PRINCE2 Foundation (PRINCE2F) — Questions 826900

1731 questions total · 24pages · All types, answers revealed

Page 11

Page 12 of 24

Page 13
826
MCQhard

An issue is raised stating that a product has been delivered but does not meet its agreed specification. What type of issue is this?

A.Request for Change
B.Risk
C.Problem/Concern
D.Off-specification
AnswerD

This describes a product not meeting its specification.

Why this answer

An Off-specification is an issue where a product should be provided but is not (or is forecast not to be) according to its specification. This includes a product delivered that does not meet its specification.

827
Multi-Selecthard

Which THREE of the following are responsibilities of the Project Manager?

Select 3 answers
A.Managing day-to-day project activities within tolerances
B.Preparing the Stage Plans
C.Maintaining the Business Case
D.Providing independent assurance to the Project Board
E.Escalating forecast tolerance deviations to the Project Board
AnswersA, B, E

The PM manages the project on a day-to-day basis.

Why this answer

Option A is correct because the Project Manager is responsible for the day-to-day management of the project within the tolerances set by the Project Board. This includes monitoring progress, managing the team, and ensuring that work packages are delivered on time and within budget. The Project Manager must operate within these tolerances and only escalate to the Project Board when forecasts deviate beyond them.

Exam trap

The trap here is confusing the Project Manager's operational responsibilities with the strategic or assurance roles of the Project Board and Project Assurance, leading candidates to incorrectly select 'Maintaining the Business Case' or 'Providing independent assurance'.

828
MCQeasy

What does the 'management by exception' principle in PRINCE2 mean?

A.The Project Board sets tolerances and only reviews the project if tolerances are forecast to be exceeded
B.The Project Manager must report all decisions to the Project Board immediately
C.The Project Board makes all decisions for the project
D.The Project Manager can ignore plans and work independently
AnswerA

This is the core of management by exception.

Why this answer

Option C is correct. Management by exception means that the Project Board sets tolerances and only gets involved if those tolerances are forecast to be exceeded. This empowers the Project Manager to manage within the tolerances without constant board oversight.

829
Multi-Selecthard

Which THREE of the following are activities performed during the Controlling a Stage process?

Select 3 answers
A.Review progress against the Stage Plan
B.Produce the Project Plan
C.Produce the End Stage Report
D.Authorize Work Packages
E.Manage issues and risks
AnswersA, D, E

Monitoring progress is a key activity in Controlling a Stage.

Why this answer

Authorizing Work Packages, reviewing progress, and managing risks and issues are key activities of Controlling a Stage. Producing the End Stage Report is done in Managing a Stage Boundary, and producing the Project Plan is done in Initiating a Project.

830
Multi-Selectmedium

Which TWO of the following are PRINCE2 principles?

Select 2 answers
A.Risk management
B.Configuration management
C.Continued business justification
D.Waterfall methodology
E.Manage by stages
AnswersC, E

This is a PRINCE2 principle.

Why this answer

Continued business justification is a core PRINCE2 principle that requires the business case to remain viable throughout the project lifecycle. This principle ensures that the project is not started without a clear justification and that this justification is reviewed and updated at key decision points, such as stage boundaries. It directly supports the PRINCE2 focus on ongoing viability rather than a one-time approval.

Exam trap

PeopleCert often tests the distinction between principles and themes, so the trap here is confusing a theme (like risk management or configuration management) with a principle, leading candidates to select options that are valid PRINCE2 components but not principles.

831
MCQmedium

A Project Manager receives a Checkpoint Report from a Team Manager. Which process is the Team Manager executing when producing this report?

A.Controlling a Stage
B.Managing a Stage Boundary
C.Directing a Project
D.Managing Product Delivery
AnswerD

The Team Manager produces Checkpoint Reports during Managing Product Delivery to report progress on Work Packages.

Why this answer

Checkpoint Reports are produced by Team Managers during the Managing Product Delivery process. They report progress on Work Package delivery. Controlling a Stage is the PM's process for managing the stage; Highlight Reports go from PM to Project Board.

Managing a Stage Boundary and Directing a Project do not involve Checkpoint Reports.

832
MCQmedium

A project is in the Initiating a Project process. Which role is responsible for preparing the Project Initiation Documentation (PID)?

A.Team Manager
B.Senior Responsible Owner
C.Project Manager
D.Project Assurance
AnswerC

The PM prepares the PID.

Why this answer

In PRINCE2, the Project Manager is responsible for preparing the Project Initiation Documentation (PID) during the Initiating a Project process. The PID is a key management product that defines the project's scope, objectives, and controls, and the Project Manager must compile it based on input from the project board and other stakeholders.

Exam trap

The trap here is that candidates often confuse the Project Manager's role in preparing the PID with the Project Board's role in approving it, or mistakenly assign the task to the Senior Responsible Owner due to the SRO's authority over the business case.

How to eliminate wrong answers

Option A is wrong because the Team Manager is responsible for delivering the work packages within a stage, not for creating the PID. Option B is wrong because the Senior Responsible Owner (SRO) is the executive role that owns the business case and provides overall direction, but does not prepare the PID. Option D is wrong because Project Assurance provides independent oversight and checks the PID for compliance, but does not prepare it.

833
MCQhard

During the Controlling a Stage process, a Team Manager reports that a work package is complete. What is the next step for the Project Manager?

A.Inform the Project Board immediately
B.Close the project
C.Accept the completed work package and update the stage plan
D.Start planning the next stage immediately
AnswerC

The Project Manager accepts the completed products and updates the stage plan to reflect progress.

Why this answer

Option C is correct because, according to PRINCE2, when a Team Manager reports a work package as complete, the Project Manager must first accept the completed work package and then update the stage plan to reflect the actual progress. This ensures the stage plan remains accurate and provides a basis for assessing the impact on the project plan and any necessary corrective actions.

Exam trap

The trap here is that candidates often confuse the completion of a single work package with the end of a stage, leading them to incorrectly select options related to stage boundaries or project closure.

How to eliminate wrong answers

Option A is wrong because the Project Manager does not inform the Project Board immediately upon completion of a work package; the Board is only informed at stage boundaries or via exception reports. Option B is wrong because closing the project is a separate process (Closing a Project) that occurs only after all stages are complete and the project is formally closed. Option D is wrong because planning the next stage is part of the Managing a Stage Boundary process, which occurs at the end of a stage, not upon completion of a single work package within the current stage.

834
MCQhard

During the Initiating a Project process, which document is produced that defines how the project will be executed, monitored, and controlled?

A.Benefits Management Approach
B.Stage Plan
C.Project Brief
D.Project Initiation Documentation (PID)
AnswerD

The PID is produced during Initiating a Project.

Why this answer

The Project Initiation Documentation (PID) is the definitive document produced during the Initiating a Project process. It consolidates the project's scope, objectives, approach, and controls, serving as the baseline against which project execution, monitoring, and control are measured throughout the PRINCE2 project lifecycle.

Exam trap

The trap here is confusing the Project Brief (a pre-initiation outline) with the Project Initiation Documentation (the comprehensive, baselined plan produced during initiation), leading candidates to select Option C instead of D.

How to eliminate wrong answers

Option A is wrong because the Benefits Management Approach defines how the project's benefits will be measured and realized, not how the project itself is executed, monitored, and controlled. Option B is wrong because a Stage Plan is a detailed plan for a specific management stage, produced during the Managing a Stage Boundary process, not the overarching document for the entire project. Option C is wrong because the Project Brief is produced during the Starting up a Project process and provides the initial outline of the project; it is refined and expanded into the PID during Initiating a Project.

835
MCQhard

A Project Manager is reviewing progress during a stage and discovers that a Work Package is behind schedule. The Team Manager has not submitted a Checkpoint Report this week. What should the Project Manager do?

A.Close the Work Package and reassign the work to another team
B.Contact the Team Manager to understand the delay and agree corrective actions
C.Escalate the issue to the Project Board immediately via an Exception Report
D.Update the Project Plan to reflect the delay and inform the Project Board in the next Highlight Report
AnswerB

The PM should first assess the situation with the Team Manager and decide if corrective action within tolerance is possible.

Why this answer

The Project Manager should contact the Team Manager to understand the situation and take corrective action. This is part of the 'Review Work Package Status' activity in Controlling a Stage.

836
MCQmedium

A project is in the Initiating a Project process. Which of the following is produced during this process?

A.Benefits Management Approach
B.Project Brief
C.End Stage Report
D.Exception Report
AnswerA

This is created during IP as part of the PID.

Why this answer

The Benefits Management Approach is produced during the Initiating a Project process because it defines how the project's benefits will be measured, managed, and realized. This document is created as part of the detailed planning and governance setup that occurs in this process, ensuring alignment with the business case.

Exam trap

The trap here is that candidates confuse the Project Brief (produced in Starting Up a Project) with outputs of Initiating a Project, but PRINCE2 explicitly separates these processes to ensure the Project Brief is refined into the PID during initiation.

How to eliminate wrong answers

Option B is wrong because the Project Brief is created in the Starting Up a Project process, not in Initiating a Project; it provides the initial outline of the project's scope and justification. Option C is wrong because the End Stage Report is produced at the end of each management stage during the Managing a Stage Boundary process, not during initiation. Option D is wrong because the Exception Report is created during the Controlling a Stage process when a stage is forecast to exceed tolerances, not during initiation.

837
MCQmedium

Which of the following is a characteristic of a project that distinguishes it from business-as-usual?

A.Permanent team structure
B.Temporary organization
C.Ongoing operations
D.Repetitive processes
AnswerB

Correct.

Why this answer

Projects are temporary endeavors with a defined start and end, producing a unique product, service, or result.

838
MCQmedium

The Project Manager receives a Highlight Report from the Project Board. Is this correct?

A.No, the Project Manager sends Highlight Reports to the Project Board
B.Yes, the Project Board uses Highlight Reports to direct the Project Manager
C.No, Highlight Reports are only used during the Initiating a Project process
D.Yes, the Project Board sends Highlight Reports to the Project Manager
AnswerA

Correct: The PM sends Highlight Reports to the Board.

Why this answer

In PRINCE2, the Highlight Report is a management product that is prepared by the Project Manager and sent to the Project Board. The purpose of the Highlight Report is to provide the Project Board with a summary of the project's progress at intervals defined in the Communication Management Strategy. Therefore, the statement that the Project Manager receives a Highlight Report from the Project Board is incorrect; the flow is from the Project Manager to the Project Board.

Exam trap

The trap here is that candidates may confuse the direction of communication, assuming the Project Board sends reports to the Project Manager, when in fact the Highlight Report is a bottom-up reporting mechanism from the Project Manager to the Project Board.

How to eliminate wrong answers

Option B is wrong because the Project Board does not use Highlight Reports to direct the Project Manager; direction is provided via other management products such as the Project Mandate or Project Brief, and the Highlight Report is an upward reporting mechanism. Option C is wrong because Highlight Reports are not limited to the Initiating a Project process; they are produced during the Managing a Stage Boundary and Controlling a Stage processes as part of ongoing stage management. Option D is wrong because the Project Board does not send Highlight Reports to the Project Manager; the Project Manager creates and sends them to the Project Board.

839
MCQmedium

Which document describes the quality expectations and acceptance criteria for a project's products?

A.Product Description
B.Quality Management Approach
C.Project Product Description
D.Quality Register
AnswerB

This document sets out the quality procedures, standards, and acceptance criteria for the project.

Why this answer

The Quality Management Approach defines how quality will be managed, including quality criteria and acceptance methods.

840
MCQmedium

Which PRINCE2 principle is being applied when a project uses management by exception?

A.Continued business justification
B.Manage by exception
C.Manage by stages
D.Focus on products
AnswerB

Correct principle.

Why this answer

Management by exception is a key principle where tolerances are set and escalation occurs only when tolerances are forecast to be exceeded.

841
Multi-Selectmedium

Which TWO of the following reports are produced by the Project Manager during the Controlling a Stage process?

Select 2 answers
A.Lessons Report
B.Highlight Report
C.End Stage Report
D.Exception Report
E.Checkpoint Report
AnswersB, D

The Project Manager produces Highlight Reports during Controlling a Stage.

Why this answer

During Controlling a Stage, the Project Manager produces Highlight Reports and Exception Reports. Checkpoint Reports are produced by Team Managers during Managing Product Delivery. The End Stage Report is from Managing a Stage Boundary.

The Lessons Report is from Closing a Project.

842
MCQhard

Which statement correctly describes the relationship between Project Assurance and quality review?

A.They are the same thing
B.Quality review is a part of Project Assurance
C.Project Assurance is a role; quality review is a technique
D.Project Assurance performs quality reviews
AnswerC

Correct distinction.

Why this answer

Project Assurance is a role within the PRINCE2 framework, responsible for ensuring that the project remains viable and compliant with its business case, while quality review is a technique used to assess the quality of products. The correct relationship is that Project Assurance is a role, and quality review is a technique, making option C correct. They are distinct concepts: one is a governance role, the other is a specific method for evaluating deliverables.

Exam trap

The trap here is that candidates often confuse the governance role of Project Assurance with the execution of quality activities, leading them to incorrectly select option D, when in fact Project Assurance oversees quality but does not perform the quality review technique itself.

How to eliminate wrong answers

Option A is wrong because Project Assurance and quality review are not the same thing; Project Assurance is a role focused on objective oversight, while quality review is a technique for product evaluation. Option B is wrong because quality review is not a part of Project Assurance; rather, Project Assurance may use quality reviews as one of many techniques to fulfill its responsibilities, but quality review is a separate technique defined in the PRINCE2 quality theme. Option D is wrong because Project Assurance does not perform quality reviews; quality reviews are conducted by a review team including the producer, reviewers, and a chair, while Project Assurance provides independent oversight and may attend but does not execute the review itself.

843
MCQmedium

Which document is the key output of the Initiating a Project process?

A.Business Case
B.Project Plan
C.Project Brief
D.Project Initiation Documentation
AnswerD

The PID is the comprehensive document that consolidates all information required to start the project.

Why this answer

The Project Initiation Documentation (PID) is the key output of the Initiating a Project process. It defines the project's scope, objectives, and approach.

844
Multi-Selectmedium

Which TWO of the following are types of issue in PRINCE2?

Select 2 answers
A.Exception Plan
B.Off-specification
C.Risk
D.Lessons Report
E.Request for Change
AnswersB, E

A product that does not meet its specification.

Why this answer

The three predefined issue types are Request for Change, Off-specification, and Problem/Concern. Risk is a different management product.

845
MCQhard

In the Risk management procedure, what is the difference between a Risk Owner and a Risk Actionee?

A.Risk Owner monitors the risk; Risk Actionee updates the Risk Register
B.Risk Owner is accountable for the risk; Risk Actionee is accountable for the response budget
C.Risk Owner manages the risk; Risk Actionee implements the response actions
D.Risk Owner identifies the risk; Risk Actionee evaluates it
AnswerC

This is the correct distinction.

Why this answer

The Risk Owner is responsible for managing the risk overall; the Risk Actionee is assigned to implement specific response actions.

846
MCQeasy

What is the purpose of the Starting Up a Project (SU) process?

A.To produce the Project Initiation Documentation (PID)
B.To ensure that there is a viable and worthwhile project before detailed planning begins
C.To authorize the initiation of the project
D.To produce the Benefits Management Approach
AnswerB

SU confirms the project is viable and worthwhile before committing to detailed initiation.

Why this answer

The Starting Up a Project (SU) process is designed to ensure that the project has a viable business justification and is worthwhile before committing significant resources. It answers the question 'Do we have a viable and worthwhile project?' by creating the Project Brief and selecting the Project Manager, not by producing detailed plans or the PID.

Exam trap

PeopleCert often tests the distinction between 'Starting Up a Project' and 'Initiating a Project' — candidates confuse the SU process (which produces the Project Brief) with the IP process (which produces the PID and detailed plans).

How to eliminate wrong answers

Option A is wrong because the Project Initiation Documentation (PID) is produced during the Initiating a Project (IP) process, not during Starting Up a Project (SU). Option C is wrong because authorizing the initiation of the project is the purpose of the Directing a Project (DP) process, specifically the 'Authorize Initiation' activity. Option D is wrong because the Benefits Management Approach is developed during the Initiating a Project (IP) process, not during SU.

847
MCQmedium

Why does PRINCE2 separate the Project Manager role from Project Assurance?

A.To reduce the workload of the Project Manager
B.To align with a functional organizational structure
C.To provide independent assurance to the Project Board
D.To allow the Project Manager to focus on team management
AnswerC

Independence is key to avoid bias.

Why this answer

Separation ensures independent oversight. Project Assurance provides an objective check on the project's health, free from the PM's day-to-day pressures.

848
MCQmedium

During which process is the Project Initiation Documentation (PID) created?

A.Directing a Project
B.Starting Up a Project
C.Initiating a Project
D.Managing a Stage Boundary
AnswerC

The PID is created during Initiating a Project.

Why this answer

The PID is the key output of Initiating a Project, which establishes solid foundations for the project.

849
MCQeasy

What is the purpose of the Managing a Stage Boundary process?

A.To provide the Project Board with information to approve the next stage
B.To authorize the start of the project
C.To control the day-to-day work of the project
D.To produce the Project Initiation Documentation
AnswerA

Correct. The process enables stage boundary review and approval.

Why this answer

The Managing a Stage Boundary process is designed to provide the Project Board with sufficient information to review the current stage's performance, approve the next Stage Plan, and decide whether to continue the project. It ensures that the project remains viable by assessing progress against the Business Case and updating plans accordingly.

Exam trap

PeopleCert often tests the distinction between processes that produce plans (Initiating a Project) versus processes that review and approve stage-level plans (Managing a Stage Boundary), leading candidates to confuse the production of the Project Initiation Documentation with stage boundary activities.

How to eliminate wrong answers

Option B is wrong because authorizing the start of the project is the purpose of the Starting Up a Project process, not Managing a Stage Boundary. Option C is wrong because controlling day-to-day work is the responsibility of the Managing Product Delivery process, which handles work package assignments and progress reporting. Option D is wrong because producing the Project Initiation Documentation is the output of the Initiating a Project process, which occurs before any stage boundaries are managed.

850
MCQmedium

A project is forecast to exceed its cost tolerance. What should the Project Manager do first?

A.Close the project immediately
B.Issue an Exception Report to the Project Board
C.Increase the budget to cover the extra cost
D.Continue with the current plan and report at the end of the stage
AnswerB

The Project Manager must escalate via an Exception Report when tolerances are forecast to be exceeded.

Why this answer

According to the management by exception principle, when a tolerance is forecast to be exceeded, the Project Manager must escalate to the Project Board via an Exception Report.

851
Multi-Selecthard

Which THREE activities are part of the Initiating a Project process?

Select 3 answers
A.Prepare the Project Plan
B.Prepare the Risk Management Approach
C.Authorize the initiation stage
D.Appoint the project board and project manager
E.Assemble the Project Initiation Documentation
AnswersA, B, E

The Project Plan is developed during initiation.

Why this answer

Option A is correct because preparing the Project Plan is a key activity in the Initiating a Project process, where the detailed plan for the project is developed based on the Project Brief and the chosen strategy. This plan covers time, cost, quality, and scope, and is a core component of the Project Initiation Documentation (PID).

Exam trap

The trap here is that candidates confuse the activities of Starting up a Project (like authorizing the initiation stage and appointing roles) with those of Initiating a Project, which focuses on detailed planning and documentation.

852
MCQmedium

The Project Board receives a Highlight Report indicating that the stage is on track. However, a Team Manager has identified a potential risk that could impact the next stage. What should the Project Manager do?

A.Wait until the next stage to address the risk
B.Update the Project Plan to include the risk
C.Update the Risk Register and manage the risk as part of the current stage
D.Raise an Exception Report to the Project Board
AnswerC

Correct. Risks should be recorded and managed as they are identified, even if impact is in the future.

Why this answer

Risks are managed by the Project Manager. The risk should be added to the Risk Register and monitored. The Highlight Report is for reporting current stage progress; the risk can be mentioned but the immediate action is to record it.

853
MCQhard

In product-based planning, what is the purpose of a Product Flow Diagram?

A.To show the hierarchical breakdown of products
B.To identify the resources needed for each product
C.To list the quality criteria for each product
D.To show the sequence and dependencies of product creation
AnswerD

The Product Flow Diagram maps the order and dependencies of product development.

Why this answer

A Product Flow Diagram shows the order in which products will be developed and the dependencies between them. It is a key input to the activity network.

854
MCQmedium

During the Initiation Stage, the project manager identifies that the selected team lacks experience with the chosen technology. What should the project manager do?

A.Replace the team members with experienced ones
B.Escalate to the Project Board for decision
C.Update the Project Plan to include training
D.Update the Risk Register and plan a response
AnswerD

The PM should first record the risk and then plan how to address it.

Why this answer

The lack of experience with the chosen technology is a risk to the project, not an immediate issue. During the Initiation Stage, the project manager should formally record this risk in the Risk Register and plan an appropriate response, such as training or mentoring, to manage the uncertainty. This aligns with PRINCE2's principle of managing by stages and the requirement to identify and respond to risks proactively.

Exam trap

The trap here is that candidates confuse a risk (uncertain future event) with an issue (current problem) and immediately jump to a corrective action like replacing team members or escalating, instead of following the formal risk management procedure of recording and planning a response first.

How to eliminate wrong answers

Option A is wrong because replacing team members is a corrective action that should only be taken after evaluating the risk response; it bypasses the formal risk management process and may not be feasible or cost-effective. Option B is wrong because the project manager has the authority to manage risks within the stage; escalation to the Project Board is only required if the risk exceeds delegated tolerances or requires a decision outside the project manager's authority. Option C is wrong because updating the Project Plan to include training is a potential risk response, but it must first be identified and assessed in the Risk Register before any plan changes are made.

855
MCQmedium

The Project Manager reports that a work package is in danger of exceeding its tolerance. What should the Project Manager do?

A.Update the Project Plan
B.Escalate to the Project Board via an Exception Report
C.Instruct the Team Manager to produce an Exception Report
D.Issue a Change Request
AnswerC
856
MCQmedium

Which of the following is an opportunity response in PRINCE2?

A.Exploit
B.Accept
C.Transfer
D.Avoid
AnswerA

Exploit is an opportunity response.

Why this answer

PRINCE2 defines five threat responses and five opportunity responses; 'Exploit' is a response to an opportunity to ensure it happens.

857
MCQmedium

Which process is used by the Project Manager to prepare the End Stage Report and the next Stage Plan?

A.Controlling a Stage
B.Managing a Stage Boundary
C.Directing a Project
D.Closing a Project
AnswerB

Correct: SB produces the End Stage Report and next Stage Plan.

Why this answer

The Managing a Stage Boundary process is where the Project Manager reviews the current stage, produces an End Stage Report, and creates the next Stage Plan (or Exception Plan) for the Project Board's approval.

858
Multi-Selectmedium

Which TWO of the following are threat response types in PRINCE2 risk management?

Select 2 answers
A.Exploit
B.Enhance
C.Share
D.Avoid
E.Reduce
AnswersD, E

Avoid is a threat response.

Why this answer

Avoid and Reduce are threat responses; Exploit and Enhance are opportunity responses.

859
MCQmedium

During which process are lessons for the project first recorded?

A.Initiating a Project
B.Managing a Stage Boundary
C.Starting Up a Project
D.Closing a Project
AnswerC

The Lessons Log is created in SU and populated with relevant lessons from previous projects.

Why this answer

In PRINCE2, the first formal recording of lessons occurs during the 'Starting Up a Project' process. This process includes the activity 'Capture Previous Lessons' (from the 'Learn from Experience' principle), where the project manager reviews lessons from similar previous projects and records them in the Lessons Log before the project is even initiated. This ensures that the project starts with the benefit of past experience.

Exam trap

The trap here is that candidates often confuse 'Initiating a Project' (where detailed planning and the PID are created) with the first recording of lessons, but PRINCE2 explicitly requires lessons to be captured before initiation begins, during the 'Starting Up a Project' process.

How to eliminate wrong answers

Option A is wrong because 'Initiating a Project' is where the Lessons Log is updated with lessons from the initiation stage itself, but the first recording of lessons happens earlier, in Starting Up a Project. Option B is wrong because 'Managing a Stage Boundary' is where lessons from the current stage are captured and reported, but this occurs after the project has already started and is not the first recording. Option D is wrong because 'Closing a Project' is where final lessons are formally documented and the Lessons Log is completed, but this is the last recording, not the first.

860
MCQmedium

What is the purpose of the Managing a Stage Boundary process?

A.To manage the day-to-day activities of the team
B.To plan the next stage in detail and obtain Project Board approval
C.To close the project and produce the End Project Report
D.To initiate the project and create the PID
AnswerB

This is the core purpose of SB: to plan the next stage and seek approval.

Why this answer

Managing a Stage Boundary (SB) is designed to provide the Project Board with information to review the current stage's performance, approve the next stage plan, and update the Business Case and project plan.

861
MCQmedium

Who is responsible for producing the Checkpoint Report?

A.Project Support
B.Team Manager
C.Project Manager
D.Senior User
AnswerB

Correct: The Team Manager produces the Checkpoint Report.

Why this answer

The Team Manager produces the Checkpoint Report for the Project Manager to report progress of a Work Package.

862
MCQhard

In PRINCE2, why is the Project Assurance role separated from the Project Manager?

A.To reduce the workload of the Project Manager.
B.To ensure that the Project Board has independent and objective advice.
C.To align with the PRINCE2 principle of continued business justification.
D.To allow the Project Manager to focus on delivery while Assurance handles quality.
AnswerB

Independence ensures that Project Assurance can objectively monitor the project.

Why this answer

Project Assurance provides independent oversight to ensure that the project is managed correctly. If the Project Manager also performed assurance, it would compromise objectivity and independence.

863
MCQhard

In the Starting Up a Project process, the project manager is appointed. Who appoints the project manager?

A.The project board
B.The senior user
C.The executive
D.The senior supplier
AnswerC

Correct. The Executive appoints the Project Manager.

Why this answer

According to PRINCE2, the Executive appoints the project manager during SU. The Executive is the key decision-maker for this appointment.

864
Multi-Selecthard

Which TWO statements correctly describe the difference between the risk owner and the risk actionee?

Select 2 answers
A.There can be multiple risk actionees for a single risk; there is only one risk owner
B.The risk owner is always a member of the Project Board; the risk actionee is always a team member
C.The risk owner is responsible for updating the risk register; the risk actionee is not
D.The risk actionee is responsible for identifying new risks; the risk owner is responsible for implementing responses
E.The risk owner is accountable for the risk; the risk actionee carries out actions
AnswersA, E

This is correct.

Why this answer

The risk owner is responsible for managing the risk, while the risk actionee performs specific actions.

865
MCQhard

What is the difference between a Request for Change (RFC) and an Off-specification (Off-spec)?

A.An Off-spec becomes an RFC after approval
B.An RFC is a change to a baselined product; an Off-spec is a product not meeting its specification
C.An RFC is raised by the Project Manager; an Off-spec is raised by the Executive
D.There is no difference; they are the same
AnswerB

Correct distinction.

Why this answer

An RFC is a proposal for a change to a product that has been baselined, while an Off-spec is a description of a product that does not meet its specification.

866
Multi-Selecthard

Which TWO of the following are characteristic differences between a project and Business As Usual (BAU)?

Select 3 answers
A.A project involves stakeholders, whereas BAU does not.
B.A project is temporary with a defined start and end, whereas BAU is ongoing.
C.A project has a unique output, whereas BAU produces the same output repeatedly.
D.A project delivers a unique output, whereas BAU has no defined end date.
E.A project involves cross-functional teams, whereas BAU does not.
AnswersB, C, D

A project is temporary; BAU is ongoing.

Why this answer

Options B and D are correct. A project is temporary with a unique output, while BAU is ongoing and repetitive. Option A is wrong because both projects and BAU can involve cross-functional teams.

Option C is wrong because BAU does not have a defined end date. Option E is wrong because both involve stakeholders.

867
MCQhard

What is the difference between a Request for Change (RFC) and an Off-specification (Off-spec)?

A.An RFC is a threat; an Off-spec is an opportunity
B.An RFC requires a change budget; an Off-spec does not
C.An RFC proposes a change to a baselined product; an Off-spec is a product that does not meet its specification
D.An RFC is raised by the Project Manager; an Off-spec is raised by the Project Board
AnswerC

This is the key distinction.

Why this answer

An RFC proposes a modification to a product that has been approved or baselined; an Off-spec is something that should be provided but is not (or will not be) as specified.

868
MCQmedium

In the Organising practice, what is the single point of accountability for the project's business justification?

A.The Project Manager
B.The Executive (Senior Responsible Owner)
C.The Senior User
D.The Project Board
AnswerB

The Executive is accountable for the Business Case and business justification.

Why this answer

The Executive (Senior Responsible Owner) is the single point of accountability for the business justification in PRINCE2.

869
Multi-Selectmedium

Which TWO outputs are produced during the Initiating a Project process?

Select 2 answers
A.Project Initiation Documentation (PID)
B.Benefits Management Approach
C.Project Brief
D.Work Package
E.End Stage Report
AnswersA, B

PID is the key output of Initiating a Project.

Why this answer

The PID and Benefits Management Approach are both produced in IP. The Project Brief is from SU, and the End Stage Report is from SB.

870
MCQhard

What is the difference between a Request for Change and an Off-specification?

A.There is no difference; the terms are interchangeable
B.A Request for Change is raised by the Project Board; an Off-specification is raised by the Project Manager
C.A Request for Change seeks to change a product without a baseline; an Off-specification relates to a baselined product
D.An Off-specification is a failure to meet a specification; a Request for Change is a proposal to change a specification
AnswerD

Off-specification indicates non-conformance; Request for Change proposes a deliberate change.

Why this answer

An Off-specification is something that should be provided but is not (or is wrong). A Request for Change is a proposed modification to a baselined product.

871
Multi-Selectmedium

Which TWO of the following are responsibilities of the Project Board?

Select 2 answers
A.Providing overall direction and control of the project
B.Managing day-to-day activities of the project
C.Approving the Project Plan and any stage plans
D.Maintaining the Business Case
E.Producing Team Plans
AnswersA, C

The Project Board is accountable for the project's success and provides direction and control.

Why this answer

Options B and D are correct. The Project Board is responsible for approving plans and resources (B) and providing direction and control (D). Maintaining the Business Case is the PM's job; producing Team Plans is the Team Manager's; managing day-to-day activities is the PM's.

872
MCQmedium

Which of the following is NOT a component of the Business Case?

A.Expected benefits
B.Major risks
C.Product description
D.Investment appraisal
AnswerC

A product description is part of quality and plans, not the Business Case.

Why this answer

The Business Case components include reasons, options, expected benefits, dis-benefits, timescale, costs, investment appraisal, and major risks. A product description is part of product-based planning, not the Business Case.

873
MCQmedium

The project board asks the project manager to produce a detailed plan for the next stage. Which plan should be produced?

A.Exception Plan
B.Stage Plan
C.Team Plan
D.Project Plan
AnswerB

A Stage Plan is required for each management stage.

Why this answer

In PRINCE2, the Project Board requests a detailed plan for the next stage, which is the Stage Plan. The Stage Plan is produced at the end of the current stage (or during Initiation for the first stage) and provides the detailed management and technical steps for the upcoming stage, aligning with the 'Managing a Stage Boundary' process. This plan is essential for the Project Board to approve the continuation of the project into the next stage.

Exam trap

PeopleCert often tests the distinction between the Project Plan (high-level, whole project) and the Stage Plan (detailed, next stage), trapping candidates who confuse the scope and purpose of these two plans.

How to eliminate wrong answers

Option A is wrong because an Exception Plan is produced only when a stage is forecast to exceed its tolerances, not as a routine request for the next stage. Option C is wrong because a Team Plan is created by a team manager for a specific work package, not by the project manager for the entire stage. Option D is wrong because the Project Plan is the high-level, overall plan covering the entire project lifecycle, not a detailed plan for a specific stage.

874
MCQeasy

What is the key output of the Starting Up a Project process?

A.End Project Report
B.Benefits Management Approach
C.Project Brief
D.Project Initiation Documentation
AnswerC

SU produces the Project Brief.

Why this answer

The Starting Up a Project process is the first process in PRINCE2, executed before project initiation. Its key output is the Project Brief, which provides a high-level overview of the project's justification, scope, and approach, enabling the project board to decide whether to proceed to the Initiation Stage. The Project Brief is derived from the project mandate and is used to create the Project Initiation Documentation later.

Exam trap

The trap here is that candidates often confuse the Project Brief with the Project Initiation Documentation, mistakenly thinking the latter is the first key output, but PRINCE2 explicitly separates these two documents across different processes.

How to eliminate wrong answers

Option A is wrong because the End Project Report is an output of the Closing a Project process, not Starting Up a Project. Option B is wrong because the Benefits Management Approach is developed during the Initiating a Project process, not Starting Up a Project. Option D is wrong because the Project Initiation Documentation is the key output of the Initiating a Project process, which occurs after Starting Up a Project has been completed and the project board has authorized initiation.

875
MCQeasy

Who is responsible for maintaining the Business Case throughout the project?

A.Senior User
B.Project Manager
C.Project Board
D.Senior Supplier
AnswerB

The Project Manager maintains the Business Case on behalf of the Executive.

Why this answer

The Executive (SRO) owns the Business Case and is responsible for maintaining its viability. The Project Manager maintains it on a day-to-day basis.

876
MCQmedium

During the Controlling a Stage process, the Project Manager identifies that the project is forecast to exceed the agreed cost tolerance for the current stage. What should the Project Manager do?

A.Increase the project budget to absorb the additional cost and continue with the current Stage Plan
B.Close the project immediately as the Business Case is no longer viable
C.Continue with the current Stage Plan and report the cost overrun in the next Highlight Report
D.Raise an Exception Report to the Project Board and await their direction before proceeding
AnswerD

When a stage tolerance is forecast to be exceeded, the Project Manager must escalate to the Project Board immediately via an Exception Report. This is management by exception.

Why this answer

Option C is correct. When a tolerance is forecast to be exceeded, the Project Manager must escalate to the Project Board via an Exception Report — this is PRINCE2's management by exception principle. The Project Manager cannot unilaterally decide to exceed tolerances; that requires Project Board authorisation.

Option A is wrong because the PM cannot increase the budget without Project Board approval. Option B is wrong because continuing without escalation violates management by exception. Option D is wrong because closing the project is not the appropriate response to a stage tolerance breach.

877
MCQeasy

Which of the following is NOT a component of the Business Case?

A.Investment appraisal
B.Risk Register
C.Major risks
D.Expected benefits
AnswerB

The Risk Register is a separate management product.

Why this answer

The Business Case includes reasons, options, benefits, dis-benefits, timescale, costs, investment appraisal, and major risks. The Risk Register is separate.

878
Multi-Selecteasy

Which TWO of the following are outputs of the Starting Up a Project process?

Select 2 answers
A.Initiation Stage Plan
B.Project Brief
C.Benefits Management Approach
D.Project Initiation Documentation (PID)
E.End Stage Report
AnswersA, B

Correct. The plan for the initiation stage is produced in SU.

Why this answer

The Project Brief and the Initiation Stage Plan are outputs of SU. The PID is output of IP. The End Stage Report is output of SB.

879
MCQeasy

What is the purpose of the Highlight Report?

A.To detail the work packages for the next stage
B.To provide the Project Board with a summary of stage progress
C.To report issues to the Project Board
D.To report team progress to the Project Manager
AnswerB

This is the main purpose of the Highlight Report.

Why this answer

The Highlight Report is produced by the Project Manager and sent to the Project Board at regular intervals to provide a summary of progress during a stage.

880
MCQmedium

A stakeholder is concerned that the project is not delivering value for money. Which role should this concern be raised with?

A.Senior User
B.Project Assurance
C.Executive
D.Project Manager
AnswerC

Correct.

Why this answer

The Executive is ultimately accountable for the project's business justification, including ensuring value for money. Concerns about cost versus benefits must be escalated to the Executive, who owns the Business Case and has the authority to approve changes or stop the project if value is not being delivered.

Exam trap

The trap here is confusing the Project Manager's responsibility for day-to-day cost control with the Executive's accountability for overall value for money and the Business Case.

How to eliminate wrong answers

Option A is wrong because the Senior User represents the users' needs and specifies the expected benefits, but is not accountable for overall value for money or the business case. Option B is wrong because Project Assurance provides independent oversight and checks compliance, but does not have the authority to make decisions on value for money; it reports issues to the Executive. Option D is wrong because the Project Manager manages day-to-day activities and escalates issues, but is not accountable for the business justification or value for money decisions.

881
MCQeasy

Which PRINCE2 principle requires that a project continues to be desirable, viable, and achievable?

A.Manage by stages
B.Tailor to suit the project environment
C.Continued business justification
D.Learn from experience
AnswerC

Correct. This principle requires that the project remains desirable, viable, and achievable, documented in the Business Case.

Why this answer

The continued business justification principle ensures that the project remains justified throughout its life. The Business Case is the key document that captures this justification.

882
Multi-Selectmedium

Which TWO of the following are components of the Business Case?

Select 2 answers
A.Investment appraisal
B.Configuration Item Records
C.Product Description
D.Risk Register
E.Expected benefits
AnswersA, E

Investment appraisal is a key component, showing the justification for the project.

Why this answer

The Business Case includes expected benefits, dis-benefits, costs, timescale, risks, and investment appraisal. Options B and E are correct; A, C, and D are not standard components.

883
MCQmedium

Which document is the key output of the Initiating a Project process?

A.Project Brief
B.Project Plan
C.Business Case
D.Project Initiation Documentation (PID)
AnswerD

The PID is the formal document that defines the project and is created during Initiating a Project.

Why this answer

The Project Initiation Documentation (PID) is the key output of the Initiating a Project process. It provides a baseline for the project and is used by the Project Board to decide whether to proceed.

884
MCQhard

A Work Package is being executed. The Team Manager discovers a product cannot meet its quality criteria due to an unforeseen technical limitation. What should the Team Manager do?

A.Directly inform the Project Board
B.Raise an issue to the Project Manager
C.Proceed with the work and accept the lower quality
D.Update the Work Package and continue
AnswerB

The Team Manager should report the issue so that the Project Manager can decide on appropriate action.

Why this answer

The Team Manager should raise an issue (or off-specification) to the Project Manager via the MP process. The Project Manager will then decide on corrective action or escalation.

885
Multi-Selectmedium

Which THREE of the following are components of the Business Case?

Select 3 answers
A.Major risks
B.Expected benefits
C.Project approach
D.Investment appraisal
E.Benefits review plan
AnswersA, B, D

Major risks are included.

Why this answer

The Business Case includes reasons, options, expected benefits, dis-benefits, timescale, costs, investment appraisal, and major risks. Benefits review plan is part of the project plan, not the Business Case.

886
MCQhard

What is the difference between a Request for Change and an Off-specification?

A.A Request for Change relates to a change in scope; an Off-specification relates to a change in quality
B.There is no difference; they are synonyms
C.A Request for Change is raised by the Project Manager; an Off-specification is raised by the Team Manager
D.A Request for Change is a proposed change to a baselined product; an Off-specification is a product that does not meet its specification
AnswerD

This correctly describes the difference.

Why this answer

Option D is correct because in PRINCE2, a Request for Change (RFC) is a formal proposal to modify a baselined product, while an Off-specification (Off-spec) is a notification that a product does not meet its agreed specification. The key distinction is that an RFC addresses a change to a product that has already been approved, whereas an Off-spec identifies a failure to meet the original requirements. This aligns with PRINCE2's change control approach, where both are captured in the Issue Register but serve different purposes.

Exam trap

The trap here is that candidates confuse the terms by associating RFCs with scope changes and Off-specs with quality defects, when in fact both can relate to any aspect of a product's specification, and the true difference lies in whether the product is baselined (RFC) or non-conforming (Off-spec).

How to eliminate wrong answers

Option A is wrong because it incorrectly associates RFCs solely with scope changes and Off-specs solely with quality changes; in PRINCE2, RFCs can affect any baselined aspect (scope, quality, time, cost) and Off-specs are about non-conformance to any specification, not just quality. Option B is wrong because RFCs and Off-specs are distinct concepts with different triggers and actions; they are not synonyms. Option C is wrong because both RFCs and Off-specs can be raised by any project stakeholder, not exclusively by the Project Manager or Team Manager; the PRINCE2 guidance states that anyone can raise an issue, which is then logged and assessed.

887
MCQeasy

According to PRINCE2, who is responsible for maintaining the Business Case throughout the project?

A.Project Manager
B.Senior Supplier
C.Senior User
D.Project Board
AnswerA

Correct. The Project Manager maintains the Business Case.

Why this answer

In PRINCE2, the Project Manager is responsible for maintaining the Business Case throughout the project. This includes monitoring the project's viability against the Business Case, updating it with actual costs and benefits, and escalating any deviations to the Project Board. The Project Manager ensures the Business Case remains a living document that reflects the current justification for the project.

Exam trap

The trap here is that candidates often assume the Project Board, as the ultimate decision-making body, is responsible for maintaining the Business Case, but PRINCE2 explicitly assigns this maintenance role to the Project Manager.

How to eliminate wrong answers

Option B is wrong because the Senior Supplier is responsible for providing the necessary resources and expertise, not for maintaining the Business Case. Option C is wrong because the Senior User represents the users' interests and specifies the benefits, but does not maintain the Business Case document. Option D is wrong because the Project Board is responsible for approving the Business Case and making key decisions, but the day-to-day maintenance and monitoring of the Business Case is delegated to the Project Manager.

888
MCQmedium

Which document is produced by the Team Manager to report progress on a Work Package?

A.Checkpoint Report
B.Exception Report
C.Highlight Report
D.End Stage Report
AnswerA

Correct. The Team Manager produces Checkpoint Reports for the Project Manager.

Why this answer

The Checkpoint Report is produced by the Team Manager and sent to the Project Manager to report progress on a Work Package.

889
Multi-Selectmedium

Which TWO of the following are produced during the Starting Up a Project process?

Select 2 answers
A.Initiation Stage Plan
B.Benefits Management Approach
C.End Project Report
D.Project Brief
E.Project Initiation Documentation
AnswersA, D

Correct: The plan for the initiation stage is created in SU.

Why this answer

SU produces the Project Brief and the Initiation Stage Plan. The PID and End Project Report are produced later.

890
MCQmedium

A project is forecast to exceed its stage cost tolerance. What should the Project Manager do?

A.Report the overrun in the next Highlight Report
B.Raise an Exception Report to the Project Board
C.Close the project as the Business Case is no longer viable
D.Increase the stage budget and continue
AnswerB

Correct action: escalate immediately via Exception Report.

Why this answer

In PRINCE2, when a project manager forecasts that a stage will exceed its cost tolerance, they must escalate the issue to the Project Board by raising an Exception Report. This is because tolerances are delegated limits, and exceeding them requires board-level decision-making, not just reporting or self-authorization. The Exception Report triggers an Exception Plan to recover or adjust the project.

Exam trap

PeopleCert often tests the distinction between reporting (Highlight Report) and escalation (Exception Report), trapping candidates who think a simple status update suffices when tolerances are breached.

How to eliminate wrong answers

Option A is wrong because a Highlight Report is a periodic status update, not an escalation mechanism for tolerance breaches; the Project Manager must raise an Exception Report immediately, not wait for the next Highlight Report. Option C is wrong because exceeding stage cost tolerance does not automatically invalidate the Business Case; the Project Board must assess viability and decide on corrective action, not unilaterally close the project. Option D is wrong because the Project Manager cannot increase the stage budget without authorization; tolerances are set by the Project Board, and only they can approve budget changes through an Exception Plan.

891
MCQeasy

Which document is the key output of the Initiating a Project process?

A.End Stage Report
B.Exception Report
C.Project Brief
D.Project Initiation Documentation (PID)
AnswerD

The PID is the key document produced during IP.

Why this answer

The Initiating a Project process is where the project's baselines are established, and its key output is the Project Initiation Documentation (PID). The PID consolidates all essential information—such as the Business Case, project plan, risk register, and project controls—into a single, approved document that defines what the project will deliver and how it will be managed. This document is the foundation for decision-making and is used throughout the project.

Exam trap

PeopleCert often tests the distinction between the Project Brief (an input from Starting Up a Project) and the Project Initiation Documentation (the key output of Initiating a Project), so candidates mistakenly select the Project Brief thinking it is the main deliverable of the initiation phase.

How to eliminate wrong answers

Option A is wrong because the End Stage Report is produced at the end of each management stage (including the final stage) to report on progress against the plan, not as an output of Initiating a Project. Option B is wrong because the Exception Report is created when a project is forecast to exceed its tolerances, triggering an exception management process, and is not a deliverable of the initiation phase. Option C is wrong because the Project Brief is actually an input to the Initiating a Project process (created during Starting Up a Project), not its key output; the PID refines and replaces the Project Brief.

892
MCQeasy

In PRINCE2, who is responsible for maintaining the Business Case throughout the project?

A.Senior Responsible Owner (Executive)
B.Project Manager
C.Senior Supplier
D.Project Assurance
AnswerA

The SRO is accountable for the Business Case throughout the project.

Why this answer

In PRINCE2, the Executive (also known as the Senior Responsible Owner) is accountable for the Business Case and must ensure it remains viable throughout the project. The Business Case is the key document that justifies the project's initiation and continued existence, and only the Executive has the authority to approve changes to it or decide to close the project if the Business Case is no longer viable.

Exam trap

The trap here is confusing the Project Manager's responsibility for 'managing' the Business Case (updating it, tracking benefits) with the Executive's accountability for 'maintaining' it (owning it, approving changes, deciding to continue or stop).

How to eliminate wrong answers

Option B is wrong because the Project Manager is responsible for creating, updating, and managing the Business Case on a day-to-day basis, but they do not own it; they cannot approve changes or decide to stop the project based on it. Option C is wrong because the Senior Supplier is responsible for providing the project's products and ensuring supplier interests are met, but they do not own the Business Case. Option D is wrong because Project Assurance is an independent monitoring function that checks the Business Case is being managed correctly, but they are not responsible for maintaining it.

893
MCQmedium

During a project, a team manager reports that a work package is taking longer than expected. The project manager needs to assess the impact on the project schedule. Which practice should be used to evaluate the effect and determine whether to escalate?

A.Risk
B.Plans
C.Organizing
D.Progress
AnswerD

Progress practice covers monitoring, control, and escalations.

Why this answer

The Progress practice is used to monitor and compare actual achievements against planned performance, and to assess the impact of deviations. When a work package takes longer than expected, the project manager uses Progress to evaluate the effect on the schedule and decide whether to escalate to the project board. This aligns with PRINCE2's principle of managing by stages and using tolerances to control deviations.

Exam trap

PeopleCert often tests the distinction between 'Risk' (managing future uncertainties) and 'Progress' (monitoring actual performance against baselines), leading candidates to incorrectly select Risk when a delay is already occurring.

How to eliminate wrong answers

Option A is wrong because Risk practice focuses on identifying, assessing, and controlling uncertainties that could affect the project, not on evaluating schedule impact from a known delay. Option B is wrong because Plans practice is about defining how, when, and by whom the products are delivered, not about monitoring actual progress or assessing deviations. Option C is wrong because Organizing practice defines roles and responsibilities, not the mechanism for evaluating schedule impact or escalation decisions.

894
MCQmedium

Who is responsible for producing the Highlight Report?

A.Project Assurance
B.Team Manager
C.Project Manager
D.Project Board
AnswerC

The PM produces Highlight Reports for the Board.

Why this answer

The Project Manager produces Highlight Reports and sends them to the Project Board during Controlling a Stage.

895
MCQhard

In PRINCE2, which role is responsible for providing an independent view of the project's progress and adherence to standards?

A.Project Support
B.Project Assurance
C.Project Manager
D.Senior User
AnswerB

Correct. Project Assurance is independent of the Project Manager.

Why this answer

Project Assurance provides an independent check on the project's progress and compliance, reporting to the Project Board.

896
Multi-Selecthard

Which THREE of the following are components of the Project Initiation Documentation (PID)?

Select 3 answers
A.Project Plan
B.Business Case
C.Lessons Log
D.Stage Plan
E.Risk Register
AnswersA, B, E

The Project Plan is included in the PID.

Why this answer

Option A is correct because the Project Plan is a core component of the Project Initiation Documentation (PID) in PRINCE2. The PID is the foundation document that defines the project's scope, objectives, and approach, and the Project Plan details the schedule, resources, and costs for the entire project, providing the baseline for progress control.

Exam trap

PeopleCert often tests the distinction between documents that are part of the PID versus those that are created or maintained separately, such as the Lessons Log and Stage Plans, which are often confused as being part of the PID due to their importance in project management.

897
MCQmedium

A project is in the Initiating a Project process. Which management product defines how the project will be controlled?

A.Business Case
B.Project Plan
C.Project Initiation Documentation
D.Stage Plan
AnswerC

Why this answer

The PID contains all the approaches (risk, quality, change, communication) and the Project Plan, defining how the project will be controlled. The Project Plan is a component of the PID, but PID is the overall management product. Stage Plan is more detailed for a stage.

Business Case justifies viability.

898
MCQmedium

During the Controlling a Stage process, the Project Manager identifies that the project is forecast to exceed the agreed cost tolerance for the current stage. What should the Project Manager do?

A.Close the project immediately as the Business Case is no longer viable
B.Continue with the current Stage Plan and report the cost overrun in the next Highlight Report
C.Raise an Exception Report to the Project Board and await their direction before proceeding
D.Increase the project budget to absorb the additional cost and continue with the current Stage Plan
AnswerC

When a stage tolerance is forecast to be exceeded, the Project Manager must escalate to the Project Board immediately via an Exception Report. This is management by exception.

Why this answer

Option C is correct. When a tolerance is forecast to be exceeded, the Project Manager must escalate to the Project Board via an Exception Report — this is PRINCE2's management by exception principle. The Project Manager cannot unilaterally decide to exceed tolerances; that requires Project Board authorisation.

Option A is wrong because the PM cannot increase the budget without Project Board approval. Option B is wrong because continuing without escalation violates management by exception. Option D is wrong because closing the project is not the appropriate response to a stage tolerance breach.

899
MCQeasy

What is the key output of the Initiating a Project process?

A.Project Plan
B.Project Brief
C.Project Initiation Documentation
D.Business Case
AnswerC

The PID is the main output of IP.

Why this answer

The key output of IP is the Project Initiation Documentation (PID). Option A is correct. The Project Brief is an input from SU.

The Business Case is part of PID. The Project Plan is part of PID.

900
MCQeasy

What is the purpose of the Highlight Report?

A.To escalate exceptions
B.To report progress to the Project Board at regular intervals
C.To request changes
D.To report progress to the Team Manager
AnswerB

Correct.

Why this answer

The Highlight Report is produced by the Project Manager for the Project Board at regular intervals to summarize progress and issues.

Page 11

Page 12 of 24

Page 13