PRINCE2F · domain
PRINCE2 Processes
Use this page to practise PRINCE2 Processes questions for this certification. Focus on how the exam tests prince2 processes in scenario format — understanding the why behind each answer builds more durable knowledge than memorising options.
Focused practice
Practice PRINCE2 Processes questions
Scored sessions drawing only from this domain — pick a length below.
Start 20-question practice test →What this domain covers
What to know about PRINCE2 Processes
PRINCE2 Processes questions on this certification test your ability to deploy and manage prince2 processes concepts in scenario-based situations.
Core PRINCE2 Processes concepts and how they apply in real-world cloud scenarios.
How to deploy prince2 processes correctly and verify the outcome.
Troubleshooting prince2 processes issues by interpreting error output and system state.
Cloud best practices and PRINCE2 Processes design trade-offs tested by this certification.
Watch out for
Common PRINCE2 Processes exam traps
- ▸Selecting the most expensive service when a simpler managed option meets the requirement.
- ▸Forgetting that cloud resources must be explicitly secured — defaults are rarely secure.
- ▸Choosing a global service fix when the issue is region-specific.
- ▸Overlooking cost implications of cross-region data transfer in architecture questions.
Question index
All PRINCE2 Processes questions (479)
Click any question to see the full explanation, or start a practice session above.
Which statement best describes the difference between Starting Up a Project (SU) and Initiating a Project (IP)?
Hard2Which process includes the activity 'Review the project's progress against the stage plan'?
Medium3Which TWO of the following are outputs of the Starting Up a Project process?
Medium4Refer to the exhibit. The project board is reviewing the End Stage Report for Stage 2 and the Stage Plan for Stage 3. The Stage Plan for Stage 3 exceeds the agreed cost tolerance. According to PRINCE2, what should the project board do?
Medium5In which process does the Project Manager produce an Exception Plan?
Medium6In which process is the Benefits Management Approach first created?
Medium7A project is in the Controlling a Stage process. The project manager receives a request from a team manager to change the design specification because of a technical difficulty. The change would not affect the stage plan or the business case. What should the project manager do first?
Medium8Which of the following is an output of the Directing a Project process?
Medium9Which process is responsible for producing the End Project Report?
Hard10Which process is used by the Project Board to oversee the entire project?
Easy11A Project Manager is planning the next stage. The current stage is on track and within tolerance. Which process is being performed?
Medium12The Project Board is reviewing an Exception Plan and decides to approve it. Which process is the Project Board executing?
Medium13Which of the following correctly distinguishes Project Assurance from Project Support?
Hard14What is the key difference between the Starting Up a Project (SU) and Initiating a Project (IP) processes?
Hard15During the Controlling a Stage process, the Project Manager receives a Checkpoint Report showing that a Work Package is behind schedule. What should the Project Manager do first?
Medium16Which process does the Project Board use to give ad-hoc direction to the project?
Easy17During which process does the Project Manager produce the End Stage Report?
Medium18Which TWO of the following are produced during the Initiating a Project process?
Medium19Which TWO of the following are outputs of the Starting Up a Project process?
Easy20Which output is produced during the Starting Up a Project process?
Easy21What is the purpose of the Closing a Project process?
Medium22A project is forecast to exceed its stage cost tolerance. The Project Manager has raised an Exception Report. Which process does the Project Board use to decide how to respond?
Hard23Which process is triggered when the Project Manager needs to plan the next stage and report on the current stage's performance?
Easy24Refer to the exhibit. PRINCE2 Configuration Item Record Item ID: CI-103 Product: User Authentication Module Version: 2.1 Status: Under Development Baseline: 2.0 Last Review: 2024-01-15 Owner: Project Support Office Issue: The team reports that the latest version (2.1) has a critical defect. The status is 'Under Development' but the baseline is still 2.0. What process should the project manager follow?
Medium25A Work Package has been completed and the Team Manager has delivered the products. The Project Manager notices a minor defect that does not affect the overall product quality. What should the Project Manager do?
Hard26During which process is the End Project Report produced?
Medium27During the Managing a Stage Boundary process, the Project Manager produces an End Stage Report. What is the primary purpose of this report?
Hard28Which TWO of the following are outputs of the Starting Up a Project process?
Medium29Which TWO of the following are outputs of the Initiating a Project process?
Medium30A project is in the Initiating a Project process. Which document is the key output of this process?
Medium31Who is responsible for producing the Highlight Report?
Medium32The Project Board is considering whether to authorize the next stage. Which document provides the information needed for this decision?
Medium33A Project Manager is preparing the End Stage Report. The project has experienced a significant issue that required an Exception Plan. How should the End Stage Report reflect this?
Hard34Which THREE of the following are activities performed during the Directing a Project process?
Hard35During the Initiating a Project process, which document is developed as part of the Project Initiation Documentation?
Hard36Which process ensures that the project's products are delivered according to the agreed quality criteria?
Easy37During which process are Work Packages authorised by the Project Manager?
Medium38Which THREE of the following are roles that are appointed during the Starting Up a Project process?
Medium39A project is forecast to exceed its stage cost tolerance. What should the Project Manager do?
Medium40Which process is responsible for appointing the Executive and the Project Manager?
Easy41Who is responsible for ensuring that the project's business case remains viable throughout the project?
Easy42What is the difference between Starting Up a Project (SU) and Initiating a Project (IP)?
Hard43Which role is responsible for maintaining the Business Case throughout the project?
Easy44Which product is produced during the Starting Up a Project process?
Medium45Which process is responsible for ensuring that products meet their quality criteria before acceptance?
Medium46In the Closing a Project process, which document confirms that the project's products have been accepted?
Hard47Which process is responsible for creating the Project Brief?
Easy48Which process ensures that the project's products are formally handed over and the project is closed in a controlled way?
Easy49Which TWO of the following are outputs of the Initiating a Project process?
Medium50A project is in the delivery stage. The team manager has accepted a work package. Which process governs the team manager's work in delivering the products?
Medium51Which THREE of the following are activities performed during the Controlling a Stage process?
Hard52A project is in an early stage and the Project Manager discovers a new risk that could cause a delay. The risk is within the stage tolerance. What should the Project Manager do?
Hard53What is the purpose of the Managing a Stage Boundary process?
Medium54What is the purpose of the Closing a Project process?
Easy55Which TWO of the following are differences between the Highlight Report and the Checkpoint Report?
Hard56Which THREE of the following are true about the Directing a Project process?
Hard57Which process is used by the Project Board to authorise the start of a new stage?
Medium58Which TWO of the following are true about the relationship between Controlling a Stage (CS) and Managing Product Delivery (MP)?
Hard59During the Managing Product Delivery process, the Team Manager identifies a problem that could affect the quality of a product. What should the Team Manager do?
Hard60What is the difference between the Starting Up a Project (SU) and Initiating a Project (IP) processes?
Hard61In the Managing Product Delivery process, what is the Team Manager responsible for?
Medium62Which TWO of the following are outputs of the Starting Up a Project process?
Medium63What is the purpose of the Closing a Project process?
Easy64Which process is responsible for authorizing the initiation of a project?
Easy65Which THREE of the following are responsibilities of the Project Board in the Directing a Project process?
Hard66What is the purpose of the Managing Product Delivery process?
Hard67Which process is responsible for authorizing the start of each stage?
Easy68Which TWO of the following are produced in the Starting Up a Project process?
Medium69Which document is the key output of the Initiating a Project process?
Medium70In the Directing a Project process, who has the authority to authorize an exception plan that exceeds the project's stage tolerance but remains within project tolerance?
Hard71What is the purpose of the Directing a Project process?
Medium72What is the difference between the Starting Up a Project process and the Initiating a Project process?
Medium73Which of the following is an output of the Initiating a Project process?
Medium74During the Controlling a Stage process, the Project Manager receives a Checkpoint Report. Who prepared this report?
Medium75A project is forecast to exceed its stage cost tolerance. What should the Project Manager do?
Medium76Match each PRINCE2 technique to its description.
Medium77In the Managing Product Delivery process, who is responsible for producing Checkpoint Reports?
Hard78Which process is triggered when a Stage Plan's tolerances are forecast to be exceeded?
Easy79During the Controlling a Stage process, the project manager receives a Checkpoint Report from the team manager. What is the primary purpose of this report?
Hard80Which THREE of the following are activities of the Managing a Stage Boundary process?
Hard81A team is working on a Work Package. The Team Manager needs to report progress to the Project Manager. Which report should be used?
Medium82Which process is responsible for authorizing the initiation of a project?
Easy83What is the purpose of the Starting Up a Project process?
Easy84During the Managing Product Delivery process, the Team Manager identifies a quality issue that will delay the product's delivery. What should the Team Manager do?
Hard85Who is responsible for authorizing the initiation of a project?
Easy86What is the difference between Starting Up a Project (SU) and Initiating a Project (IP)?
Medium87Which TWO of the following are true about the Managing a Stage Boundary process?
Hard88Which process is responsible for authorizing the work to be done in a stage?
Easy89During the Initiating a Project process, which management approach is created to define how benefits will be realized?
Medium90What is the purpose of the Directing a Project process?
Medium91The project manager is preparing the next Stage Plan during the Managing a Stage Boundary process. Which document should be used as the basis for updating the Business Case?
Hard92Which process covers the Project Board's decision to authorise project closure?
Easy93During the Controlling a Stage process, the Project Manager receives a Checkpoint Report. Who prepared this report?
Medium94Who is responsible for producing the End Stage Report?
Medium95Which document is the key output of the Initiating a Project process?
Easy96During the Managing a Stage Boundary process, the project manager produces an End Stage Report. Who receives this report and what decision do they make?
Medium97Which THREE of the following are activities performed during the Managing a Stage Boundary process?
Medium98Which THREE of the following are responsibilities of the Project Board during the Directing a Project process?
Hard99The Project Board is reviewing an Exception Plan submitted by the Project Manager. Which process is the Project Board performing?
Medium100Which THREE of the following are activities performed during the Directing a Project process?
Hard101During the Closing a Project process, which document is produced to capture lessons for future projects?
Medium102The Project Board is considering a request to close a project early due to loss of business justification. Which process is the Project Board using to make this decision?
Medium103What is the difference between the Starting Up a Project process and the Initiating a Project process?
Hard104Which document is the key output of the Initiating a Project process?
Easy105Who is responsible for producing Checkpoint Reports?
Medium106During the Managing a Stage Boundary process, which report is produced to provide the Project Board with information on the current stage's performance?
Medium107What is the key output of the Initiating a Project process?
Easy108Which process is triggered when the Project Board authorizes a stage plan?
Medium109Which TWO of the following are differences between the Starting Up a Project (SU) and Initiating a Project (IP) processes?
Hard110Who is responsible for authorising the start of a project in PRINCE2?
Easy111A project is in the Managing Product Delivery process. The Team Manager discovers a problem that will delay the completion of a Work Package beyond its agreed tolerance. What should the Team Manager do?
Hard112Which process is responsible for appointing the Executive and the Project Manager?
Easy113During a stage, a Team Manager identifies a quality problem with a product. This is reported as an Off-specification. According to PRINCE2, what is the first action the Project Manager should take?
Hard114Which THREE of the following are responsibilities of the Project Board during the Directing a Project process?
Hard115A Project Manager receives a Checkpoint Report from a Team Manager. Which process is the Project Manager executing when they review this report?
Hard116What is the purpose of the Managing Product Delivery process?
Medium117Which role produces Highlight Reports?
Easy118Which THREE activities are performed in the Managing a Stage Boundary process?
Hard119Which TWO roles are appointed during the Starting Up a Project process?
Easy120Which process is responsible for the project board giving ad-hoc direction to the project manager?
Easy121What is the first process in PRINCE2?
Easy122Which THREE of the following are activities performed in the Closing a Project process?
Medium123In the Closing a Project process, which document is produced to capture lessons learned for future projects?
Medium124In the Controlling a Stage process, the Project Manager receives a Checkpoint Report indicating that a work package is behind schedule. What should the Project Manager do first?
Hard125In the Managing a Stage Boundary process, what is produced to request permission to proceed to the next stage?
Hard126Refer to the exhibit. The project manager is reviewing a completed work package in Stage 2. The actual cost exceeds the planned cost by $5,000. What should the project manager do?
Easy127What is the purpose of the Closing a Project process?
Easy128What is the purpose of the Starting Up a Project process?
Easy129Which process is used by the Project Board to give ad-hoc direction to the Project Manager?
Easy130During the Controlling a Stage process, the Project Manager receives a Checkpoint Report showing that a Work Package is behind schedule. What should the Project Manager do first?
Medium131A Project Manager is preparing the Project Initiation Documentation. In which process is this work done?
Medium132A project is forecast to exceed its stage cost tolerance. What is the Project Manager's first action?
Medium133Which TWO of the following statements about the Directing a Project process are true?
Hard134Which process is used by the Project Board to authorize the next stage of a project?
Medium135During the Managing Product Delivery process, what is used to assign work to the Team Manager?
Medium136The Project Board authorizes an Exception Plan. In which process does the Project Manager produce the Exception Plan?
Hard137A project is in the Closing a Project process. What must be produced before the Project Board can authorise project closure?
Medium138Which process is responsible for authorizing the initiation of a project?
Easy139During the Managing a Stage Boundary process, which document is produced to seek approval to proceed to the next stage?
Medium140Which TWO of the following are outputs of the Closing a Project process?
Medium141What is the purpose of the Starting Up a Project process?
Medium142Which THREE of the following are responsibilities of the Project Manager during the Controlling a Stage process?
Hard143Which TWO of the following are true about the Managing Product Delivery process?
Medium144Which of the following statements about Starting Up a Project (SU) and Initiating a Project (IP) is true?
Hard145During the Controlling a Stage process, the Project Manager identifies a deviation that is expected to remain within the stage tolerance. What should the Project Manager do?
Hard146What is the purpose of the Directing a Project process?
Easy147In which process is the Project Manager appointed?
Easy148In which process does the Project Board decide whether to authorise an Exception Plan?
Hard149Which TWO of the following are responsibilities of the Project Board in the Directing a Project process?
Medium150Who is responsible for producing the Lessons Report at the end of the project?
Hard151During which process are the Benefits Management Approach and the Project Plan created?
Medium152Which TWO of the following are purposes of the Managing Product Delivery process?
Medium153Which THREE of the following are responsibilities of the Project Board during the Directing a Project process?
Medium154What is the purpose of the Closing a Project process?
Easy155Which process is responsible for authorizing the initiation of a project?
Easy156Who is responsible for authorizing the initiation of a project?
Easy157A project is in the Initiating a Project process. The project manager is creating the Project Plan. Which management product should be used as a key input for developing the Project Plan?
Easy158What is the difference between Starting Up a Project and Initiating a Project?
Hard159Which TWO of the following are responsibilities of the Project Board in the Directing a Project process?
Hard160A project is in the Initiating a Project process. Which activity would typically be performed during this process?
Hard161Which process is the first to be executed in a PRINCE2 project?
Easy162During the Controlling a Stage process, the Project Manager receives a Checkpoint Report indicating a team member will be unavailable for two weeks. What should the Project Manager do first?
Hard163Which document is the key output of the Initiating a Project process?
Medium164Which TWO of the following are outputs of the Starting Up a Project process?
Medium165Who is responsible for producing the Highlight Report during the Controlling a Stage process?
Medium166What is the difference between a Highlight Report and a Checkpoint Report?
Hard167Which process ensures that products are delivered according to the Work Package requirements?
Easy168The Project Manager identifies that the project's approved Business Case is no longer viable. Which process should the Project Manager use to escalate this?
Hard169Which process includes the activity 'Authorize Work Packages'?
Medium170A project is in the Closing a Project process. Which of the following is a required activity before the Project Board can authorize closure?
Hard171Which process is used by the Project Manager to assign work to the Team Manager?
Easy172Which TWO of the following are outputs of the Starting Up a Project process?
Medium173Who is responsible for ensuring that the products are delivered in accordance with the Work Package?
Easy174A project is in the Managing a Stage Boundary process. Which of the following is produced during this process?
Hard175In the Directing a Project process, when does the project board authorize the project?
Medium176A project is in the Managing Product Delivery process. A team member identifies a quality issue with a product being developed. Who is responsible for producing a Checkpoint Report?
Hard177Which process is responsible for authorising the project's closure?
Easy178Who is responsible for producing the Highlight Report during the Controlling a Stage process?
Easy179What is the purpose of the Starting Up a Project process?
Easy180Which TWO of the following are outputs of the Managing a Stage Boundary process?
Medium181In PRINCE2, who is responsible for updating the Business Case during the project?
Medium182Which TWO of the following are outputs of the Managing a Stage Boundary process?
Medium183You are the project manager for a construction project. The project is in the Initiating a Project process. The project board has approved the project brief, and you are now developing the project initiation documentation (PID). During this process, you identify that the project's business case is no longer viable due to a change in market conditions. What is the most appropriate action?
Easy184What is the purpose of the Directing a Project process?
Easy185Which TWO of the following are typical activities in the Closing a Project process?
Easy186What is the purpose of the Closing a Project process?
Medium187A project manager is planning the next stage. Which process should they use to produce the next Stage Plan and an End Stage Report?
Medium188Which TWO of the following are purposes of the Directing a Project process?
Medium189A project manager is closing a project using the Closing a Project process. The project has delivered all products, but the business case has not been fully realized because the expected benefits will take longer to materialize. What should the project manager do with the Benefits Management Approach?
Hard190Which process is responsible for appointing the Executive and the Project Manager?
Easy191Who is responsible for producing Highlight Reports?
Easy192What is the difference between a Highlight Report and an Exception Report?
Hard193Which THREE of the following are activities performed in the Controlling a Stage process?
Medium194During the Managing Product Delivery process, the Team Manager completes a product. What should happen next?
Hard195In the Managing Product Delivery process, who produces Checkpoint Reports?
Hard196A project manager is reviewing progress and identifies a product that does not meet its quality criteria. What should the project manager do?
Medium197A project manager is preparing the End Stage Report for the second stage. The project's planned budget for the stage is $500,000, but actual costs are $520,000. The project board is concerned about cost overrun. What is the most appropriate action for the project manager?
Hard198Which TWO of the following are outputs of the Initiating a Project process?
Medium199A Work Package has been authorized, but the Team Manager discovers that the work will require more effort than estimated. The tolerance for the Work Package is insufficient. What should the Team Manager do?
Hard200What should the Project Manager do when a stage is forecast to exceed its tolerance?
Medium201A project manager is initiating a project using PRINCE2. The project board has approved the project mandate, but the project manager is unsure about the next step. Which process should be executed first?
Medium202During the Controlling a Stage process, the Project Manager identifies that the project is forecast to exceed the agreed cost tolerance for the current stage. What should the Project Manager do?
Medium203Which process is responsible for authorizing the initiation of a project?
Easy204Which process produces the Project Brief?
Easy205The Project Board has requested a report summarizing the current stage performance and the plan for the next stage. Which process should the Project Manager use?
Medium206Who is responsible for producing Checkpoint Reports?
Medium207During which process are Work Packages authorised by the Project Manager?
Medium208A Work Package is authorized by the Project Manager. In which process does this happen?
Medium209Which TWO of the following are outputs of the Initiating a Project process?
Medium210In which process are Highlight Reports produced and sent to the Project Board?
Medium211A project is in the Managing a Stage Boundary process. Which TWO outputs are produced during this process? (Select TWO)
Hard212What is the purpose of the Starting Up a Project process?
Easy213Which document is produced in the Starting Up a Project process and is used as input to Initiating a Project?
Medium214Which process is used by the Project Manager to authorize work for a Team Manager?
Easy215A project team is about to begin the first stage of a project. The project board has approved the project initiation documentation. Which process should be used to authorize the work?
Easy216A project is in the Managing a Stage Boundary process. The Project Manager identifies a deviation that will cause the stage to exceed its tolerance. What should the Project Manager produce?
Hard217During the Controlling a Stage process, the Project Manager receives a Checkpoint Report from a Team Manager. What is the primary purpose of this report?
Hard218Which TWO of the following are outputs of the Managing a Stage Boundary process?
Medium219What is the purpose of the Starting Up a Project process?
Easy220Which process provides the Project Board with information needed to decide whether to authorize project initiation?
Easy221What is the primary purpose of the Managing Product Delivery process?
Easy222Which TWO of the following are outputs of the Initiating a Project process?
Medium223What is the purpose of the Directing a Project process?
Easy224In the Starting Up a Project process, which document is created that outlines the project's scope, objectives, and approach?
Hard225During the Controlling a Stage process, who receives the Highlight Report?
Medium226Who is responsible for maintaining the Business Case throughout the project?
Easy227Which THREE of the following are components of the Project Initiation Documentation (PID)?
Medium228A Project Manager is reviewing progress during a stage and notices that the stage is on track. Which report should the Project Manager send to the Project Board?
Medium229Which process produces the End Project Report?
Easy230What is the key difference between the Starting Up a Project (SU) and Initiating a Project (IP) processes?
Hard231Which THREE of the following are activities performed during the Controlling a Stage process?
Hard232A Project Manager receives a Checkpoint Report from a Team Manager. Which process is the Team Manager executing when producing this report?
Medium233During the Controlling a Stage process, a Team Manager reports that a work package is complete. What is the next step for the Project Manager?
Hard234A Project Manager is reviewing progress during a stage and discovers that a Work Package is behind schedule. The Team Manager has not submitted a Checkpoint Report this week. What should the Project Manager do?
Hard235A project is in the Initiating a Project process. Which of the following is produced during this process?
Medium236The Project Manager receives a Highlight Report from the Project Board. Is this correct?
Medium237Which TWO of the following reports are produced by the Project Manager during the Controlling a Stage process?
Medium238What is the purpose of the Starting Up a Project (SU) process?
Easy239During which process is the Project Initiation Documentation (PID) created?
Medium240Which THREE activities are part of the Initiating a Project process?
Hard241The Project Board receives a Highlight Report indicating that the stage is on track. However, a Team Manager has identified a potential risk that could impact the next stage. What should the Project Manager do?
Medium242Which process is used by the Project Manager to prepare the End Stage Report and the next Stage Plan?
Medium243During which process are lessons for the project first recorded?
Medium244In the Starting Up a Project process, the project manager is appointed. Who appoints the project manager?
Hard245Which TWO outputs are produced during the Initiating a Project process?
Medium246What is the key output of the Starting Up a Project process?
Easy247Which TWO of the following are outputs of the Starting Up a Project process?
Easy248A Work Package is being executed. The Team Manager discovers a product cannot meet its quality criteria due to an unforeseen technical limitation. What should the Team Manager do?
Hard249Which TWO of the following are produced during the Starting Up a Project process?
Medium250Which document is the key output of the Initiating a Project process?
Easy251A project is in the Initiating a Project process. Which management product defines how the project will be controlled?
Medium252Which process covers the day-to-day management of a stage by the Project Manager?
Easy253A project is in the Initiating a Project process. Which document is the key output of this process?
Medium254The Project Board is reviewing the End Stage Report and the next Stage Plan. Which process are they performing?
Medium255During the Controlling a Stage process, the Project Manager needs to assign work to a team. What should the Project Manager create?
Medium256Who is responsible for authorising the initiation of a project?
Easy257Which THREE of the following are responsibilities of the Project Manager during the Controlling a Stage process?
Hard258Which TWO of the following statements about the Directing a Project process are correct?
Medium259Which TWO of the following are outputs of the Starting Up a Project process?
Medium260Which TWO of the following are responsibilities of the Project Board?
Medium261During a stage, a Team Manager identifies a quality problem with a product. The product fails its quality inspection. What should the Team Manager do?
Hard262Which TWO of the following are outputs of the Starting Up a Project process?
Medium263During which process is the Benefits Management Approach first produced?
Medium264Which process is the Project Board's primary process for making key decisions?
Easy265During the Controlling a Stage process, the Project Manager receives a Highlight Report from a Team Manager. What should the Project Manager do with this information?
Medium266During the Closing a Project process, which document is produced to capture lessons for future projects?
Medium267Who is responsible for authorising the initiation of a project?
Medium268During the Managing Product Delivery process, what does the Team Manager produce to inform the Project Manager of progress?
Medium269A Team Manager sends a Checkpoint Report to the Project Manager. Which process is the Team Manager executing?
Medium270During the Closing a Project process, the Project Manager produces a Lessons Report. What should happen to this report?
Hard271What is the main difference between the Starting Up a Project process and the Initiating a Project process?
Medium272The Project Board has authorized the project and the first stage. Which process is used by the Project Manager to manage the work of the first stage?
Medium273During which process does the Project Manager produce a Highlight Report for the Project Board?
Medium274Which TWO of the following are true about the Managing Product Delivery process?
Hard275Which TWO of the following are outputs of the Initiating a Project process?
Medium276In the Managing Product Delivery process, who produces the Checkpoint Report?
Hard277In the Managing Product Delivery process, who is responsible for producing Checkpoint Reports?
Medium278Who is responsible for approving the End Project Report?
Easy279Which document is produced in the Initiating a Project process and provides a baseline for the project?
Medium280In which process does the Project Manager prepare an Exception Plan?
Hard281Which THREE of the following are responsibilities of the Project Board during the Directing a Project process?
Medium282Which TWO statements about the Managing Product Delivery process are correct?
Medium283Which TWO activities are part of the Closing a Project process?
Medium284In the Managing Product Delivery process, who is responsible for producing Checkpoint Reports?
Easy285Which process is responsible for authorising the initiation of a project?
Easy286What is the purpose of the Starting Up a Project process?
Easy287During the Controlling a Stage process, the Project Manager receives a Checkpoint Report from the Team Manager. What should the Project Manager do with this report?
Medium288Who produces Checkpoint Reports?
Medium289Which document is the key output of the Initiating a Project process?
Easy290Which process is triggered when the Project Manager identifies that a stage tolerance is forecast to be exceeded?
Easy291Which TWO of the following are outputs of the Closing a Project process?
Medium292Who is responsible for authorizing the initiation of a project?
Medium293A project manager is planning a project and needs to decide at which point the project board should approve the project's initiation. According to PRINCE2, which process is responsible for obtaining approval to proceed with the initiation stage?
Medium294Which process includes the activity 'Authorize a Work Package'?
Easy295During which process does the Project Manager produce a Highlight Report?
Easy296Who is responsible for producing Checkpoint Reports?
Medium297Which TWO of the following are outputs of the Initiating a Project process?
Medium298What is the purpose of the Starting Up a Project process?
Easy299A Team Manager has completed the work assigned in a Work Package. Which process is used to deliver the completed products back to the Project Manager?
Medium300Which process includes the activity of 'authorizing a Work Package'?
Medium301Who is responsible for producing Checkpoint Reports?
Easy302During the Managing a Stage Boundary process, the project manager produces an End Stage Report for the current stage and a Stage Plan for the next stage. However, the project board rejects the Stage Plan. What is the project manager's next course of action according to PRINCE2?
Hard303Which of the following is a key output of the Managing a Stage Boundary process?
Hard304In the Directing a Project process, which activity is performed by the Project Board when a stage is complete?
Hard305Which process provides the Project Board with information needed to evaluate the project's ongoing viability at the end of each stage?
Easy306You are the project manager for a software development project following PRINCE2. The project is in its second stage, which has a budget tolerance of 10% above the planned cost of $200,000. The project board is composed of the executive, senior user, and senior supplier. The team has been working on a critical feature, but a key supplier has announced a 15% price increase for their services, effective immediately. This increase will push the stage costs to $230,000, exceeding the tolerance. The project manager must decide the best course of action. Which option should the project manager take?
Hard307A project is in the Initiating a Project process. Which document describes how changes to baselined products will be managed?
Hard308During the Controlling a Stage process, the Project Manager identifies an issue that could affect the project's ability to meet its agreed tolerances. What is the first action the Project Manager should take?
Hard309What is the purpose of the Directing a Project process?
Easy310A Project Manager receives a Checkpoint Report from a Team Manager. In which process does this occur?
Medium311Which statement correctly distinguishes the Starting Up a Project process from the Initiating a Project process?
Hard312Which THREE of the following are components of the Project Initiation Documentation (PID)?
Medium313Who is responsible for producing the End Project Report?
Easy314Which THREE of the following are outputs of the Starting Up a Project process?
Hard315Which process is performed by the Project Board to authorize the start of a project?
Easy316Which document is the key output of the Initiating a Project process?
Medium317What is the difference between the Starting Up a Project (SU) and Initiating a Project (IP) processes?
Hard318What is the purpose of the Managing Product Delivery process?
Easy319Which process is responsible for ensuring that the project does not proceed until the Project Board has authorized the initiation?
Medium320Which TWO of the following are outputs of the Managing a Stage Boundary process?
Medium321Which document is the key output of the Initiating a Project process?
Easy322The Project Manager has identified an issue that could cause a delay in the current stage. The issue cannot be resolved within the stage's tolerance. What should the Project Manager do?
Medium323What is the purpose of the Closing a Project process?
Easy324Who is responsible for ensuring that the project's products meet their quality criteria before acceptance?
Medium325Which role is responsible for maintaining the Business Case throughout the project?
Medium326Which TWO statements about the Initiating a Project process are correct?
Hard327Which TWO of the following are purposes of the Controlling a Stage process?
Medium328Which process is responsible for capturing lessons learned at the end of a stage?
Hard329Which TWO of the following are produced during the Managing a Stage Boundary process?
Medium330Which process is responsible for authorizing Work Packages?
Easy331What is the purpose of the Managing a Stage Boundary process?
Medium332During the Managing a Stage Boundary process, the Project Manager produces an End Stage Report. What is the purpose of this report?
Medium333What is the difference between a Checkpoint Report and a Highlight Report in PRINCE2?
Hard334What is the purpose of the Managing Product Delivery process?
Medium335Which process produces the Daily Log as an output?
Easy336Who produces Checkpoint Reports during the Managing Product Delivery process?
Medium337During which process does the Project Manager produce an Exception Plan?
Hard338Who is responsible for ensuring that project assurance is independent of the Project Manager?
Hard339What is the difference between the Starting Up a Project (SU) process and the Initiating a Project (IP) process?
Hard340Which process is triggered when the Project Manager needs to escalate an exception to the Project Board?
Easy341What is the difference between a Request for Change and an Off-specification?
Hard342During the Closing a Project process, what must be produced to confirm that the project has delivered what was expected?
Medium343Which THREE of the following are responsibilities of the Project Board during the Directing a Project process?
Hard344Refer to the exhibit. A project has just completed the Starting up a Project process and received authorization to initiate. Which process should the project manager execute next?
Easy345Which document is the key output of the Initiating a Project process?
Easy346Which THREE of the following are outputs of the Initiating a Project process?
Medium347A Team Manager is assigned a Work Package. In which process does the Team Manager execute the work and deliver the products?
Medium348Which TWO of the following are activities performed during the Controlling a Stage process?
Medium349A Project Manager is in the Managing a Stage Boundary process and has produced the End Stage Report. The project is forecasting to exceed the project-level cost tolerance. What must the PM include in the next Stage Plan?
Hard350In the Closing a Project process, what is the Project Manager responsible for producing?
Medium351Which document is the key output of the Initiating a Project process?
Easy352During which process does the Project Board give ad-hoc direction to the Project Manager?
Medium353A Team Manager is assigned a Work Package. The Team Manager realizes that the work cannot be completed within the agreed tolerances. What should the Team Manager do?
Hard354A project is forecast to exceed its stage cost tolerance. What should the Project Manager do?
Hard355What is the purpose of the Directing a Project process?
Medium356When should the Project Manager escalate an issue to the Project Board?
Medium357A project is in the Managing a Stage Boundary process. Which document should the Project Manager produce to report the current stage's performance?
Medium358Which THREE of the following are components of the Project Initiation Documentation (PID)?
Hard359Which TWO of the following are responsibilities of the Project Manager during the Controlling a Stage process?
Hard360Who is responsible for producing a Checkpoint Report?
Medium361Which role is responsible for authorizing the initiation of a project?
Medium362In the Controlling a Stage process, a Team Manager reports that a product is complete. Which activity does the Project Manager perform next?
Hard363A project is in its final stage. The Project Manager has prepared the End Project Report and Lessons Report. What must happen before the project can be closed?
Hard364During the Managing a Stage Boundary process, the Project Manager produces an End Stage Report. What is the primary purpose of this report?
Hard365What is the purpose of the Closing a Project process?
Easy366What is the difference between Starting Up a Project and Initiating a Project?
Medium367In the Directing a Project process, the Project Board authorizes an Exception Plan. What triggers the need for an Exception Plan?
Hard368Which THREE of the following are responsibilities of the Project Board during the Directing a Project process?
Hard369During the Managing Product Delivery process, who produces Checkpoint Reports?
Medium370Which PRINCE2 process produces the Project Initiation Documentation (PID)?
Easy371A project is in the Managing a Stage Boundary process. The Project Manager has produced an End Stage Report. What else must be produced?
Hard372What is the purpose of the Starting Up a Project process?
Easy373A project is nearing the end of its final stage. The Project Manager has prepared the End Project Report and a Lessons Report. Which process is responsible for authorising the project closure?
Hard374Which process is responsible for appointing the Executive and the Project Manager?
Easy375What is the primary difference between Starting Up a Project (SU) and Initiating a Project (IP)?
Hard376A Project Manager is planning the next stage and updates the Project Plan. In which process is this activity performed?
Hard377During the Managing Product Delivery process, who produces the Checkpoint Report?
Medium378Which process includes the activity of 'Authorize Work Packages'?
Medium379Which document is the key output of the Initiating a Project process?
Easy380During the Directing a Project process, the Project Board receives an Exception Report. What action should the Project Board take?
Medium381Which TWO of the following are outputs of the Initiating a Project process?
Medium382A Work Package has been completed and the products have passed quality checks. What should the Team Manager do next in the Managing Product Delivery process?
Medium383In the Closing a Project process, what is the Project Board's responsibility?
Hard384Which document is the key output of the Initiating a Project process?
Medium385Which TWO of the following are responsibilities of the Project Manager during the Controlling a Stage process?
Medium386Which document is the key output of the Initiating a Project process?
Easy387A project is in the Closing a Project process. What should the Project Manager produce to recommend project closure?
Medium388Which THREE activities are part of the Controlling a Stage process?
Hard389A Team Manager completes a Work Package and requests formal acceptance of the product. Which process handles this?
Medium390What is the purpose of the Starting Up a Project process?
Medium391In the Directing a Project process, which of the following is a key responsibility of the Project Board?
Easy392During the Controlling a Stage process, who is responsible for producing Checkpoint Reports?
Medium393During the Initiating a Project process, which document is the key output that defines how the project will be managed?
Medium394Which TWO of the following are activities performed in the Directing a Project process?
Medium395Which TWO of the following are responsibilities of the Project Manager during the Controlling a Stage process?
Hard396Which TWO documents are produced during the Starting Up a Project process?
Easy397Who is responsible for authorising the initiation of a project?
Easy398During the Initiating a Project process, the project manager is reviewing the Business Case. Which statement best describes the purpose of this review?
Easy399Which document is the key output of the Initiating a Project process?
Easy400Who produces Checkpoint Reports?
Medium401What is the difference between Starting Up a Project and Initiating a Project?
Medium402The Project Board has received an Exception Report from the Project Manager. What is the Project Board's next step?
Medium403What is the difference between the Starting Up a Project (SU) and Initiating a Project (IP) processes?
Hard404In the Managing a Stage Boundary process, the Project Manager updates the Project Plan. What is the main purpose of this update?
Hard405The Project Board gives ad-hoc direction during which process?
Hard406A Work Package is being executed by the Team Manager. During this, the Team Manager identifies a new risk that could delay delivery. What should the Team Manager do?
Medium407Which THREE of the following are activities of the Managing a Stage Boundary process?
Medium408Which report from the Team Manager is used by the Project Manager to review progress within a stage?
Hard409Who is responsible for reviewing the End Stage Report and deciding whether to authorize the next stage?
Medium410During which process are the Benefits Management Approach and the Risk Management Approach first created?
Medium411Which process is responsible for authorising the initiation of a project?
Easy412What is the purpose of the Starting Up a Project process?
Easy413A project is in the Initiating a Project process. Which document is the key output that defines how the project will be managed?
Medium414What is the difference between Starting Up a Project and Initiating a Project?
Hard415What is the purpose of the Closing a Project process?
Easy416During the Controlling a Stage process, which report does the Project Manager send to the Project Board?
Medium417Which TWO of the following statements about the Managing Product Delivery process are correct?
Hard418According to PRINCE2, which process is responsible for ensuring that the project has a clear and agreed start before any substantial work is undertaken?
Medium419What is the primary difference between Managing Product Delivery and Controlling a Stage?
Hard420Which document is the key output of the Initiating a Project process?
Easy421A Project Manager is about to begin work on a new stage. Which document provides the authority to proceed with the stage?
Medium422Which THREE of the following are activities performed during the Controlling a Stage process?
Medium423Which process ensures that the project's products are handed over and the project is formally closed?
Easy424Which TWO of the following are outputs of the Initiating a Project process?
Medium425What is the purpose of the Managing a Stage Boundary process?
Medium426A project has completed all work but the Project Manager discovers that a key product was delivered with a minor defect that does not affect the Business Case. What should the Project Manager do during Closing a Project?
Hard427Which process is responsible for authorizing the initiation of a project?
Easy428During the Closing a Project process, which document is used to confirm that the project's products have been accepted?
Hard429Which role is responsible for producing the Highlight Report?
Medium430The Project Board has authorized a Stage Plan. During the stage, the Project Manager identifies a risk that could cause the stage to exceed its time tolerance. What should the Project Manager do first?
Medium431Which THREE of the following are responsibilities of the Project Board during the Directing a Project process?
Medium432A Team Manager identifies a quality problem in a product that is being delivered. What should the Team Manager do?
Hard433In which process are Work Packages authorized and progress reviewed by the Project Manager?
Medium434Which process ensures that the project's products are formally handed over to the operational environment?
Medium435Which process is responsible for producing the End Project Report?
Medium436Which TWO of the following are outputs of the Starting Up a Project process?
Medium437What is the purpose of the Closing a Project process?
Easy438The Project Manager has produced an End Stage Report for the current stage. According to PRINCE2, what is the next step?
Medium439During the Managing Product Delivery process, a Team Manager discovers that a product cannot meet its quality criteria without significant extra work. What should the Team Manager do?
Medium440Which TWO documents are produced during the Closing a Project process?
Medium441In which process are the Project Board's key decisions made, such as authorizing initiation and authorizing stage plans?
Medium442In which process is the End Stage Report produced?
Medium443The Project Board wants to provide ad-hoc direction to the Project Manager regarding a critical issue. Which process should the Project Board use?
Medium444Which process is the Project Board primarily responsible for, according to PRINCE2?
Hard445Which TWO of the following activities are performed in the Starting Up a Project process?
Hard446What is the purpose of the Starting Up a Project process?
Easy447A project is in its final stage. The Project Manager has verified that all products have been accepted and operational support is in place. Which process should the Project Manager initiate next?
Medium448During the Controlling a Stage process, the Project Manager identifies that the project is forecast to exceed the agreed cost tolerance for the current stage. What should the Project Manager do?
Medium449Drag and drop the steps to manage a configuration item in PRINCE2 into the correct order.
Medium450The project manager notices that a team member has not completed a critical product according to the quality criteria. What should the project manager do first?
Medium451During the Initiating a Project process, which document details how quality will be managed on the project?
Medium452A project is in the Initiating a Project process. Which management product is defined as the key output of this process?
Hard453Which process is responsible for authorizing a Work Package?
Easy454A project is in the Controlling a Stage process, and the Project Manager receives a Request for Change (RFC) from a stakeholder. What should the Project Manager do first?
Hard455Which TWO of the following are outputs of the Initiating a Project process?
Medium456In which process are End Stage Reports produced?
Medium457The Project Board is considering whether to approve an Exception Plan. Which process should they use to make this decision?
Hard458Which TWO of the following are components of the Project Initiation Documentation (PID)?
Easy459During the Controlling a Stage process, the Project Manager receives a Checkpoint Report indicating that a product will be delivered late. What should the Project Manager do first?
Hard460During which process is the Business Case formally created and reviewed?
Medium461Which process ensures that the project's products are formally accepted and the project is closed in a controlled way?
Easy462Which TWO processes involve the Project Board making key authorizations? (Select two)
Hard463The Project Board has given ad-hoc direction to the Project Manager. In which process does this occur?
Medium464During the Closing a Project process, what is the purpose of the End Project Report?
Medium465Who is responsible for authorizing the initiation of a project?
Medium466What is the purpose of the Closing a Project process?
Easy467Which TWO of the following are activities performed in the Directing a Project process?
Medium468Which THREE of the following are outputs of the Initiating a Project process?
Medium469Who is responsible for authorizing a Work Package?
Easy470Which THREE of the following are correct responsibilities of the Project Board in the Directing a Project process?
Hard471A project is underway, and the project manager notices that the team is frequently re-prioritizing work and losing focus. Which PRINCE2 process should the project manager use to re-establish control?
Medium472Which THREE of the following are activities performed in the Controlling a Stage process?
Hard473What is the purpose of the Closing a Project process?
Medium474Which process is used by the Project Board to give ad-hoc direction to the project?
Easy475What is the purpose of the Starting Up a Project process?
Easy476Which TWO of the following are activities performed in the Managing a Stage Boundary process?
Medium477A project is forecast to exceed its stage cost tolerance. What should the Project Manager do?
Medium478Which TWO of the following are purposes of the Managing Product Delivery process?
Easy479Who is responsible for ensuring that the Business Case remains viable throughout the project?
EasyOther domains
All PRINCE2F exam domains
Frequently asked questions
- What does the PRINCE2 Processes domain cover on the PRINCE2F exam?
- PRINCE2 Processes questions on this certification test your ability to deploy and manage prince2 processes concepts in scenario-based situations.
- How many questions are in this domain?
- This page lists all 479 PRINCE2 Processes questions in the PRINCE2F question bank. The actual exam draws from this domain proportionally to its weighting in the official exam blueprint.
- What is the best way to practise this domain?
- Start with a short focused session (10 questions) to identify gaps, then work through explanations. Repeat with a longer session once the weak areas feel solid.
- Can I practise only PRINCE2 Processes questions?
- Yes — the session launcher on this page filters questions to this domain only. Choose any session length for inline explanations and scoring.