the product is ready for acceptance. The PM arranges quality review and acceptance.

696
MCQeasy

Who is responsible for maintaining the Business Case throughout the project?

A.Senior Responsible Owner (SRO/Executive)
B.Project Assurance
C.Project Manager
D.Senior User
AnswerA

The SRO is accountable for the Business Case throughout the project.

Why this answer

The Senior Responsible Owner (SRO/Executive) is accountable for the Business Case and must ensure it remains viable. The Project Manager develops and maintains it on behalf of the SRO.

697
MCQeasy

What is the primary purpose of the Project Support role in PRINCE2?

A.To provide independent assurance to the Project Board
B.To approve Work Packages
C.To provide administrative support, such as maintaining files and tools
D.To manage the day-to-day activities of the project
AnswerC

Project Support handles the administrative aspects of the project.

Why this answer

Project Support provides administrative and support services to the project team. It is an optional role.

698
Multi-Selectmedium

Which TWO of the following are responsibilities of the Project Assurance role?

Select 2 answers
A.To manage the project team on a daily basis
B.To allocate Work Packages to teams
C.To monitor project compliance with PRINCE2 processes
D.To administer project documentation
E.To provide independent advice to the Project Board on project status
AnswersC, E

Assurance ensures the project follows processes correctly.

Why this answer

Project Assurance independently monitors compliance with standards and assesses risks and issues, reporting to the Project Board. It does not manage day-to-day or provide admin support.

699
MCQhard

In the Managing Product Delivery process, who produces Checkpoint Reports?

A.Team Manager
B.Project Manager
C.Project Assurance
D.Project Board
AnswerA

Why this answer

Checkpoint Reports are produced by the Team Manager (or team members) and sent to the Project Manager to report progress on a Work Package.

700
MCQeasy

What is the definition of quality in PRINCE2?

A.The lowest cost to produce
B.Customer satisfaction
C.Fit for purpose
D.Zero defects
AnswerC

This is the correct definition: the product must be suitable for its intended use.

Why this answer

Option C is correct. PRINCE2 defines quality as 'fit for purpose' — the product must meet the needs of the user. Option A is wrong because zero defects is not the PRINCE2 definition.

Option B is wrong because quality is not about cost efficiency. Option D is wrong because customer satisfaction is a broader concept.

701
MCQmedium

A project manager is reviewing progress and identifies a product that does not meet its quality criteria. What should the project manager do?

A.Raise an Issue for the Project Board to decide
B.Update the product description to match the delivered product
C.Raise an Issue and decide on corrective action within delegated authority
D.Accept the product as-is and update the quality register
AnswerC

Why this answer

If a product does not meet quality criteria, the Project Manager should raise an Issue (specifically an Off-specification) and decide on corrective action.

702
MCQeasy

Who is responsible for maintaining the Business Case throughout the project?

A.Senior Responsible Owner (SRO)
B.Project Manager
C.Senior User
D.Project Support
AnswerA

The SRO is responsible for the Business Case and its ongoing viability.

Why this answer

The Senior Responsible Owner (SRO/Executive) is accountable for the Business Case and ensuring it remains viable. Option A is correct.

703
MCQhard

A project manager is preparing the End Stage Report for the second stage. The project's planned budget for the stage is $500,000, but actual costs are $520,000. The project board is concerned about cost overrun. What is the most appropriate action for the project manager?

A.Request immediate additional budget from the project board before submitting the report.
B.Ignore the overrun because it is within the tolerance set by the project board.
C.Include the cost variance and updated forecast in the End Stage Report and submit it.
D.Raise an exception report to the project board immediately.
AnswerC

The report should highlight variances and forecasts for the next stage.

Why this answer

Option C is correct because the End Stage Report is the formal mechanism to report stage performance, including cost variances, to the Project Board. The project manager must include the actual cost ($520,000) against the planned budget ($500,000) and provide an updated forecast, allowing the board to make an informed decision. This aligns with PRINCE2's management by exception principle, where variances within tolerance are reported in the End Stage Report, not via an exception report.

Exam trap

PeopleCert often tests the distinction between reporting variances within tolerance (End Stage Report) versus exceeding tolerance (Exception Report), and the trap here is assuming any cost overrun automatically triggers an exception report, ignoring the role of tolerance thresholds.

How to eliminate wrong answers

Option A is wrong because requesting additional budget before submitting the End Stage Report bypasses the formal reporting process; the board needs the full stage context (including variance and forecast) to assess the request. Option B is wrong because ignoring the overrun is a violation of PRINCE2's continuous justification principle; the project manager must report all variances, even if within tolerance, as the End Stage Report is the mandatory communication vehicle. Option D is wrong because an exception report is only raised when the stage's forecast indicates that tolerance will be exceeded; here, the actual cost is $520,000, but without evidence that the tolerance (e.g., ±10% of $500,000) is breached, an exception report is premature and inappropriate.

704
Multi-Selectmedium

Which THREE of the following are roles in the project management team?

Select 3 answers
A.Executive
B.Risk Actionee
C.Senior User
D.Change Authority
E.Project Manager
AnswersA, C, E

The Executive is a key role on the Project Board.

Why this answer

The project management team includes the Project Board (Executive, Senior User, Senior Supplier), Project Manager, Team Manager, and Project Assurance. Project Support is also a role but not part of the management team? Actually Project Support is a role. The three correct ones are Executive, Senior User, and Project Manager.

705
Multi-Selectmedium

Which TWO of the following are outputs of the Initiating a Project process?

Select 2 answers
A.Benefits Management Approach
B.Project Brief
C.Project Initiation Documentation
D.Daily Log
E.End Project Report
AnswersA, C

Created in IP.

Why this answer

The PID and Benefits Management Approach are outputs of IP. The Project Brief is from SU. The Daily Log is from SU.

The End Project Report is from CP.

706
Multi-Selectmedium

Which TWO of the following are responsibilities of the Project Board?

Select 2 answers
A.Write Work Packages
B.Perform Project Assurance
C.Manage the project on a day-to-day basis
D.Provide resources and authorize funds
E.Authorize stage plans and major deviations
AnswersD, E

The Project Board ensures resources are available.

Why this answer

Option D is correct because the Project Board is responsible for providing resources and authorizing funds for the project. This is a key duty of the board, as they own the business case and must ensure the project remains viable by approving the necessary budget and resource allocation.

Exam trap

The trap here is confusing the Project Board's strategic oversight responsibilities (like authorizing stage plans and providing resources) with the Project Manager's tactical duties (like writing Work Packages or day-to-day management), leading candidates to select options A or C instead of the correct pair D and E.

707
MCQhard

A Work Package has been authorized, but the Team Manager discovers that the work will require more effort than estimated. The tolerance for the Work Package is insufficient. What should the Team Manager do?

A.Continue working and report the issue in the next Checkpoint Report
B.Raise an Exception Report directly to the Project Board
C.Revise the Work Package and continue
D.Inform the Project Manager and request guidance on how to proceed
AnswerD

Correct. The Team Manager escalates to the PM, who may adjust the Work Package or escalate further.

Why this answer

The Team Manager should escalate to the Project Manager via the Managing Product Delivery process. The Project Manager will decide to revise the Work Package or raise an exception.

708
MCQmedium

In PRINCE2, what is the definition of quality?

A.Highest possible standard
B.Fit for purpose
C.Zero defects
D.Conformance to specification
AnswerB

The PRINCE2 definition of quality is 'fit for purpose'.

Why this answer

PRINCE2 defines quality as 'fit for purpose' — meeting agreed requirements and fulfilling its purpose.

709
MCQmedium

A project is forecast to exceed its stage cost tolerance. What should the Project Manager do?

A.Continue and report in the next Highlight Report
B.Close the project as the Business Case is no longer viable
C.Raise an Exception Report to the Project Board
D.Increase the stage budget to absorb the overrun
AnswerC

Management by exception requires immediate escalation.

Why this answer

When a tolerance is forecast to be exceeded, the Project Manager must escalate to the Project Board via an Exception Report immediately.

710
MCQmedium

What is the purpose of the Risk Register?

A.To approve risk budgets
B.To report progress to stakeholders
C.To capture and track information about identified risks throughout the project
D.To record all decisions made by the Project Board
AnswerC

Correct: the Risk Register is used for recording and tracking risks.

Why this answer

The Risk Register records identified risks, their analysis, and planned responses.

711
MCQmedium

A project is forecast to exceed its cost tolerance for the current stage. What should the Project Manager do?

A.Increase the project budget to absorb the additional cost and continue with the current Stage Plan
B.Continue with the current Stage Plan and report the cost overrun in the next Highlight Report
C.Close the project immediately as the Business Case is no longer viable
D.Raise an Exception Report to the Project Board and await their direction before proceeding
AnswerD

Correct. The PM must escalate immediately via an Exception Report.

Why this answer

In PRINCE2, when a stage is forecast to exceed its cost tolerance, the Project Manager must escalate the issue to the Project Board by raising an Exception Report. This is because the Project Manager does not have authority to exceed the agreed tolerance; the Project Board must decide whether to approve a revised plan or take other corrective action. Option D correctly follows the PRINCE2 exception management process.

Exam trap

The trap here is that candidates may think the Project Manager can adjust the budget or delay reporting, but PRINCE2 strictly requires immediate escalation via an Exception Report when tolerances are forecast to be exceeded.

How to eliminate wrong answers

Option A is wrong because the Project Manager cannot unilaterally increase the project budget; only the Project Board can authorize a budget change, and doing so without approval violates the delegated authority and tolerance levels. Option B is wrong because the Project Manager must report the forecast overrun immediately via an Exception Report, not wait for the next Highlight Report, as this would delay necessary corrective action and breach the management by exception principle. Option C is wrong because the Business Case may still be viable; the Project Board should assess the situation and decide whether to continue, amend, or close the project, not the Project Manager unilaterally.

712
MCQmedium

In PRINCE2, the Project Board should meet at which frequency?

A.Weekly
B.Monthly
C.Exception-driven (triggered by management by exception)
D.Daily
AnswerC

Correct: the Board meets when exceptions occur or for stage boundaries.

Why this answer

The Project Board meets on an exception-driven basis, i.e., when decisions are needed due to deviations or at stage boundaries, not on a fixed schedule.

713
MCQmedium

Which process covers the Project Board's decision to authorize a stage?

A.Directing a Project
B.Controlling a Stage
C.Managing a Stage Boundary
D.Managing Product Delivery
AnswerA

DP is the Project Board process for making key decisions.

Why this answer

Option A is correct. The Directing a Project process covers Project Board decisions, including authorization to start a stage. Controlling a Stage is a Project Manager process.

714
MCQmedium

During the Managing Product Delivery process, the Team Manager delivers products to the Project Manager. What document authorizes the Team Manager to deliver the work?

A.Work Package
B.Project Plan
C.Stage Plan
D.Product Description
AnswerA

Correct. A Work Package authorizes the work for the Team Manager.

Why this answer

A Work Package is the document that authorizes the Team Manager to create one or more products. It contains details of the work to be done and constraints.

715
Multi-Selectmedium

Which TWO of the following are responsibilities of the Senior Responsible Owner (SRO)?

Select 2 answers
A.Managing the day-to-day activities of the project
B.Ensuring the project delivers the expected benefits
C.Maintaining the Business Case
D.Preparing the Project Plan
E.Approving the Work Packages
AnswersB, C

Benefits realization is a key accountability of the SRO.

Why this answer

The SRO owns the Business Case and is accountable for the project's success and benefits realization. They also chair the Project Board.

716
MCQmedium

What should the Project Manager do when a stage is forecast to exceed its tolerance?

A.Raise an Exception Report to the Project Board
B.Continue with the plan and inform the Project Board at the next Highlight Report
C.Ask the Team Manager to reduce the scope of work
D.Revise the stage plan and continue
AnswerA

The Project Manager raises an Exception Report to the Project Board, who will decide on corrective action.

Why this answer

When a tolerance is forecast to be exceeded, the Project Manager must escalate to the Project Board via an Exception Report. This is management by exception.

717
MCQmedium

A project manager is initiating a project using PRINCE2. The project board has approved the project mandate, but the project manager is unsure about the next step. Which process should be executed first?

A.Starting up a Project
B.Managing a Stage Boundary
C.Directing a Project
D.Initiating a Project
AnswerA

Starting up a Project is the first process, triggered by the project mandate, to ensure prerequisites are in place.

Why this answer

The correct answer is A, Starting up a Project. According to PRINCE2, the first process after the project mandate is approved is 'Starting up a Project'. This process ensures that the project is viable and that the necessary people are appointed (e.g., the Executive, Senior User, and Senior Supplier) before any detailed planning or initiation begins.

The project manager must execute this process to create the Project Brief and prepare for the 'Initiating a Project' process.

Exam trap

The trap here is that candidates often confuse 'Initiating a Project' (which involves detailed planning and the PID) with the very first process, not realizing that PRINCE2 mandates a separate 'Starting up a Project' process to ensure the project is even worth initiating before any significant effort is spent.

How to eliminate wrong answers

Option B (Managing a Stage Boundary) is wrong because this process is executed at the end of each management stage (except the final stage) to provide the Project Board with information to assess the current stage's performance and approve the next stage plan; it cannot be the first process. Option C (Directing a Project) is wrong because this is the process used by the Project Board to make key decisions and provide overall direction; it runs from project start to project closure but is not the first process executed by the project manager. Option D (Initiating a Project) is wrong because this process comes after 'Starting up a Project' and requires the Project Brief and other outputs from the startup process to develop the Project Initiation Documentation (PID).

718
MCQeasy

What is the purpose of the Managing a Stage Boundary process?

A.To close the project
B.To prepare an Exception Plan when tolerances are exceeded
C.To control the work of the current stage
D.To enable the Project Board to approve completion of the current stage and authorize the next stage
AnswerD

This is the key purpose: review and authorize the next stage.

Why this answer

This process provides the Project Board with information to decide whether to continue with the next stage, based on review of the current stage's performance and updated plans.

719
MCQmedium

During the Controlling a Stage process, the Project Manager identifies that the project is forecast to exceed the agreed cost tolerance for the current stage. What should the Project Manager do?

A.Close the project immediately as the Business Case is no longer viable
B.Raise an Exception Report to the Project Board and await their direction before proceeding
C.Increase the project budget to absorb the additional cost and continue with the current Stage Plan
D.Continue with the current Stage Plan and report the cost overrun in the next Highlight Report
AnswerB

Correct. The PM must escalate via an Exception Report.

Why this answer

When a stage tolerance is forecast to be exceeded, the Project Manager must escalate to the Project Board via an Exception Report. This is PRINCE2's management by exception principle.

720
MCQeasy

Which practice defines the project management team structure?

A.Business Case
B.Plans
C.Progress
D.Organising
AnswerD

Correct.

Why this answer

The Organising practice defines the roles and responsibilities within the project management team.

721
MCQeasy

What is the key output of the Starting Up a Project process?

A.End Project Report
B.Project Initiation Documentation
C.Project Brief
D.Business Case
AnswerC

The Project Brief is produced during Starting Up a Project.

Why this answer

The Project Brief is the key output that provides a definition of the project and justifies its viability.

722
MCQmedium

During the Managing a Stage Boundary process, the Project Manager creates the Stage Plan for the next stage. Who approves this Stage Plan?

A.Project Manager
B.Senior Responsible Owner
C.Senior Supplier
D.Project Board
AnswerD

The Project Board approves the Stage Plan before the next stage can begin.

Why this answer

The Project Board approves the Stage Plan for the next stage, allowing the project to proceed. This is part of the exception-driven decision-making.

723
MCQeasy

Which process is responsible for authorizing the initiation of a project?

A.Directing a Project
B.Controlling a Stage
C.Starting Up a Project
D.Initiating a Project
AnswerA

Correct. The Project Board authorizes initiation in the Directing a Project process.

Why this answer

Directing a Project is the process by which the Project Board authorizes initiation, authorizes the project, authorizes stage plans, and gives ad hoc direction.

724
MCQeasy

Which process produces the Project Brief?

A.Directing a Project
B.Initiating a Project
C.Starting Up a Project
D.Managing a Stage Boundary
AnswerC

Correct. SU produces the Project Brief, initiation Stage Plan, and Daily Log.

Why this answer

The Starting Up a Project process produces the Project Brief, which provides a high-level overview of the project to support the decision to proceed to initiation.

725
Multi-Selectmedium

Which TWO of the following are components of a Product Description?

Select 2 answers
A.Lessons Report
B.Acceptance methods
C.Stage boundaries
D.Risk budget
E.Quality criteria
AnswersB, E

Acceptance methods describe how the product will be verified against its quality criteria.

Why this answer

Options B and D are correct. A Product Description includes quality criteria (B) and acceptance methods (D). The risk budget and stage boundaries are not part of a Product Description.

726
MCQmedium

The Project Board has requested a report summarizing the current stage performance and the plan for the next stage. Which process should the Project Manager use?

A.Controlling a Stage
B.Closing a Project
C.Managing a Stage Boundary
D.Directing a Project
AnswerC

SB produces the End Stage Report and next Stage Plan for Project Board approval.

Why this answer

Managing a Stage Boundary (SB) is the process where the PM reports on the current stage (End Stage Report) and plans the next stage (next Stage Plan).

727
Multi-Selectmedium

Which TWO of the following are types of issues in PRINCE2?

Select 2 answers
A.Off-specification
B.Request for Change
C.Constraint
D.Opportunity
E.Risk
AnswersA, B

Why this answer

Issue types are: Request for Change, Off-specification, and Problem/Concern. Risk is not an issue; it is a separate practice.

728
MCQmedium

Who is responsible for producing Checkpoint Reports?

A.Team Manager
B.Project Board
C.Project Manager
D.Project Support
AnswerA

Correct. The Team Manager produces Checkpoint Reports to inform the Project Manager of progress.

Why this answer

Checkpoint Reports are produced by the Team Manager and sent to the Project Manager as part of the Managing Product Delivery process.

729
MCQeasy

Who is responsible for defining the project's tolerance levels?

A.Senior User
B.Project Manager
C.Team Manager
D.Project Board
AnswerD

The Board sets tolerances as part of project governance.

Why this answer

The Project Board sets project-level tolerances (e.g., time, cost, quality) in the PID, providing boundaries within which the Project Manager operates.

730
Multi-Selectmedium

Which TWO of the following statements correctly describe the relationship between the Project Manager and Project Assurance?

Select 2 answers
A.Project Assurance reports to the Project Manager
B.Project Assurance is independent of the Project Manager
C.Project Assurance provides an independent view of the project's health
D.The Project Manager can assign Project Assurance tasks to themselves if resources are limited
E.The Project Manager can delegate Project Assurance duties to a Team Manager
AnswersB, C

Independence is a key principle.

Why this answer

Option B is correct because PRINCE2 mandates that Project Assurance is independent of the Project Manager to ensure objective oversight. Option C is correct because Project Assurance's primary role is to provide an independent view of the project's health, checking compliance with standards and business justification.

Exam trap

The trap here is that candidates confuse Project Assurance with quality control or project support roles, assuming the Project Manager can control or delegate assurance tasks, when in fact PRINCE2 strictly separates assurance from management to maintain objectivity.

731
Multi-Selectmedium

Which TWO of the following are valid tolerances in PRINCE2?

Select 2 answers
A.Benefit
B.Time
C.Resource
D.Cost
E.Budget
AnswersB, D

Time is one of the six tolerances.

Why this answer

In PRINCE2, tolerances are the permissible deviations from a plan without needing to escalate to the next management level. The six standard tolerances are Time, Cost, Quality, Scope, Risk, and Benefit. Time (B) and Cost (D) are explicitly defined as tolerances for managing stage and project plans.

Exam trap

The trap here is that candidates confuse 'Resource' (a management lever) with a formal tolerance, or think 'Budget' is the official term when PRINCE2 specifically uses 'Cost'.

732
MCQmedium

What is the key output of the 'Starting Up a Project' process?

A.Project Brief
B.Project Initiation Documentation
C.Business Case
D.Stage Plan
AnswerA

The Project Brief is created during Starting Up a Project.

Why this answer

The Project Brief is the key output of the Starting Up a Project process, providing the initial information to decide whether to proceed to initiation.

733
Multi-Selecteasy

Which TWO of the following are types of tolerance that can be set in PRINCE2?

Select 2 answers
A.Change control approach
B.Quality management approach
C.Risk budget
D.Time
E.Cost
AnswersD, E

Time is one of the six PRINCE2 tolerances.

Why this answer

Options A and B are correct. The six tolerances in PRINCE2 are time, cost, quality, scope, risk, and benefits. Options C, D, and E are not standard PRINCE2 tolerances; they are management approaches or budgets.

734
Multi-Selectmedium

Which TWO of the following are components of the Business Case?

Select 2 answers
A.Expected benefits
B.Configuration item records
C.Major risks
D.Team structure
E.Product Breakdown Structure
AnswersA, C

Expected benefits are a key component of the Business Case.

Why this answer

The Business Case includes reasons, options, expected benefits, dis-benefits, timescale, costs, investment appraisal, and major risks. Expected benefits and major risks are two of these components.

735
MCQmedium

During which process are Work Packages authorised by the Project Manager?

A.Directing a Project
B.Controlling a Stage
C.Managing a Stage Boundary
D.Managing Product Delivery
AnswerB

Why this answer

In Controlling a Stage, the Project Manager authorises Work Packages (CS activity 'Authorise a Work Package'). Managing Product Delivery is where the Team Manager executes the Work Package. DP is board-level.

SB plans the next stage.

736
MCQmedium

A Work Package is authorized by the Project Manager. In which process does this happen?

A.Controlling a Stage
B.Managing Product Delivery
C.Directing a Project
D.Starting Up a Project
AnswerA

CS includes authorizing Work Packages.

Why this answer

Authorizing Work Packages is an activity in the Controlling a Stage process, where the PM assigns work to Team Managers.

737
MCQhard

In PRINCE2, what is the purpose of the Managing a Stage Boundary process?

A.To authorize the work for the next stage
B.To enable the Project Board to review the current stage, approve the next stage plan, and confirm continued business justification
C.To produce the End Project Report
D.To update the Project Plan with actual progress
AnswerB

This is the correct purpose of the Managing a Stage Boundary process.

Why this answer

The purpose is to provide the Project Board with sufficient information to review the current stage, approve the next stage plan, and confirm continued business justification.

738
Multi-Selectmedium

Which THREE of the following are responsibilities of the Project Manager in PRINCE2?

Select 3 answers
A.Producing the Project Initiation Documentation
B.Reporting progress to the Project Board
C.Approving the Business Case
D.Managing the project's day-to-day activities
E.Providing independent assurance to the Project Board
AnswersA, B, D

The PM is responsible for creating the PID.

Why this answer

Option A is correct because the Project Manager is responsible for producing the Project Initiation Documentation (PID) in PRINCE2. The PID is a key deliverable that consolidates the project's scope, business justification, plans, and controls, and the Project Manager compiles it based on input from the Project Board and other stakeholders. This responsibility is explicitly defined in the PRINCE2 Project Manager role description.

Exam trap

The trap here is confusing the Project Manager's responsibility for maintaining the Business Case with the authority to approve it, which is reserved for the Project Board or Senior User.

739
MCQeasy

During the Initiating a Project process, the project manager identifies that the business case relies on a key supplier delivering critical components by a fixed date. However, the supplier has a history of delays. What should the project manager do?

A.Proceed with the plan as the supplier has always delivered eventually
B.Adjust the business case to remove the supplier dependency
C.Ask the project board to approve the project with a note about the risk
D.Record the risk in the risk register and plan a response in the risk management approach
AnswerD

Risks must be formally recorded and managed.

Why this answer

In PRINCE2, the risk register is the central repository for recording all identified risks, and the risk management approach defines how risks will be managed throughout the project. During the Initiating a Project process, the project manager must formally document the supplier delay risk and plan appropriate responses (e.g., mitigation, contingency) within the risk management approach. This ensures the risk is actively managed rather than ignored or deferred, aligning with PRINCE2's principle of continued business justification.

Exam trap

PeopleCert often tests the misconception that a risk can be handled informally or deferred to later stages, but PRINCE2 requires formal recording and planning of risks during the Initiating a Project process to ensure they are managed from the start.

How to eliminate wrong answers

Option A is wrong because proceeding without action ignores the risk management principle; PRINCE2 requires proactive risk handling, not reliance on past behavior. Option B is wrong because adjusting the business case to remove the dependency is unrealistic and may invalidate the project's justification; dependencies should be managed, not eliminated arbitrarily. Option C is wrong because asking the project board to approve with a note is informal; PRINCE2 mandates that risks be formally recorded in the risk register and addressed in the risk management approach before seeking approval.

740
Multi-Selectmedium

Which TWO of the following are types of issue in PRINCE2?

Select 2 answers
A.Risk
B.Action Item
C.Lessons Learned
D.Off-specification
E.Request for Change
AnswersD, E

One of the three issue types.

Why this answer

The three issue types are Request for Change, Off-specification, and Problem/Concern.

741
MCQmedium

During the Managing a Stage Boundary process, the Project Manager produces an Exception Plan. What triggers this?

A.The stage is forecast to exceed its tolerance
B.A Team Manager reports a delay in the Work Package
C.The Project Board requests a new plan for the next stage
D.The Project Manager decides to change the project approach
AnswerA

An Exception Plan replaces the current plan when tolerances are breached.

Why this answer

An Exception Plan is produced when a stage is forecast to exceed its tolerances, as an alternative to the current Stage Plan, for approval by the Project Board.

742
MCQmedium

A Project Manager delegates the management of a Work Package to a Team Manager. What is the Team Manager's responsibility?

A.To perform Project Assurance for the Work Package
B.To deliver the Work Package within tolerances
C.To raise issues directly to the Project Board
D.To update the project plan with actual progress
AnswerB

The Team Manager manages the work and reports to the PM.

Why this answer

The Team Manager is responsible for delivering the Work Package within agreed tolerances and reporting progress via Checkpoint Reports.

743
Multi-Selectmedium

Which TWO of the following are outputs of the Initiating a Project process?

Select 2 answers
A.Project Initiation Documentation
B.Project Brief
C.Benefits Management Approach
D.Exception Report
E.End Project Report
AnswersA, C

Key output of IP.

Why this answer

The PID and Benefits Management Approach are created in IP. The Project Brief is from SU, and the End Project Report is from CP.

744
MCQmedium

Which document is the key output of the Initiating a Project process?

A.Project Initiation Documentation
B.Stage Plan
C.Project Brief
D.Project Plan
AnswerA

The PID is the comprehensive document created during Initiation.

Why this answer

The Project Initiation Documentation (PID) is the key output of the Initiating a Project process, providing a foundation for the project.

745
MCQmedium

In which process are Highlight Reports produced and sent to the Project Board?

A.Managing a Stage Boundary
B.Directing a Project
C.Managing Product Delivery
D.Controlling a Stage
AnswerD

Correct. The PM produces Highlight Reports in Controlling a Stage.

Why this answer

Highlight Reports are produced by the Project Manager during the Controlling a Stage process and sent to the Project Board to provide a summary of progress.

746
MCQmedium

In PRINCE2, what is the primary difference between Project Assurance and a quality review?

A.There is no difference; they are synonymous.
B.Project Assurance ensures the project is on track; a quality review checks product quality.
C.Project Assurance is performed by the Project Manager; quality review is performed by the team.
D.Project Assurance is a process; quality review is a role.
AnswerB

Project Assurance is about governance; quality review is about product verification.

Why this answer

Option B is correct because Project Assurance and quality reviews serve distinct purposes in PRINCE2. Project Assurance is an independent oversight function that ensures the project remains viable, compliant, and on track against the business case and plans. A quality review, on the other hand, is a structured technique used to assess whether a specific product meets its defined quality criteria and is fit for purpose.

Exam trap

The trap here is that candidates often confuse the independent oversight role of Project Assurance with the product-focused checking of a quality review, leading them to think they are the same or that the Project Manager performs assurance.

How to eliminate wrong answers

Option A is wrong because Project Assurance and a quality review are not synonymous; they have different objectives, participants, and timing within the project lifecycle. Option C is wrong because Project Assurance is performed by an independent person or group (often from the corporate, programme management, or customer side), not by the Project Manager; the Project Manager is responsible for day-to-day management, not assurance. Option D is wrong because Project Assurance is a role (or set of responsibilities), not a process; a quality review is a technique (or activity), not a role.

747
Multi-Selectmedium

Which TWO of the following are opportunity responses in PRINCE2 risk management?

Select 2 answers
A.Exploit
B.Accept
C.Enhance
D.Transfer
E.Avoid
AnswersA, C

Exploit is an opportunity response.

Why this answer

Exploit and Enhance are opportunity responses. Avoid and Transfer are threat responses. Accept can be used for both.

748
MCQhard

A project is in the Managing a Stage Boundary process. Which TWO outputs are produced during this process? (Select TWO)

A.Project Plan
B.Benefits Management Approach
C.End Stage Report
D.Project Brief
E.Next Stage Plan
AnswerC, E

Yes, the End Stage Report summarises the current stage.

Why this answer

SB produces the End Stage Report and the next Stage Plan (or Exception Plan).

749
MCQeasy

What is the purpose of the Starting Up a Project process?

A.To ensure that the prerequisites for initiating a project are in place
B.To authorise the project
C.To produce the Project Initiation Documentation
D.To manage the delivery of products in a stage
AnswerA

SU checks that basic conditions exist before committing to initiation.

Why this answer

SU is a pre-project process that ensures the prerequisites for initiating a project are in place, including the appointment of the Executive and Project Manager and the creation of the Project Brief.

Page 9

Page 10 of 24

Page 11