PRINCE2F PRINCE2 Practices Practice Question
During the Managing Product Delivery process, the Team Manager identifies a problem with the quality criteria for a work package. What should the Team Manager do?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Raise an issue to the Project Manager
The Team Manager should raise an issue to the Project Manager, who then decides on the appropriate action (e.g., Request for Change or Off-specification).
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Raise an issue to the Project Manager
Why this is correct
Correct: the Team Manager communicates issues to the Project Manager.
- ✗
Escalate directly to the Project Board
Why it's wrong here
Escalation is through the Project Manager.
- ✗
Reject the work package and stop work
Why it's wrong here
The Team Manager should not unilaterally stop work; they should report the issue.
- ✗
Revise the quality criteria and continue
Why it's wrong here
Quality criteria are part of the baseline; changes require approval.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
Same concept, more angles
1 more way this is tested on PRINCE2F
These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.
Variation 1. During the Managing Product Delivery process, a Team Manager identifies a defect in a product that is currently being developed. The defect means the product will not meet its agreed quality criteria. What should the Team Manager do?
medium- A.Stop work on the product and wait for instructions
- ✓ B.Raise an Issue to the Project Manager
- C.Correct the defect immediately and report it in the next Checkpoint Report
- D.Record the defect in the Quality Register only
Why B: The correct action is to raise an Issue. In PRINCE2, any problem, including a defect, is logged as an Issue. The Project Manager then decides if it is an Off-specification, Request for Change, or Problem/Concern.
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.