Courseiva
PRINCE2 PracticesmediumMultiple ChoiceObjective-mapped

PRINCE2F PRINCE2 Practices Practice Question

In PRINCE2, which document is used to record quality activities and their results?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Quality Register

The Quality Register is a log of all planned quality checks and their results.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Project Plan

    Why it's wrong here

    The project plan includes schedules, not quality records.

  • Quality Register

    Why this is correct

    The Quality Register records quality activities and outcomes.

  • Quality Management Strategy

    Why it's wrong here

    The strategy describes how quality will be managed, not the record of results.

  • Product Description

    Why it's wrong here

    Product descriptions define quality criteria for specific products.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.