Courseiva

PRINCE2F Project Initiation and Stages Practice Question

Which role is responsible for approving the Project Initiation Documentation?

⚠ Common exam trap

PeopleCert often tests the misconception that the Project Manager or a single board member (like the Senior User) can approve the PID, when in fact only the full Project Board has the authority to do so.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Project Board

The Project Board is responsible for approving the Project Initiation Documentation (PID) because it represents the collective authority of the business, user, and supplier interests. The PID formally authorizes the initiation of the project and commits resources, so only the Project Board has the necessary authority to approve it.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    Project Board

    Why this is correct

    The Project Board holds collective accountability for the project's viability, so approving the Project Initiation Documentation sits with it rather than the Project Manager, who authors it. This satisfies the stem's requirement by matching PRINCE2's principle that authority to commit resources rests with the Board, not delegated delivery roles.

  • ✗

    Senior User

    Why it's wrong here

    The Senior User represents user interests on the Project Board and contributes to the PID, but approval requires the Board collectively, including the Executive and Senior Supplier. It is tempting because the Senior User reviews and signs off user-related content, not the document as a whole.

  • ✗

    Project Manager

    Why it's wrong here

    The Project Manager drafts and assembles the Project Initiation Documentation but cannot approve it, since approval authorises the project and sits with the Project Board. It is tempting because the Project Manager owns the document's production, yet approval authority is deliberately separated from authorship.

  • ✗

    Senior Supplier

    Why it's wrong here

    The Senior Supplier represents those delivering the products and provides supplier assurance; approval of the Project Initiation Documentation rests with the Project Board, specifically the Executive. It is tempting because suppliers do agree to deliver project outputs, but that concerns product delivery, not authorising the baseline documentation.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,189-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.