Correct answer & explanation
✓Starting Up a Project: To ensure that the pre-requisites for initiating a project are in place.
In this matching question, only two pairs are correctly matched: A and B are accurate process-purpose pairings. Options C, D, and E contain incorrect pairings. The correct purpose for Initiating a Project is to establish solid foundations, not to monitor and control work. Controlling a Stage is for monitoring and controlling work of the stage, not authorizing work packages. Managing Product Delivery is for authorizing work packages and accepting completed products, not establishing foundations.
About these practice questions
Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
How Courseiva writes practice questions · Editorial policy
Same concept, more angles
1 more way this is tested on PRINCE2F
These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.
Variation 1. Match each PRINCE2 process to its purpose.
medium- ✓ A.Starting Up a Project: To ensure that the prerequisites for initiating a project are in place.
- B.Starting Up a Project: To establish a solid foundation for the project, enabling the project board to decide on committing to the project.
- ✓ C.Initiating a Project: To establish a solid foundation for the project, enabling the project board to decide on committing to the project.
- D.Initiating a Project: To ensure that the prerequisites for initiating a project are in place.
Why A: The correct matches are: Starting Up a Project ensures prerequisites are in place; Initiating a Project establishes the project's foundation. Common confusion: mixing up these two processes.