Courseiva
PRINCE2 ProcesseshardMultiple ChoiceObjective-mapped

PRINCE2F PRINCE2 Processes Practice Question

A Project Manager is preparing the End Stage Report. The project has experienced a significant issue that required an Exception Plan. How should the End Stage Report reflect this?

⚠ Common exam trap

It's easy for candidates to think an Exception Plan means the stage was 'off plan' and should be hidden, or that the Exception Report replaces the End Stage Report, when in fact the End Stage Report must transparently document the issue and the Exception Plan's impact.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

It should include a summary of the issue and the impact of the Exception Plan on the stage

The End Stage Report is a management product that provides a summary of the stage's performance against the plan. When an Exception Plan has been used, the End Stage Report must include a summary of the issue that triggered the exception and the impact of the Exception Plan on the stage's objectives, budget, and schedule. This ensures that the Project Board has a complete picture of the stage's actual performance, including any deviations from the original Stage Plan.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • It should not mention the Exception Plan because the stage completed successfully

    Why it's wrong here

    The End Stage Report must include all significant events, including Exception Plans.

  • It should be replaced by the Exception Report

    Why it's wrong here

    The Exception Report is a separate document; the End Stage Report is still required.

  • It should only report the final budget and schedule, not the details of issues

    Why it's wrong here

    The report includes a review of the stage, not just final numbers.

  • It should include a summary of the issue and the impact of the Exception Plan on the stage

    Why this is correct

    The End Stage Report provides a review of the stage, including any issues and their resolution.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.