PRINCE2 Practices →easyMultiple Choice

PRINCE2F PRINCE2 Practices Practice Question

Which role is responsible for ensuring that the project continues to have business justification?

⚠ Common exam trap

Many exam-takers confuse the Project Manager's responsibility for developing and maintaining the business case with the Executive's accountability for approving and ensuring its ongoing validity.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Executive

The Executive is the single point of accountability for the project and is responsible for ensuring that the project continues to have business justification throughout its lifecycle. This includes approving the business case, monitoring its validity, and making the final decision to continue, change, or close the project based on ongoing justification.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Senior Supplier

    Why it's wrong here

    The Senior Supplier represents those providing resources and expertise, focusing on delivery feasibility and quality rather than ongoing viability. It is tempting because suppliers care about project value, but the Business Case and continued business justification are owned by the Executive, supported by the Business Case theme.

  • ✗

    Senior User

    Why it's wrong here

    The Senior User specifies requirements and represents those who will use the project's outputs, focusing on benefits realisation rather than overall viability. It is tempting because users care about value, but the Executive owns the Business Case and is accountable for continued business justification.

  • ✓

    Executive

    Why this is correct

    The Executive owns the Business Case and is accountable for ensuring the project remains aligned with business objectives and delivers value for money. This role-specific accountability directly satisfies the stem's requirement for whoever confirms continuing business justification.

  • ✗

    Project Manager

    Why it's wrong here

    The Project Manager handles day-to-day delivery, planning, and reporting on the Business Case, but does not own the decision that the project remains justified. It is tempting because the role manages the Business Case document, yet the Executive is accountable for confirming continued business justification.

About these practice questions

One of 1,189 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.