PRINCE2 Foundation (PRINCE2F) — Questions 301375

1731 questions total · 24pages · All types, answers revealed

Page 4

Page 5 of 24

Page 6
301
MCQhard

During a stage, the Project Manager receives a Checkpoint Report from a Team Manager indicating that the team has implemented a workaround for an off-specification without prior approval. What should the Project Manager do?

A.Raise an Issue Report and assess the impact of the workaround
B.Accept the workaround as it has already been implemented
C.Update the Configuration Item Record to reflect the change
D.Instruct the Team Manager to reverse the workaround immediately
AnswerA

The Project Manager should document the issue and assess the impact, then decide on the appropriate action.

Why this answer

Any off-specification must be formally documented as an issue. The team should not have implemented a workaround without approval. The Project Manager should raise an Issue Report and investigate the impact.

302
MCQhard

The project manager is preparing the next Stage Plan during the Managing a Stage Boundary process. Which document should be used as the basis for updating the Business Case?

A.The Project Brief
B.The project's risk register
C.The End Stage Report
D.The Quality Management Approach
AnswerC

Correct. The End Stage Report provides actual results vs planned, informing the BC update.

Why this answer

The End Stage Report provides the current stage's performance, which feeds into the Business Case update. The Benefits Management Approach and other documents are also considered, but the End Stage Report is key for performance data.

303
MCQeasy

Which process covers the Project Board's decision to authorise project closure?

A.Managing a Stage Boundary
B.Initiating a Project
C.Directing a Project
D.Closing a Project
AnswerC

DP includes the activity 'Authorise Project Closure'.

Why this answer

The Project Board uses the Directing a Project process to authorise closure, based on the recommendation from CP.

304
Multi-Selecthard

Which THREE of the following are reasons why PRINCE2 recommends separating the Project Manager from Project Assurance?

Select 3 answers
A.To ensure objective and independent monitoring of the project
B.To provide the Project Board with an independent view that the project is being managed correctly
C.To reduce the overall cost of project management
D.To avoid a conflict of interest between managing and assuring the project
E.To speed up decision-making by the Project Board
AnswersA, B, D

Independence is key for unbiased assurance.

Why this answer

Independence ensures objective oversight, reduces conflict of interest, and helps identify issues early. It does not speed up decisions (that may be slower) nor reduce costs (it adds overhead).

305
MCQeasy

Which process is triggered when a project is forecast to exceed its stage tolerances?

A.Controlling a Stage
B.Managing Product Delivery
C.Managing a Stage Boundary
D.Directing a Project
AnswerC

Correct. The Managing a Stage Boundary process handles exceptions and produces Exception Plans.

Why this answer

When stage tolerances are forecast to be exceeded, the Project Manager raises an Exception Report and the Managing a Stage Boundary process is used to plan the response. The Project Board may approve an Exception Plan via this process.

306
MCQmedium

Refer to the exhibit. The project manager needs to get approval to proceed with the initiation stage. Who is responsible for authorizing the initiation stage?

A.Senior User
B.Executive
C.Project Manager
D.Team Manager
AnswerB

The Executive is responsible for authorizing the initiation stage.

Why this answer

The Executive is the single person accountable for the project and has the authority to authorize the initiation stage. According to PRINCE2, only the Executive can give the approval to proceed from the Starting Up a Project process to the Initiation Stage, as they own the business case and are responsible for the project's overall justification.

Exam trap

PeopleCert often tests the distinction between the Project Manager's role in preparing documentation and the Executive's role in making the authorization decision, causing candidates to mistakenly attribute stage authorization to the Project Manager.

How to eliminate wrong answers

Option A is wrong because the Senior User represents the interests of those who will use the project's products, but they do not have the authority to authorize stages; that responsibility lies with the Executive. Option C is wrong because the Project Manager manages the day-to-day activities and produces the plans, but they cannot authorize their own stage; authorization must come from the Project Board, specifically the Executive. Option D is wrong because the Team Manager is responsible for delivering work packages within a stage, not for authorizing the initiation of a stage.

307
Multi-Selectmedium

Which TWO of the following are roles that are part of the Project Board?

Select 2 answers
A.Senior User
B.Team Manager
C.Executive
D.Project Assurance
E.Project Support
AnswersA, C

The Senior User is a mandatory Project Board role.

Why this answer

The Project Board is the PRINCE2 management layer responsible for overall project direction and key decision-making. The Senior User is a mandatory Project Board role representing the interests of those who will use the project's products, ensuring the project delivers the required benefits. The Executive is also a mandatory Project Board role, acting as the project's ultimate decision-maker and owner of the business case.

Exam trap

PeopleCert often tests the distinction between roles that are part of the Project Board (Executive, Senior User, Senior Supplier) and roles that support or execute within the Project Management Team (Project Manager, Team Manager, Project Assurance, Project Support), tempting candidates to select Project Assurance or Project Support as Board members.

308
MCQmedium

What is the role of the Change Authority in PRINCE2?

A.To maintain the issue register
B.To identify all changes in the project
C.To implement approved changes
D.To approve requests for change within an agreed delegated limit
AnswerD

Correct. The Change Authority has delegated authority.

Why this answer

The Change Authority in PRINCE2 is a role that is delegated by the Project Board to approve requests for change within a specific, agreed-upon limit (e.g., cost or time). This allows for efficient decision-making without requiring the full Project Board to convene for every minor change, while still maintaining control over the project's scope and budget.

Exam trap

The trap here is confusing the Change Authority with the Project Board or the project team, as candidates often assume that all changes must be approved by the highest authority or that the Change Authority is responsible for implementing changes, rather than understanding it as a delegated decision-making role with specific limits.

How to eliminate wrong answers

Option A is wrong because maintaining the issue register is the responsibility of the Project Support role, not the Change Authority. Option B is wrong because identifying all changes in the project is a continuous activity performed by the entire project team, not a specific role; the Change Authority only reviews and approves changes within its delegated limits. Option C is wrong because implementing approved changes is the responsibility of the project team members (e.g., team managers or specialists), not the Change Authority, whose role is purely decision-making and authorization.

309
MCQmedium

During the Controlling a Stage process, the Project Manager receives a Checkpoint Report. Who prepared this report?

A.Project Manager
B.Project Board
C.Team Manager
D.Project Support
AnswerC

Why this answer

Checkpoint Reports are prepared by the Team Manager and sent to the Project Manager as part of Managing Product Delivery. They inform the Project Manager of progress on Work Packages.

310
MCQmedium

A large IT project is implementing a new customer relationship management (CRM) system for a multinational corporation. The project is organized with a Project Board comprising the Executive (VP of Sales), Senior User (Regional Sales Director), and Senior Supplier (IT Director). The Project Manager is an experienced PMP-certified professional. The team includes several business analysts and developers from an external supplier. The project has just completed the Initiating a Project process and received authorization to proceed to the next stage. However, during the first week of the Delivery Stage, the Project Manager notices that the business analysts are not collaborating effectively with the developers, leading to misunderstandings about requirements. The Project Manager holds a meeting and discovers that the business analysts feel excluded from decision-making and the developers complain about unclear specifications. The Project Manager wants to resolve this using PRINCE2 principles and practices. Which of the following is the BEST course of action?

A.Ignore the issue as it is a normal part of team dynamics and will resolve itself over time.
B.Replace the business analysts with more experienced ones who can work better with developers.
C.Revisit the Communication Management Strategy and clarify roles and responsibilities in the team.
D.Escalate the issue to the Project Board for a decision on how to restructure the team.
AnswerC

Correct: The Project Manager should use the Communication Management Strategy to facilitate collaboration and ensure roles are clear.

Why this answer

Option C is correct because PRINCE2's Communication Management Strategy is the formal mechanism for defining roles, responsibilities, and information flows. By revisiting it, the Project Manager can clarify the business analysts' and developers' roles in decision-making and requirements specification, directly addressing the root cause of misunderstandings. This aligns with the 'Manage by Stages' and 'Defined Roles and Responsibilities' principles, ensuring the team collaborates effectively without unnecessary escalation or personnel changes.

Exam trap

The trap here is that candidates may assume any team conflict requires escalation to the Project Board (Option D), but PRINCE2 reserves escalation only for issues exceeding stage tolerances or requiring business-level decisions, not for internal team coordination problems.

How to eliminate wrong answers

Option A is wrong because ignoring the issue violates PRINCE2's 'Manage by Exception' principle; unresolved team dynamics can escalate into requirements errors and rework, jeopardizing stage tolerances. Option B is wrong because replacing team members without first addressing the communication breakdown ignores the PRINCE2 focus on process improvement and the 'Learn from Experience' principle; the problem is likely procedural, not individual competence. Option D is wrong because the issue is within the Project Manager's authority to resolve via the Communication Management Strategy; escalating to the Project Board for a team restructuring decision bypasses the PM's responsibility and violates the 'Manage by Stages' principle where the PM manages day-to-day issues.

311
Multi-Selectmedium

Which TWO are part of the Project Initiation Documentation?

Select 2 answers
A.Exception Report
B.End Stage Report
C.Business Case
D.Project Plan
E.Checkpoint Report
AnswersC, D

The Business Case is a key component of the PID.

Why this answer

The Business Case is part of the Project Initiation Documentation because it provides the justification for the project and is developed during the Initiating a Project process. The Project Plan is also part of the PID as it defines the project-level plan, including costs, timescales, and controls, and is created during initiation. Both are mandatory components of the PID as per PRINCE2.

Exam trap

PeopleCert often tests the distinction between management products created during initiation versus those produced during ongoing stage management, so the trap here is confusing operational reports like Exception Reports or Checkpoint Reports with the foundational documents in the PID.

312
Multi-Selectmedium

Which TWO of the following are types of issue in PRINCE2?

Select 2 answers
A.Request for Change
B.Assumption
C.Constraint
D.Risk
E.Off-specification
AnswersA, E

An RFC is a type of issue.

Why this answer

PRINCE2 defines three types of issue: Request for Change (RFC), Off-specification (Off-spec), and Problem/Concern. Risk is a separate concept.

313
MCQmedium

During a quality review, a reviewer identifies a major defect that would make the product unfit for purpose. What should happen?

A.The defect is recorded in the Quality Register and the product is approved with a concession
B.The product is not approved; the author must correct the defect and resubmit for review
C.The review chair revises the quality criteria to accept the defect
D.The project is closed because the product cannot meet requirements
AnswerB

Products with major defects are not approved; the author must fix them and re-enter the review process.

Why this answer

Quality reviews identify defects. If a major defect is found, the product is not approved. The author must correct the defect and re-enter the review process.

Options A and B are wrong because the review does not change quality criteria or bypass the process. Option D is wrong because closing the project is too drastic.

314
Multi-Selectmedium

Which TWO of the following are components of a Business Case?

Select 2 answers
A.Lessons log
B.Expected benefits
C.Product descriptions
D.Major risks
E.Configuration item records
AnswersB, D

Expected benefits are a key component.

Why this answer

The Business Case includes reasons, options, expected benefits, dis-benefits, timescale, costs, investment appraisal, and major risks. Major risks and expected benefits are two of these.

315
MCQmedium

Who is responsible for producing the End Stage Report?

A.The Project Manager
B.The Project Board
C.The Team Manager
D.The Senior User
AnswerA

The Project Manager produces the End Stage Report as part of Managing a Stage Boundary.

Why this answer

The Project Manager produces the End Stage Report during the Managing a Stage Boundary process.

316
MCQmedium

Which process includes the activity 'Assembling the Project Initiation Documentation'?

A.Directing a Project
B.Managing a Stage Boundary
C.Starting Up a Project
D.Initiating a Project
AnswerD

IP includes the activity to assemble the PID.

Why this answer

Assembling the PID is a key activity in the Initiating a Project process. Starting Up a Project assembles the Project Brief. Directing a Project authorises initiation.

Managing a Stage Boundary does not assemble PID.

317
MCQeasy

Who is responsible for managing the delivery of a Work Package?

A.Project Manager
B.Project Support
C.Team Manager
D.Senior Supplier
AnswerC

The Team Manager manages Work Package delivery.

Why this answer

The Team Manager is responsible for the delivery of one or more Work Packages and reports to the Project Manager.

318
MCQeasy

Who is responsible for maintaining the Business Case throughout the project?

A.Project Manager
B.Project Assurance
C.Executive
D.Senior User
AnswerA

The Project Manager maintains the Business Case throughout the project.

Why this answer

The Project Manager is responsible for maintaining the Business Case on a day-to-day basis, while the Executive (SRO) owns it and is ultimately accountable for its justification.

319
MCQmedium

In PRINCE2, the Project Board typically meets on which basis?

A.Weekly
B.Exception-driven
C.Daily
D.At the end of each stage
AnswerB

The Project Board meets only when needed to make decisions outside delegated tolerances.

Why this answer

In PRINCE2, the Project Board is a decision-making body that manages by exception. It does not meet on a fixed schedule like weekly or daily; instead, it convenes only when a deviation from the plan (an exception) requires its intervention, such as when a stage plan exceeds tolerance levels. This exception-driven approach ensures the Board focuses on strategic oversight rather than operational details.

Exam trap

The trap here is that candidates confuse the Project Board's meeting frequency with the project manager's regular reporting (e.g., Highlight Reports) or with the mandatory end-stage assessments, mistakenly thinking the Board meets on a fixed schedule or only at stage ends.

How to eliminate wrong answers

Option A is wrong because PRINCE2 does not prescribe a weekly meeting cadence for the Project Board; such a fixed schedule would undermine the management-by-exception principle and burden the Board with routine updates. Option C is wrong because daily meetings are far too frequent for a strategic oversight body and would conflict with the project manager's day-to-day management responsibilities. Option D is wrong because while the Board does approve stage boundaries, it does not meet only at the end of each stage; it may also convene for ad-hoc decisions or exception situations between stages.

320
MCQeasy

Which document defines the project's organization structure and roles?

A.Risk Register
B.Project Initiation Documentation
C.Project Plan
D.Business Case
AnswerB

The PID includes the organization structure.

Why this answer

The Project Initiation Documentation (PID) is the definitive document that defines the project's organization structure and roles, including the project management team structure, role descriptions, and responsibilities. It is created during the Initiating a Project process and provides a baseline for how the project will be managed and controlled.

Exam trap

PeopleCert often tests the distinction between the Project Plan (which focuses on schedule and resources) and the Project Initiation Documentation (which is the comprehensive document that includes the organization structure and roles), leading candidates to mistakenly select the Project Plan.

How to eliminate wrong answers

Option A is wrong because the Risk Register is a document that records identified risks, their analysis, and planned responses, not the project's organization structure and roles. Option C is wrong because the Project Plan defines the schedule, resources, and costs for delivering the project's products, not the organizational structure. Option D is wrong because the Business Case provides the justification for the project, including costs, benefits, and risks, but does not define the organization structure or roles.

321
MCQeasy

Which document is the key output of the Initiating a Project process?

A.Project Brief
B.Project Initiation Documentation (PID)
C.Benefits Review Plan
D.End Project Report
AnswerB

Correct: The PID is the key output of Initiating a Project.

Why this answer

The Initiating a Project process is where the project's foundations are solidified, and its key output is the Project Initiation Documentation (PID). The PID consolidates all the planning and analysis from the initiation stage into a single, comprehensive document that defines the project's scope, objectives, business justification, risks, and management controls, serving as the baseline for the project board's authorization to proceed.

Exam trap

PeopleCert often tests the distinction between the Project Brief (from Starting Up a Project) and the PID (from Initiating a Project), trapping candidates who confuse the two as both are created early in the project lifecycle.

How to eliminate wrong answers

Option A is wrong because the Project Brief is created during the Starting Up a Project process, not the Initiating a Project process; it provides the initial outline and justification but lacks the detailed planning and controls that the PID contains. Option C is wrong because the Benefits Review Plan is a separate document produced during the Initiating a Project process, but it is not the key output; it is a component of the PID or a standalone plan that defines how and when the project's benefits will be reviewed. Option D is wrong because the End Project Report is produced during the Closing a Project process, not during initiation; it summarizes the project's performance against the PID and is used to formally close the project.

322
MCQeasy

Who is responsible for maintaining the Business Case throughout the project?

A.Project Assurance
B.Senior User
C.Project Manager
D.Executive
AnswerC

The Project Manager is responsible for maintaining the Business Case throughout the project.

Why this answer

The Project Manager (PM) maintains the Business Case on a day-to-day basis, but the Executive owns it and is accountable for it. The PM ensures it is updated and reviewed.

323
Multi-Selectmedium

Which TWO of the following are types of issue in PRINCE2?

Select 2 answers
A.Risk
B.Highlight Report
C.Off-specification
D.Request for Change
E.Lessons Report
AnswersC, D

An Off-specification is a type of issue.

Why this answer

In PRINCE2, an issue is a relevant event that has occurred and requires management attention. The two recognized types of issue are 'Off-specification' (something that should be provided but is not) and 'Request for Change' (a proposal for a change to a product's specification). These are formally defined in the PRINCE2 manual as the only issue types.

Exam trap

PeopleCert often tests the confusion between 'issue' and 'risk' — candidates mistakenly select 'Risk' because they think it is a type of issue, but PRINCE2 treats risks and issues as distinct concepts with separate processes and registers.

324
MCQmedium

During the Managing a Stage Boundary process, the project manager produces an End Stage Report. Who receives this report and what decision do they make?

A.The project manager receives it to plan the next stage
B.The team manager receives it to assess work package performance
C.The executive receives it to update the business case
D.The project board receives it to decide whether to authorize the next stage
AnswerD

Correct. The Board reviews the End Stage Report and decides on stage authorization.

Why this answer

The End Stage Report is sent to the Project Board, who then decides whether to authorize the next stage (or, if the project is in the final stage, to close the project).

325
MCQmedium

Which role is responsible for the Project Plan?

A.Executive
B.Project Board
C.Senior User
D.Project Manager
AnswerD

The PM is responsible for planning.

Why this answer

The Project Manager is responsible for producing and maintaining the Project Plan, as defined in PRINCE2's management products. This includes defining the project's stages, activities, dependencies, and resource estimates, and ensuring the plan aligns with the Business Case. The Project Manager owns the planning process and is accountable for the plan's accuracy and updates throughout the project.

Exam trap

PeopleCert often tests the distinction between responsibility for creating versus approving a plan, leading candidates to mistakenly select the Project Board (Option B) because they confuse approval authority with ownership.

How to eliminate wrong answers

Option A is wrong because the Executive is responsible for the Business Case and overall project justification, not for creating the detailed Project Plan. Option B is wrong because the Project Board approves the Project Plan and provides direction, but does not create or maintain it. Option C is wrong because the Senior User represents user requirements and benefits, but has no direct responsibility for producing the Project Plan.

326
Multi-Selectmedium

Which THREE of the following are activities performed during the Managing a Stage Boundary process?

Select 3 answers
A.Produce a Stage Plan for the next stage
B.Produce a Highlight Report
C.Produce the End Stage Report
D.Update the Project Plan
E.Authorize work packages
AnswersA, C, D

Correct. The next stage plan is produced in SB.

Why this answer

In SB, the PM produces the End Stage Report, updates the Project Plan, and produces a Stage Plan for the next stage. Authorizing work packages is done in CS. Producing Highlight Reports is done in CS.

327
MCQhard

Why does PRINCE2 separate the Project Manager from Project Assurance?

A.To create a career path for team members
B.To ensure that the Project Board receives independent and objective assurance
C.To reduce the workload of the Project Manager
D.To allow the Project Manager to focus on team management
AnswerB

Correct.

Why this answer

The separation ensures independent oversight. The Project Manager is responsible for day-to-day management, while Project Assurance provides an impartial view to the Project Board to avoid conflicts of interest.

328
MCQmedium

In PRINCE2, what is the difference between a Highlight Report and a Checkpoint Report?

A.Highlight Report covers the entire project; Checkpoint Report covers only a stage
B.Highlight Report is sent by the Team Manager; Checkpoint Report is sent by the Project Manager
C.There is no difference; they are the same document
D.Highlight Report is sent to the Project Board; Checkpoint Report is sent to the Project Manager
AnswerD

This is correct.

Why this answer

A Highlight Report is sent from the Project Manager to the Project Board regularly, while a Checkpoint Report is sent from the Team Manager to the Project Manager more frequently.

329
MCQhard

A project team member identifies a problem with the product being developed that was not known at the time of the last stage. The Project Manager logs this as an Issue. Which type of Issue is this?

A.Risk
B.Problem/Concern
C.Request for Change
D.Off-specification
AnswerD

Correct. The product is not meeting its specification, so it is an Off-specification.

Why this answer

An Off-specification is something that should be provided by the project but is not (or is forecast not to be) present. A Request for Change is a proposal for a change. A Problem/Concern is other issues.

This fits Off-specification because the product does not meet the specification.

330
Multi-Selecthard

Which THREE of the following are responsibilities of the Project Board during the Directing a Project process?

Select 3 answers
A.Authorize the closure of the project
B.Authorize an Exception Plan
C.Authorize the initiation of the project
D.Manage day-to-day work of the team
E.Produce the Project Plan
AnswersA, B, C

The Project Board authorizes closure in DP.

Why this answer

The Project Board is responsible for making key decisions and exercising overall control over the project. Authorizing closure (A) ensures the project has met its objectives and that the product has been accepted before formal closure. Authorizing an Exception Plan (B) is a board-level decision to approve a deviation from the plan when a tolerance is forecast to be exceeded.

Authorizing initiation (C) gives the go-ahead for the project to proceed from the initiation stage into the detailed planning and delivery stages.

Exam trap

The trap here is that candidates often confuse the Project Board's strategic decision-making responsibilities with the Project Manager's operational tasks, such as managing daily work or producing plans, leading them to incorrectly select options D or E.

331
Multi-Selectmedium

Which TWO of the following are benefits of adopting PRINCE2?

Select 2 answers
A.Eliminates the need for project managers
B.Removes the need for tailoring
C.Guarantees that all projects are delivered on time and within budget
D.Ensures a focus on business justification throughout the project
E.Provides a common language and improves communication
AnswersD, E

Correct. The continued business justification principle ensures this.

Why this answer

PRINCE2 provides a common language and improves communication, and it ensures a focus on business justification through the Business Case. It does not eliminate the need for project managers nor guarantee successful delivery.

332
MCQmedium

A project to develop a new software application has completed its first stage. The Project Manager is preparing the End Stage Report. What is the primary purpose of this report?

A.To document lessons learned for future projects
B.To request authorization for the next stage and give a summary of the current stage's performance
C.To highlight any deviations from the project plan
D.To update the Business Case based on actual costs
AnswerB

Correct. The End Stage Report is used to obtain approval to proceed to the next stage.

Why this answer

The End Stage Report in PRINCE2 serves a dual purpose: it summarizes the current stage's performance against the plan and requests authorization to proceed to the next stage. This aligns with the PRINCE2 principle of managing by stages, where each stage ends with a formal review and decision point. The report provides the Project Board with the necessary information to approve continued investment.

Exam trap

The trap here is that candidates confuse the End Stage Report with a Lessons Report or an Exception Report, failing to recognize its primary role as a stage-gate authorization mechanism.

How to eliminate wrong answers

Option A is wrong because lessons learned are formally captured in the Lessons Log and Lessons Report, not in the End Stage Report, which focuses on stage performance and next-stage authorization. Option C is wrong because while deviations may be mentioned, the primary purpose is not to highlight them; that is the function of an Exception Report when tolerances are exceeded. Option D is wrong because the Business Case is updated via the Business Case document and the Benefits Review Plan, not through the End Stage Report, which only summarizes actual costs for the current stage.

333
MCQhard

Which process is triggered when an Exception Plan is approved?

A.Controlling a Stage
B.Initiating a Project
C.Managing a Stage Boundary
D.Directing a Project
AnswerC

This process is used to plan the next stage after an exception.

Why this answer

When an Exception Plan is approved, the project moves to a new stage, and the Managing a Stage Boundary process is used to set up the new stage.

334
Drag & Dropmedium

Drag and drop the steps to manage a product delivery work package in PRINCE2 into the correct order.

Drag steps to the numbered slots on the right, or tap a step then tap a slot.

Steps
Order

Why this order

Managing Product Delivery involves accepting the work package, executing the work, delivering the products, obtaining approval, and then reporting completion.

335
MCQmedium

What is the difference between a Request for Change (RFC) and an Off-specification?

A.An RFC proposes a change; an Off-specification reports a failure to meet the specification
B.An RFC impacts time; an Off-specification impacts cost
C.An RFC is handled by the Project Manager; an Off-specification goes to the Project Board
D.An RFC is raised by the Project Board; an Off-specification is raised by the Project Manager
AnswerA

Correct: RFCs are for desired modifications; Off-specifications are for deviations from the original specification.

Why this answer

An RFC is a proposal for a modification (change) to the project's products, while an Off-specification is a situation where a product does not meet its specification (a deviation).

336
MCQhard

A project is initiated in a highly regulated environment where external auditors will review compliance. The project manager is concerned about maintaining clear evidence of decisions. Which PRINCE2 principle is most important to apply in this situation?

A.Manage by stages
B.Continued business justification
C.Tailor to suit the project environment
D.Learn from experience
AnswerA

Stage boundaries provide formal review and decision points, creating clear audit evidence.

Why this answer

Manage by stages is the most important principle because it requires the project to be planned, monitored, and controlled in discrete stages, with each stage authorizing the next only after a formal review. In a highly regulated environment, this creates clear, auditable decision points (e.g., stage boundary approvals) that external auditors can trace. The project manager can document stage plans, exception reports, and end-stage assessments as explicit evidence of governance.

Exam trap

PeopleCert often tests the misconception that 'Tailor to suit the project environment' is the catch-all answer for any environmental challenge, but the trap here is that tailoring is about adapting methods, not about creating the specific, stage-gated evidence trail that auditors require.

How to eliminate wrong answers

Option B (Continued business justification) is wrong because while it ensures the project remains viable, it does not directly address the need for clear, stage-gated evidence of decisions; auditors focus on process compliance, not just business case updates. Option C (Tailor to suit the project environment) is wrong because tailoring adjusts PRINCE2 processes to the context, but the core mechanism for creating auditable decision records is the stage-based management structure, not tailoring itself. Option D (Learn from experience) is wrong because it focuses on capturing lessons for future projects, not on producing the formal, timestamped evidence of decisions required by external auditors.

337
MCQeasy

A project is in its initiation stage. The project manager needs to identify the major risks that could affect the project. Which practice should be applied to identify, assess, and control these risks?

A.Business Case
B.Progress
C.Organizing
D.Risk
AnswerD

The Risk practice covers the entire risk management process.

Why this answer

The Risk practice in PRINCE2 is specifically designed to identify, assess, and control uncertainties that could affect the project's objectives. During the initiation stage, the project manager applies this practice to systematically identify major risks, evaluate their probability and impact, and plan appropriate responses, ensuring proactive management of threats and opportunities.

Exam trap

The trap here is that candidates may confuse the Risk practice with the Business Case practice, mistakenly thinking that risk management is part of justifying the project, whereas PRINCE2 separates risk management as a distinct practice focused on uncertainty rather than justification.

How to eliminate wrong answers

Option A is wrong because the Business Case practice focuses on justifying the project's viability and tracking benefits, not on identifying, assessing, or controlling risks. Option B is wrong because the Progress practice deals with monitoring and reporting project performance against plans, not with the structured management of risks. Option C is wrong because the Organizing practice defines roles, responsibilities, and the project management team structure, but does not include the processes for risk identification, assessment, or control.

338
MCQmedium

During the Controlling a Stage process, the Project Manager receives a Highlight Report from a Team Manager. What should the Project Manager do with this report?

A.Return it to the Team Manager for correction
B.Forward it directly to the Project Board as a Highlight Report
C.Ignore it as it is not a formal report
D.Use it to compile the next Highlight Report to the Project Board
AnswerD

Checkpoint Reports provide progress information that the Project Manager uses to produce the Highlight Report.

Why this answer

Checkpoint Reports are produced by Team Managers for the Project Manager. Highlight Reports are produced by the Project Manager for the Project Board. Note: The scenario says 'Highlight Report from a Team Manager' — this is incorrect; Team Managers produce Checkpoint Reports.

However, if we assume it's a Checkpoint Report, the PM uses it to compile the Highlight Report. The question tests understanding of report flow.

339
Multi-Selecteasy

Which TWO documents are created during the Starting up a Project process?

Select 2 answers
A.Project Plan
B.End Project Report
C.Business Case
D.Project Brief
E.Risk Register
AnswersC, D

The Business Case is created in Starting up a Project.

Why this answer

The Starting up a Project (SU) process in PRINCE2 is the pre-project phase where the project is evaluated before any detailed planning begins. During SU, the Project Brief is created to outline the project's scope, objectives, and approach, and the Business Case is developed at a high level to justify the project's viability. Both documents are essential for the Project Board to decide whether to proceed to the Initiation Stage.

Exam trap

PeopleCert often tests the distinction between documents created in the pre-project phase (SU) versus the initiation phase, so candidates mistakenly select the Project Plan (A) because they confuse it with the Project Brief, or the Risk Register (E) because they think risk identification starts immediately in SU.

340
MCQhard

In PRINCE2, what is the difference between Project Assurance and Project Support?

A.Project Assurance ensures quality; Project Support manages risks
B.Project Assurance is independent of the project; Project Support provides administrative services
C.Project Assurance is performed by the Project Board; Project Support is performed by the Project Manager
D.There is no difference; they are the same function
AnswerB

This is the correct distinction.

Why this answer

Project Assurance is an independent check that the project is running correctly, while Project Support provides administrative services.

341
MCQmedium

A project is in the initiation stage. The project board asks the project manager to produce a document that justifies the project. Which document should the project manager produce?

A.Project Initiation Documentation
B.Business Case
C.Project Brief
D.Benefits Management Approach
AnswerB

The Business Case provides the justification for the project.

Why this answer

The Business Case is the document that justifies the project by providing the justification, costs, benefits, and risks. During the initiation stage, the project manager develops the Business Case to confirm that the project is viable and aligns with corporate objectives. The Project Board then reviews and approves it to authorize the project to proceed.

Exam trap

PeopleCert often tests the distinction between the Project Brief (which contains an outline Business Case) and the full Business Case developed during initiation, leading candidates to mistakenly choose the Project Brief as the justification document.

How to eliminate wrong answers

Option A is wrong because the Project Initiation Documentation (PID) is a comprehensive set of documents that includes the Business Case, but it is not solely the justification document; it covers the project plan, controls, and other management products. Option C is wrong because the Project Brief is created during the Starting Up a Project process to provide a high-level overview and is used to trigger the initiation stage, but it does not contain the detailed justification required for the project to proceed. Option D is wrong because the Benefits Management Approach defines how the project's benefits will be realized and measured, but it does not justify the project itself; it is derived from the Business Case.

342
MCQhard

What is the difference between a risk owner and a risk actionee?

A.Risk owner manages the risk; risk actionee monitors it
B.Risk owner is accountable for the risk; risk actionee implements the response actions
C.Risk owner is the same as risk actionee
D.Risk owner identifies risks; risk actionee assesses them
AnswerB

This is the correct distinction.

Why this answer

The risk owner is accountable for managing the risk, while the risk actionee carries out specific actions to respond to the risk.

343
MCQhard

A project is forecast to exceed its cost tolerance. What should the Project Manager do?

A.Close the project immediately as the Business Case is no longer viable
B.Increase the project budget to absorb the additional cost and continue with the current Stage Plan
C.Raise an Exception Report to the Project Board and await their direction before proceeding
D.Continue with the current Stage Plan and report the cost overrun in the next Highlight Report
AnswerC

This is the correct action per management by exception.

Why this answer

According to PRINCE2's management by exception principle, the Project Manager must escalate to the Project Board via an Exception Report when a tolerance is forecast to be exceeded.

344
MCQmedium

The Project Board is reviewing an Exception Plan submitted by the Project Manager. Which process is the Project Board performing?

A.Managing a Stage Boundary
B.Closing a Project
C.Directing a Project
D.Controlling a Stage
AnswerC

Correct. The Project Board authorizes Exception Plans in DP.

Why this answer

The Project Board authorizes Exception Plans during the Directing a Project process, which includes decisions on stage plans and exceptions.

345
Multi-Selecthard

Which THREE of the following are activities performed during the Directing a Project process?

Select 3 answers
A.Authorize closure of the project
B.Appoint the Project Manager
C.Authorize initiation
D.Give ad-hoc direction to the Project Manager
E.Produce Highlight Reports
AnswersA, C, D

The Project Board authorizes closure during Directing a Project.

Why this answer

Directing a Project includes authorizing initiation, authorizing stages, giving ad-hoc direction, and authorizing closure. Producing Highlight Reports is for the PM during Controlling a Stage. Appointing the Project Manager is during Starting Up a Project.

346
Multi-Selectmedium

Which THREE of the following are components of the Business Case?

Select 3 answers
A.Expected benefits
B.Investment appraisal
C.Project team structure
D.Major risks
E.Project Plan
AnswersA, B, D

Benefits are a key component.

Why this answer

The Business Case includes reasons, expected benefits, costs, timescale, etc.

347
Matchingmedium

Match each PRINCE2 principle to its description.

Drag a concept onto its matching description — or click a concept then click the description.

Concepts
Matches

Ensure there is a justifiable reason to start and continue the project.

Seek lessons from previous and current projects.

Clearly define roles and responsibilities for all involved.

Plan, monitor, and control the project on a stage-by-stage basis.

Define tolerances for each objective and delegate authority within those limits.

Why these pairings

The seven PRINCE2 principles are these five plus 'Focus on Products' and 'Tailor to Suit the Project Environment'.

348
MCQeasy

Who is responsible for project assurance in PRINCE2?

A.Senior Supplier
B.Project Board
C.Project Support
D.Project Manager
AnswerB

The Project Board is ultimately responsible for project assurance.

Why this answer

Project Assurance is the Project Board's responsibility, but it can be delegated to individuals or teams independent of the Project Manager.

349
MCQmedium

In product-based planning, what is the purpose of a Product Flow Diagram?

A.To define the quality criteria for each product
B.To show the sequence of product development and dependencies
C.To show the hierarchical breakdown of products
D.To estimate the effort required to create each product
AnswerB

The Product Flow Diagram illustrates the order and relationships among products.

Why this answer

The Product Flow Diagram shows the order in which products will be developed and the dependencies between them, which helps in planning the sequence of activities.

350
MCQmedium

During the Closing a Project process, which document is produced to capture lessons for future projects?

A.Project Product Description
B.Benefits Management Approach
C.End Project Report
D.Lessons Report
AnswerD

Lessons Report is the key document for capturing lessons in CP.

Why this answer

Option A is correct. The Lessons Report is produced in CP to document lessons learned for future benefit.

351
MCQmedium

The Project Board is considering a request to close a project early due to loss of business justification. Which process is the Project Board using to make this decision?

A.Managing a Stage Boundary
B.Closing a Project
C.Starting Up a Project
D.Directing a Project
AnswerD

Correct. DP includes the activity 'Authorise Project Closure'.

Why this answer

The Project Board uses the Directing a Project process throughout the project, including authorising closure. Closing a Project is the process that produces the recommendation, but the decision to close is taken by the Project Board via Directing a Project.

352
MCQhard

In PRINCE2, what is the difference between Project Assurance and Project Support?

A.Assurance is independent and objective oversight; Support provides administrative and planning assistance
B.There is no difference; they are the same role
C.Assurance is provided by the Project Board; Support is provided by the Project Manager
D.Assurance manages risks; Support manages issues
AnswerA

This is the key distinction.

Why this answer

Project Assurance is independent of the Project Manager and provides objective oversight, while Project Support provides administrative and planning support to the Project Manager.

353
MCQmedium

In PRINCE2, a Team Manager reports to the Project Manager. What is the primary responsibility of a Team Manager?

A.Provide independent assurance to the Project Board
B.Deliver one or more Work Packages as defined in the Stage Plan
C.Update the Business Case
D.Manage day-to-day project activities across all stages
AnswerB

Correct. The Team Manager manages work package delivery.

Why this answer

The Team Manager is responsible for delivering one or more Work Packages as defined in the Stage Plan. This role focuses on the technical delivery of products within the constraints agreed with the Project Manager, ensuring quality, time, and cost targets are met for those specific work packages.

Exam trap

The trap here is confusing the Team Manager's scope with the Project Manager's broader responsibilities, leading candidates to select Option D, which describes the Project Manager's role, not the Team Manager's.

How to eliminate wrong answers

Option A is wrong because providing independent assurance to the Project Board is the responsibility of the Project Assurance role, not the Team Manager. Option C is wrong because updating the Business Case is the responsibility of the Senior User or Executive, not the Team Manager. Option D is wrong because managing day-to-day project activities across all stages is the responsibility of the Project Manager, while the Team Manager only manages activities within their assigned Work Packages.

354
MCQhard

What is the difference between a risk owner and a risk actionee?

A.They are the same role
B.The risk owner is responsible for threats; the risk actionee for opportunities
C.The risk owner is on the Project Board; the risk actionee is in the project team
D.The risk owner manages the risk; the risk actionee implements actions
AnswerD

Correct.

Why this answer

The risk owner is responsible for managing the risk overall. The risk actionee is responsible for carrying out specific risk response actions.

355
MCQmedium

What is the difference between a Request for Change and an Off-specification?

A.A Request for Change is a change to the project scope; an Off-specification is a change to the schedule
B.A Request for Change is raised by the Project Board; an Off-specification is raised by the Project Manager
C.A Request for Change is a proposal for a change; an Off-specification is a non-conformance with a baseline
D.A Request for Change always requires a change budget; an Off-specification does not
AnswerC

Correct distinction.

Why this answer

A Request for Change is a proposal for a change that would modify agreed baselines or requirements. An Off-specification is something that should be provided but is not currently present (or is incorrect).

356
Multi-Selecthard

Which THREE of the following are typical responsibilities of the Project Board?

Select 3 answers
A.Providing resources and authorizing funding
B.Monitoring progress via Highlight Reports
C.Managing the day-to-day activities of the project
D.Approving the Project Initiation Documentation
E.Preparing the Business Case
AnswersA, B, D

The Project Board provides resources.

Why this answer

The Project Board is responsible for approving the PID, monitoring progress via Highlight Reports, and providing resources. Options B, C, and D are correct.

357
MCQmedium

During the Managing Product Delivery process, what is the Team Manager responsible for producing?

A.End Stage Report
B.Exception Report
C.Highlight Report
D.Checkpoint Report
AnswerD

Team Managers produce Checkpoint Reports.

Why this answer

The Team Manager produces Checkpoint Reports to inform the Project Manager of progress within a Work Package.

358
MCQhard

What is the difference between the Starting Up a Project process and the Initiating a Project process?

A.SU creates the Business Case; IP approves it
B.SU produces the Project Brief; IP produces the PID
C.SU appoints the Project Board; IP appoints the Project Manager
D.SU is done by the Project Board; IP is done by the Project Manager
AnswerB

SU outputs Project Brief; IP outputs PID.

Why this answer

SU is a pre-project process to decide whether to initiate; IP formally establishes the project with detailed planning and PID.

359
MCQeasy

Which document is the key output of the Initiating a Project process?

A.Project Brief
B.Project Initiation Documentation
C.End Stage Report
D.Exception Report
AnswerB

Correct: PID is the key output of IP.

Why this answer

The Project Initiation Documentation (PID) is the key output of IP. It provides the foundation for the project.

360
MCQhard

What is the key difference between Project Assurance and Project Support?

A.Project Assurance is a role performed by the Project Manager, whereas Project Support is performed by the team
B.Project Assurance provides independent oversight on behalf of the Project Board; Project Support provides administrative services to the Project Manager
C.Project Assurance focuses on quality, while Project Support focuses on risk management
D.Project Assurance is optional, while Project Support is mandatory
AnswerB

This is the correct distinction as defined in PRINCE2.

Why this answer

Option B is correct because Project Assurance is an independent oversight function, performed on behalf of the Project Board, to ensure that the project is being conducted correctly and remains viable. Project Support, in contrast, is a set of administrative and advisory services provided to the Project Manager to help them manage the project effectively. This distinction is fundamental to PRINCE2's separation of 'doing' from 'checking'.

Exam trap

The trap here is confusing the independent oversight of Project Assurance with the administrative assistance of Project Support, leading candidates to incorrectly assign Assurance to the Project Manager or to think Support is optional.

How to eliminate wrong answers

Option A is wrong because Project Assurance is not performed by the Project Manager; it is an independent role, often fulfilled by someone outside the project management team, while Project Support is provided to the Project Manager, not by the team. Option C is wrong because both Project Assurance and Project Support can address quality and risk; the key difference is not the focus area but the independence and accountability (Assurance reports to the Board, Support assists the Manager). Option D is wrong because both Project Assurance and Project Support are mandatory roles in PRINCE2; neither is optional.

361
MCQeasy

What is the purpose of the Product Breakdown Structure (PBS) in product-based planning?

A.To provide a hierarchical structure of all products that the project will deliver
B.To identify the activities needed to create the products
C.To define the quality criteria for each product
D.To show the sequence of product creation
AnswerA

The PBS is a hierarchical decomposition of products.

Why this answer

The PBS provides a hierarchical decomposition of all products to be created, showing their relationships.

362
MCQeasy

Which of the following is NOT a component of the Business Case?

A.Quality Register
B.Expected benefits
C.Dis-benefits
D.Major risks
AnswerA

The Quality Register is not part of the Business Case; it is a separate management product.

Why this answer

The Business Case includes: reasons, options, expected benefits, dis-benefits, timescale, costs, investment appraisal, and major risks. The Quality Register is a separate document used for tracking quality activities.

363
Multi-Selectmedium

Which THREE of the following statements about the Project Board are correct?

Select 3 answers
A.The Project Board authorizes stage boundaries
B.The Project Board is accountable for the success of the project
C.The Project Board approves the Project Plan
D.The Project Board includes the Project Manager
E.The Project Board meets on a fixed schedule monthly
AnswersA, B, C

Yes, the Board authorizes stage transitions.

Why this answer

Option A is correct because the Project Board is responsible for authorizing the movement from one stage to the next, which includes approving the Stage Plan for the next stage and reviewing the current stage's completion. This is a key control point in PRINCE2's stage-gate management approach, ensuring that the project only proceeds when the Board is satisfied with progress and the business case remains viable.

Exam trap

The trap here is that candidates often confuse the Project Board's composition with the project team, mistakenly including the Project Manager, or assume a fixed meeting schedule similar to a steering committee in other methodologies, whereas PRINCE2 mandates event-driven rather than time-driven Board meetings.

364
MCQmedium

Who is responsible for producing Checkpoint Reports?

A.Team Manager
B.Project Assurance
C.Project Board
D.Project Manager
AnswerA

The Team Manager produces Checkpoint Reports to inform the Project Manager of progress.

Why this answer

Checkpoint Reports are produced by the Team Manager and sent to the Project Manager as part of Managing Product Delivery.

365
MCQmedium

What is the key difference between Project Assurance and a quality review?

A.Project Assurance is performed by the Project Manager; quality review is performed by the team
B.Quality review is a role; Project Assurance is a process
C.They are the same thing
D.Project Assurance is a role; quality review is a technique
AnswerD

Correct. Project Assurance is a continuous role; quality review is a technique used to assess product quality.

Why this answer

Project Assurance is a role within the PRINCE2 management structure, responsible for ensuring that the project remains viable and compliant with the business case, while a quality review is a technique used to assess the quality of a product. Option D correctly distinguishes between these two concepts: Project Assurance is a role, and quality review is a technique. This aligns with PRINCE2's separation of management responsibilities from quality control activities.

Exam trap

The trap here is that candidates confuse the hierarchical nature of PRINCE2 roles and techniques, often misidentifying Project Assurance as a process or quality review as a role, due to the similar-sounding names and overlapping involvement in quality activities.

How to eliminate wrong answers

Option A is wrong because Project Assurance is not performed by the Project Manager; it is an independent role performed by the Project Board or its delegates, while quality review involves the team, but the key difference is not about who performs them. Option B is wrong because it reverses the definitions: quality review is a technique, not a role, and Project Assurance is a role, not a process. Option C is wrong because they are fundamentally different concepts: Project Assurance is a governance role ensuring ongoing compliance, while quality review is a specific technique for product quality assessment.

366
MCQmedium

During the Managing a Stage Boundary process, which report is produced to provide the Project Board with information on the current stage's performance?

A.End Stage Report
B.Checkpoint Report
C.Highlight Report
D.Exception Report
AnswerA

Correct. The End Stage Report is a key output of SB.

Why this answer

The End Stage Report is produced during the Managing a Stage Boundary process to summarize the current stage's performance and inform the Project Board's decision to authorize the next stage.

367
MCQeasy

What is the key output of the Initiating a Project process?

A.Project Brief
B.Project Initiation Documentation
C.Checkpoint Report
D.End Stage Report
AnswerB

The PID is the definitive document created during IP to define the project.

Why this answer

The Initiating a Project process is where the project's scope, objectives, and approach are fully defined and documented. Its key output is the Project Initiation Documentation (PID), which consolidates all the baseline plans and strategies needed to justify and manage the project. The PID replaces the Project Brief, which is created earlier in the Starting Up a Project process.

Exam trap

The trap here is that candidates confuse the Project Brief (created in Starting Up a Project) with the Project Initiation Documentation (created in Initiating a Project), as both contain project definitions, but the PID is the comprehensive, approved baseline that replaces the brief.

How to eliminate wrong answers

Option A is wrong because the Project Brief is an output of the Starting Up a Project process, not the Initiating a Project process; it is used as input to initiate the project but is superseded by the PID. Option C is wrong because a Checkpoint Report is a periodic progress report produced during the Managing a Stage Boundary and Controlling a Stage processes, not during initiation. Option D is wrong because the End Stage Report is produced at the end of each management stage (including the final stage) to report stage progress, not at the start of the project.

368
MCQmedium

During a stage, a team manager discovers a product cannot be delivered on time due to technical issues. The stage plan has no tolerance left for time. What should the team manager do?

A.Inform the Project Manager via a Checkpoint Report
B.Raise an Exception Report directly to the Project Board
C.Continue working and catch up later
D.Request more time from the Senior User
AnswerA

Correct. The team manager reports to the PM, who then decides on escalation.

Why this answer

When a work package tolerance is forecast to be exceeded, the team manager should inform the Project Manager via a Checkpoint Report so the PM can assess impact.

369
MCQmedium

Which process is triggered when the Project Board authorizes a stage plan?

A.Starting Up a Project
B.Managing a Stage Boundary
C.Initiating a Project
D.Controlling a Stage
AnswerD

After a stage plan is authorized, the PM begins controlling that stage.

Why this answer

When the Project Board authorizes a stage plan, the next process to execute is Controlling a Stage, where the Project Manager manages the work of that stage.

370
MCQeasy

Who is responsible for maintaining the Business Case throughout the project?

A.Project Support
B.Executive
C.Project Manager
D.Senior User
AnswerC

The Project Manager maintains the Business Case throughout the project.

Why this answer

The Project Manager maintains the Business Case on behalf of the Executive, who owns it.

371
Multi-Selecthard

Which TWO of the following are differences between the Starting Up a Project (SU) and Initiating a Project (IP) processes?

Select 2 answers
A.SU focuses on whether the project is viable; IP focuses on how the project will be managed
B.SU produces the Project Initiation Documentation
C.IP involves creating the next Stage Plan
D.SU is optional; IP is mandatory
E.SU is done before the project is authorized; IP is done after authorization to initiate
AnswersA, E

SU determines if the project is worthwhile; IP develops detailed management approaches.

Why this answer

Option A is correct because the Starting Up a Project (SU) process is designed to evaluate the project's viability by creating the Project Brief and checking if the project is worthwhile, while the Initiating a Project (IP) process focuses on establishing a solid management foundation by creating the Project Initiation Documentation (PID) and detailed plans for how the project will be managed and controlled.

Exam trap

The trap here is that candidates often confuse the outputs of SU and IP, mistakenly thinking the PID is produced in SU, or that SU is optional, when in fact both processes are mandatory and serve distinct pre- and post-authorization roles.

372
Multi-Selectmedium

Which TWO of the following are types of issues in PRINCE2?

Select 2 answers
A.Risk
B.Defect
C.Request for Change
D.Change Request
E.Off-specification
AnswersC, E

A Request for Change is a formal proposal for a change to a product's specification.

Why this answer

The three issue types are: Request for Change, Off-specification, and Problem/Concern. Options A and B are correct. Options C, D, and E are not official issue types.

373
MCQeasy

Who is responsible for authorising the start of a project in PRINCE2?

A.The Senior Supplier
B.The Project Manager
C.The Senior User
D.The Project Board
AnswerD

The Project Board authorises the project, initiation, and all key decisions.

Why this answer

The Project Board, through the Directing a Project process, authorises initiation, the project itself, stage plans, and closure. The Project Manager recommends but does not authorise. The Senior User and Senior Supplier are members of the Project Board.

374
MCQhard

A project is in the Managing Product Delivery process. The Team Manager discovers a problem that will delay the completion of a Work Package beyond its agreed tolerance. What should the Team Manager do?

A.Update the Work Package tolerance and proceed
B.Raise an Exception Report to the Project Board
C.Continue with the work and report the delay in the next Checkpoint Report
D.Inform the Project Manager and request guidance
AnswerD

The Team Manager should escalate to the Project Manager, who may then raise an Exception Report if needed.

Why this answer

The Team Manager must escalate the issue to the Project Manager promptly, as they cannot exceed Work Package tolerances without authorization. The Project Manager will then handle the escalation.

375
Multi-Selectmedium

Which THREE of the following are responsibilities of the Project Manager?

Select 3 answers
A.Producing Highlight Reports
B.Performing Project Assurance
C.Day-to-day management of the project
D.Chairing the Project Board
E.Maintaining the Business Case
AnswersA, C, E

The PM produces Highlight Reports for the board.

Why this answer

The Project Manager manages day-to-day activities, produces Highlight Reports for the board, and updates the Business Case as needed. The PM does not chair the board or perform assurance.

Page 4

Page 5 of 24

Page 6