A project manager is tailoring PRINCE2 for a project using an agile delivery approach. The project board wants to ensure that the 'Learn from Experience' principle is applied effectively. Which action best demonstrates the application of this principle in this context?
This action demonstrates Learn from Experience by seeking lessons from similar past projects during initiation and maintaining a lessons log. The log is updated as new lessons emerge, and lessons are applied to improve the current project and inform future projects.
Why this answer
Learn from Experience means seeking lessons from previous projects during initiation, maintaining a lessons log, and updating it throughout the project. Lessons should be applied at each stage boundary and used to improve the current project as well as future ones.
Exam trap
The trap here is thinking lessons are only captured at the end of the project or only when something goes wrong, rather than continuously throughout.