Courseiva
People: organizations, teams, and leadershiphardMultiple ChoiceObjective-mapped

PRINCE2F People: organizations, teams, and leadership Practice Question

A project is in its Controlling a Stage process. The Team Manager reports that a Work Package is likely to be completed late. The Project Manager reviews the Stage Plan and sees that stage tolerance is not forecast to be exceeded. What should the Project Manager do?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Take corrective action within the tolerances delegated by the Project Board.

Since stage tolerance is not threatened, the Project Manager can take corrective action within the delegated tolerances, such as re-planning or re-assigning resources, without escalating to the Project Board.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Instruct the Team Manager to continue as planned.

    Why it's wrong here

    The Project Manager should take corrective action if needed, not ignore the issue.

  • Close the stage early.

    Why it's wrong here

    Closing the stage early is a decision for the Project Board, not the PM.

  • Take corrective action within the tolerances delegated by the Project Board.

    Why this is correct

    The Project Manager can manage within tolerances without escalation.

  • Escalate to the Project Board via an Exception Report.

    Why it's wrong here

    Escalation is only required if stage tolerance is forecast to be exceeded.

About these practice questions

One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

1 more way this is tested on PRINCE2F

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. During the Controlling a Stage process, the Project Manager receives a Checkpoint Report from a Team Manager indicating a delay in delivering a Work Package. What should the Project Manager do first?

medium
  • A.Instruct the Team Manager to recover the delay within the Work Package tolerances
  • B.Close the Work Package and re-plan the stage
  • C.Raise an Exception Report to the Project Board immediately
  • D.Assess the impact on the Stage Plan and decide on corrective action within stage tolerances

Why D: The Project Manager must first assess the impact of the delay on the Stage Plan and decide on corrective action within the agreed stage tolerances. This aligns with the PRINCE2 principle of management by exception, where the Project Manager handles deviations within tolerances before escalating. Only if the delay exceeds stage tolerances should an Exception Report be raised to the Project Board.

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.