Courseiva

PRINCE2 Foundation (PRINCE2F) — Questions 826900

1599 questions total · 22pages · All types, answers revealed

Page 11

Page 12 of 22

Page 13
826
MCQmedium

During the Controlling a Stage process, the Project Manager identifies that the project is forecast to exceed the agreed cost tolerance for the current stage. What should the Project Manager do?

A.Close the project immediately as the Business Case is no longer viable
B.Continue with the current Stage Plan and report the cost overrun in the next Highlight Report
C.Raise an Exception Report to the Project Board and await their direction before proceeding
D.Increase the project budget to absorb the additional cost and continue with the current Stage Plan
AnswerC

Correct. When a tolerance is forecast to be exceeded, the Project Manager must raise an Exception Report to the Project Board and await direction.

Why this answer

When a tolerance is forecast to be exceeded, the Project Manager must escalate to the Project Board via an Exception Report — this is PRINCE2's management by exception principle. The Project Manager cannot unilaterally decide to exceed tolerances; that requires Project Board authorisation. Option A is wrong because closing the project immediately is not the appropriate first response.

Option B is wrong because continuing without escalation violates management by exception. Option D is wrong because the Project Manager cannot increase the budget without Project Board approval.

827
MCQeasy

What is the key output of the Initiating a Project process?

A.Project Plan
B.Project Brief
C.Project Initiation Documentation
D.Business Case
AnswerC

The Project Initiation Documentation (PID) is the definitive output of the Initiating a Project process because it formally consolidates the project’s business case, scope, risks, and controls into a single baseline. This satisfies the stem’s constraint for a “key output” by providing the authorisation and reference point required to proceed into the Delivery Stage, distinguishing it from earlier process outputs like the Project Brief.

Why this answer

The key output of the Initiating a Project process is the Project Initiation Documentation (PID). Option C is correct. Option A, Project Plan, is developed as part of the PID but is not the overall output.

Option B, Project Brief, is an input from the Starting Up a Project process. Option D, Business Case, is a component of the PID, not the complete output.

828
MCQeasy

What is the purpose of the Highlight Report?

A.To escalate exceptions
B.To report progress to the Project Board at regular intervals
C.To request changes
D.To report progress to the Team Manager
AnswerB

Correct.

Why this answer

The Highlight Report is produced by the Project Manager for the Project Board at regular intervals to summarize progress and issues.

829
MCQmedium

Which document is the key output of the Initiating a Project process?

A.The Project Initiation Documentation
B.The Business Case
C.The Risk Register
D.The Project Plan
AnswerA

The PID is the key output of Initiating a Project.

Why this answer

The Initiating a Project process is where the project's foundations are established, and its key output is the Project Initiation Documentation (PID). The PID consolidates all essential information—including the Business Case, Project Plan, and Risk Register—into a single, coherent document that defines what the project will deliver, why, how, and against what constraints. It serves as the baseline for decision-making and is formally approved before the project proceeds to the next stage.

Exam trap

PeopleCert often tests the distinction between the PID as the overarching output and its individual components (like the Business Case or Project Plan) to see if candidates understand that the PID is the consolidated deliverable, not any single part of it.

How to eliminate wrong answers

Option B is wrong because the Business Case is a component of the Project Initiation Documentation, not the key output of the Initiating a Project process; it is developed and refined during the Starting Up a Project process and updated in Initiating a Project. Option C is wrong because the Risk Register is a management product that is created and maintained throughout the project, but it is not the primary output of Initiating a Project; it is one of many components that feed into the PID. Option D is wrong because the Project Plan is also a component of the PID, not the key output itself; it is produced during the Initiating a Project process but is only one part of the comprehensive PID.

830
MCQmedium

What is the purpose of the Managing a Stage Boundary process?

A.To close the project
B.To manage the delivery of work packages
C.To enable the Project Board to review the current stage and approve the next Stage Plan
D.To plan the entire project in detail
AnswerC

This is the primary purpose of the Managing a Stage Boundary process.

Why this answer

The purpose of the Managing a Stage Boundary process is to enable the Project Board to review the current stage, approve the next Stage Plan, and confirm continued business justification. Option C correctly describes this.

831
MCQeasy

Which process covers the day-to-day management of a stage by the Project Manager?

A.Managing a Stage Boundary
B.Directing a Project
C.Managing Product Delivery
D.Controlling a Stage
AnswerD

Why this answer

The Controlling a Stage (CS) process covers the day-to-day management activities of the Project Manager within a stage.

832
MCQmedium

During the Controlling a Stage process, the Project Manager identifies that the project is forecast to exceed the agreed cost tolerance for the current stage. What should the Project Manager do?

A.Continue with the current Stage Plan and report the cost overrun in the next Highlight Report
B.Close the project immediately as the Business Case is no longer viable
C.Raise an Exception Report to the Project Board and await their direction before proceeding
D.Increase the project budget to absorb the additional cost and continue with the current Stage Plan
AnswerC

When a stage tolerance is forecast to be exceeded, the PM must escalate via an Exception Report. This is management by exception.

Why this answer

According to the management by exception principle, when a stage tolerance is forecast to be exceeded, the Project Manager must escalate to the Project Board via an Exception Report. The Project Manager cannot unilaterally increase the budget or ignore the breach.

833
MCQeasy

Which role is responsible for maintaining the Business Case throughout the project?

A.Senior Responsible Owner (Executive)
B.Project Assurance
C.Project Manager
D.Senior User
AnswerA

The SRO/Executive is accountable for the Business Case.

Why this answer

The Senior Responsible Owner (SRO/Executive) owns the Business Case and is accountable for ensuring it remains viable. The Project Manager maintains the Business Case on behalf of the Executive.

834
MCQeasy

Which PRINCE2 principle ensures that the Project Board delegates decision-making to the Project Manager within defined tolerances?

A.Learn from Experience
B.Continued Business Justification
C.Management by Exception
D.Manage by Stages
AnswerC

This principle defines tolerance-based delegation.

Why this answer

Management by Exception means the PM is empowered within tolerances, and only escalates when tolerances are forecast to be exceeded.

835
MCQhard

In PRINCE2, what is the difference between a Request for Change (RFC) and an Off-specification?

A.There is no difference; they are synonyms in PRINCE2
B.An Off-specification is always raised by the Project Manager; an RFC is raised by the Project Board
C.An RFC only applies to project products; an Off-specification applies to the Business Case
D.An RFC is a proposal to change a baseline; an Off-specification is a failure to meet a baseline requirement
AnswerD

Correct. RFC proposes a change; Off-specification is a deviation from what was specified.

Why this answer

A Request for Change (RFC) is a formal proposal to modify a baseline (e.g., a product, plan, or scope), while an Off-specification is a documented deviation where a product or component fails to meet its agreed specification or baseline requirement. In PRINCE2, an RFC seeks approval for a change, whereas an Off-specification identifies a non-compliance that must be resolved, often through a change request or concession.

Exam trap

The trap here is that candidates confuse the purpose of an RFC (proactive change proposal) with an Off-specification (reactive non-compliance detection), leading them to incorrectly treat them as synonyms or misattribute who raises them.

How to eliminate wrong answers

Option A is wrong because RFC and Off-specification are distinct concepts in PRINCE2; an RFC proposes a change to a baseline, while an Off-specification identifies a failure to meet a baseline requirement. Option B is wrong because both RFCs and Off-specifications can be raised by any project role (e.g., team members, Project Manager, or Project Board), not exclusively by the Project Manager or Project Board. Option C is wrong because an RFC can apply to any baseline (including the Business Case, plans, or products), and an Off-specification applies to any product or component that fails to meet its specification, not just the Business Case.

836
MCQmedium

A project is in the Initiating a Project process. Which document is the key output of this process?

A.End Stage Report
B.Lessons Report
C.Project Brief
D.Project Initiation Documentation
AnswerD

The PID is the definitive document produced during Initiating a Project.

Why this answer

The Project Initiation Documentation (PID) is the key output of Initiating a Project. It brings together all the information needed to justify the project and define its scope.

837
Drag & Dropmedium

Drag and drop the steps of the PRINCE2 Starting up a Project process into the correct order.

Drag steps to the numbered slots on the right, or tap a step then tap a slot.

Steps
Order
1Step 1
2Step 2
3Step 3
4Step 4

Why this order

The Starting up a Project process ensures that the prerequisites for initiating a project are in place, starting with appointing key roles, then learning from past projects, building the team, developing the outline business case, and finally selecting the approach.

838
MCQmedium

The Project Board is reviewing the End Stage Report and the next Stage Plan. Which process are they performing?

A.Closing a Project
B.Managing a Stage Boundary
C.Controlling a Stage
D.Directing a Project
AnswerD

DP includes the activity of authorizing a stage plan.

Why this answer

The Project Board reviews stage-end reports and decides whether to authorize the next stage. This is part of Directing a Project (DP). The PM produces the End Stage Report and next Stage Plan during Managing a Stage Boundary (SB).

839
MCQmedium

During the Controlling a Stage process, the Project Manager needs to assign work to a team. What should the Project Manager create?

A.Work Package
B.Team Plan
C.Project Plan
D.Product Description
AnswerA

A Work Package is the set of instructions for the team to produce one or more products.

Why this answer

The Project Manager authorizes work by issuing a Work Package to the Team Manager.

840
MCQeasy

Which role is responsible for ensuring that project assurance is carried out independently of the Project Manager?

A.Project Manager
B.Project Board
C.Team Manager
D.Project Support
AnswerB

Correct. The Project Board is accountable for project assurance and ensures it is independent.

Why this answer

The Project Board members (Executive, Senior User, Senior Supplier) are responsible for project assurance. They delegate assurance tasks but remain accountable. The Project Manager does not perform assurance; that would compromise independence.

841
MCQhard

Why does PRINCE2 recommend separating the role of Project Manager from Project Assurance?

A.To comply with regulatory requirements
B.To reduce the workload of the Project Manager
C.To provide an independent perspective on the project's status
D.To allow the Project Manager to focus on quality reviews
AnswerC

Independence is key to effective assurance.

Why this answer

Separating Project Manager from Project Assurance ensures objectivity and independence of assurance activities. The Project Manager is responsible for day-to-day management and cannot objectively assess their own work.

842
MCQmedium

A project is experiencing many changes due to evolving requirements. Which document should the Project Manager use to track all requests for change?

A.Risk Register
B.Configuration Item Record
C.Issue Register
D.Quality Register
AnswerC

All issues, including requests for change, are logged in the Issue Register.

Why this answer

The Issue Register is the PRINCE2 document specifically designed to capture, track, and manage all requests for change, including off-specifications, problems, and concerns. Since the project is experiencing many changes due to evolving requirements, the Project Manager must log each change request in the Issue Register to ensure proper impact analysis, decision-making, and audit trail. This aligns with the PRINCE2 practice of managing issues and changes through a controlled process.

Exam trap

The trap here is that candidates often confuse the Issue Register with the Risk Register, mistakenly thinking that a change request is a risk to be mitigated, rather than a formal issue that must be logged and managed through the change control procedure.

How to eliminate wrong answers

Option A is wrong because the Risk Register is used to record identified risks (threats and opportunities), not requests for change; changes are handled through the issue management process. Option B is wrong because a Configuration Item Record tracks the status and version of a specific product or component, not the lifecycle of a change request. Option D is wrong because the Quality Register logs quality activities such as inspections and audits, not change requests.

843
MCQhard

A team member reports that a product does not meet its specification. How should the Project Manager record this?

A.As a Risk
B.As a Request for Change
C.As a Lesson
D.As an Off-specification
AnswerD

Correct.

Why this answer

In PRINCE2, an Off-specification is the correct record when a product fails to meet its agreed specification or quality criteria. The Project Manager logs this in the Issue Register as a type of issue, not a risk, change, or lesson, because the product already exists and does not conform to its defined requirements.

Exam trap

Candidates often mistake an Off-specification for a Request for Change. An Off-specification is recorded when an existing product fails to meet its agreed specification, whereas a Request for Change proposes a modification to the specification. This question tests the correct classification of issues in PRINCE2.

How to eliminate wrong answers

Option A is wrong because a Risk is an uncertain event that could affect the project, not a confirmed failure of an existing product against its specification. Option B is wrong because a Request for Change is a proposal to modify a product's specification or baseline, not a record of a product that already fails to meet its current specification. Option C is wrong because a Lesson is a learning point captured for future benefit, not a record of a specific product non-conformance.

844
MCQhard

What is the difference between a Request for Change and an Off-specification?

A.There is no difference; they are the same
B.Off-specification is raised by the Project Board; Request for Change by users
C.A Request for Change is always budgeted; Off-specification is not
D.A Request for Change proposes a modification; Off-specification identifies something that is missing or not working
AnswerD

Correct distinction per PRINCE2.

Why this answer

A Request for Change is a proposal for a modification, while an Off-specification is something that should have been provided but is missing or not working.

845
MCQmedium

Who is responsible for maintaining the Business Case throughout the project?

A.The Executive
B.The Project Manager
C.The Project Support
D.The Senior User
AnswerB

The Project Manager is responsible for maintaining the Business Case on a day-to-day basis.

Why this answer

The Senior User is responsible for specifying the benefits and ensuring they are realized, but the Executive owns the Business Case. The Project Manager maintains it on a day-to-day basis.

846
MCQmedium

What is the purpose of the Highlight Report?

A.To report stage progress to the Project Board
B.To report the end of a stage
C.To report team progress to the Project Manager
D.To report a forecast deviation
AnswerA

The Highlight Report goes to the Project Board.

Why this answer

The Highlight Report is provided by the Project Manager to the Project Board at the end of each reporting period to summarize progress.

847
MCQeasy

Which of the following is a characteristic of a project according to PRINCE2?

A.Repetitive activities
B.Ongoing operations
C.Temporary organization
D.Functional management
AnswerC
848
MCQhard

A project is forecast to exceed its cost tolerance. What should the Project Manager do?

A.Continue and report in the next Highlight Report
B.Increase the project budget and continue
C.Close the project immediately
D.Raise an Exception Report to the Project Board
AnswerD

An Exception Report is raised to the Project Board to decide on corrective action.

Why this answer

Management by exception requires escalation via an Exception Report to the Project Board when a tolerance is forecast to be exceeded.

849
MCQeasy

Who is responsible for authorising the initiation of a project?

A.Project Board
B.Executive
C.Corporate management
D.Project Manager
AnswerA

The Project Board authorises initiation via DP.

Why this answer

In PRINCE2, the Project Board is collectively responsible for authorizing the initiation of a project. This decision is made during the 'Directing a Project' process, where the Project Board reviews the Project Brief and decides whether to proceed to the Initiation Stage. The Project Board's authority is derived from the corporate or programme management, but the actual authorization to initiate is a board-level responsibility.

Exam trap

The trap here is that candidates often confuse the Executive's role as the single decision-maker with the collective responsibility of the Project Board, leading them to select 'Executive' instead of 'Project Board'.

How to eliminate wrong answers

Option B is wrong because the Executive is a single role on the Project Board, not the sole authority for authorizing initiation; the Project Board as a whole must agree. Option C is wrong because corporate or programme management provides the mandate and high-level direction but does not directly authorize initiation—they delegate this to the Project Board. Option D is wrong because the Project Manager manages the project on a day-to-day basis and does not have the authority to authorize initiation; they prepare the initiation documentation for the Project Board's approval.

850
Multi-Selecthard

Which THREE of the following are responsibilities of the Project Manager during the Controlling a Stage process?

Select 3 answers
A.Authorize Work Packages
B.Review the progress of work packages
C.Produce the Project Plan
D.Produce the Stage Plan for the next stage
E.Manage issues and risks
AnswersA, B, E

The PM authorizes work packages in CS.

Why this answer

The PM authorizes Work Packages, monitors progress, and manages issues and risks. Producing the next stage plan is done in SB, and producing the Project Plan is done in IP.

851
Multi-Selectmedium

Which TWO roles are part of the Project Board?

Select 2 answers
A.Senior User
B.Team Manager
C.Project Manager
D.Project Support
E.Executive (SRO)
AnswersA, E

The Senior User is a board role.

Why this answer

The Project Board consists of three roles: the Executive (Senior Responsible Owner), Senior User(s), and Senior Supplier(s). In this question, the two roles from the Project Board that are listed are Senior User (Option A) and Executive (Option E). Team Manager, Project Manager, and Project Support are not Project Board roles.

852
Multi-Selectmedium

Which TWO of the following statements about the Directing a Project process are correct?

Select 2 answers
A.It is performed by the Project Board
B.It includes producing Highlight Reports
C.It includes the day-to-day management of the project
D.It includes authorizing the initiation of the project
E.It is performed only at the start and end of the project
AnswersA, D

DP is the Project Board's process.

Why this answer

DP is performed by the Project Board and runs throughout the project. The Project Board gives direction and authorizes key decisions but does not manage day-to-day. The PM manages day-to-day in CS.

853
Multi-Selecthard

Which TWO are true about Stage Plans in PRINCE2?

Select 2 answers
A.They are approved by the Project Board
B.They cover the entire project timeline
C.They are produced at the start of each stage
D.They replace the Project Plan
E.They are less detailed than the Project Plan
AnswersA, C

The Board approves each Stage Plan.

Why this answer

Stage Plans in PRINCE2 are formally approved by the Project Board at the end of the current stage (or at the start of the next stage) as part of the 'Manage a Stage Boundary' process. The Project Board uses the Stage Plan to authorize the work for the upcoming stage, ensuring it aligns with the Business Case and tolerances.

Exam trap

The trap here is confusing the level of detail between Stage Plans and the Project Plan; candidates often assume Stage Plans are less detailed because they cover a shorter time period, but PRINCE2 requires them to be more detailed to enable day-to-day management.

854
MCQhard

In PRINCE2, which role is responsible for providing independent assurance that the project is being managed correctly?

A.Project Assurance
B.Team Manager
C.Project Support
D.Project Manager
AnswerA

Project Assurance is independent and checks compliance.

Why this answer

Project Assurance is an independent role, separate from Project Support.

855
MCQmedium

A project is in the Initiating a Project process. The project manager is reviewing the Business Case and notes that the expected benefits are not clearly linked to the project's objectives. Which practice should the project manager use to address this issue?

A.Quality practice
B.Risk practice
C.Business Case practice
D.Plans practice
AnswerC

The Business Case practice ensures the project remains viable and benefits are defined and linked to objectives.

Why this answer

The Business Case practice is responsible for establishing and maintaining the justification for the project, including the link between objectives and expected benefits. During the Initiating a Project process, the Business Case must be refined to ensure that all benefits are clearly traceable to the project's objectives, as this alignment is critical for ongoing viability decisions. The project manager should use the Business Case practice to address this gap by updating the Business Case to explicitly map each benefit to a specific project objective.

Exam trap

PeopleCert often tests the distinction between the Business Case practice (which owns the justification and benefit-objective linkage) and the Plans practice (which owns the schedule and activities), leading candidates to incorrectly choose Plans when the issue is about benefit alignment rather than sequencing.

How to eliminate wrong answers

Option A is wrong because the Quality practice focuses on defining and verifying the quality criteria of products, not on linking benefits to objectives. Option B is wrong because the Risk practice deals with identifying, assessing, and controlling uncertainties that could affect the project, not with ensuring benefit-objective alignment. Option D is wrong because the Plans practice is concerned with defining the sequence of activities, resources, and schedules to deliver the project's products, not with the justification or benefit mapping in the Business Case.

856
Multi-Selectmedium

Which TWO of the following are outputs of the Starting Up a Project process?

Select 2 answers
A.Project Initiation Documentation
B.End Stage Report
C.Project Brief
D.Benefits Management Approach
E.Initiation Stage Plan
AnswersC, E

The Project Brief is formally created during the Starting Up a Project process to provide a firm foundation for the initiation stage. It consolidates the outline business case, project product description, and project approach, satisfying the constraint that the project board must have sufficient information to authorise initiation. Without this output, the board cannot evaluate whether the project is viable before committing resources.

Why this answer

The Starting Up a Project process is the pre-project phase where the project is evaluated for viability before full initiation. Its key outputs include the Project Brief, which outlines the project's scope, objectives, and approach, and the Initiation Stage Plan, which details the work needed to produce the Project Initiation Documentation. These two outputs are formally defined in PRINCE2 as products of this process.

Exam trap

A common trap in PRINCE2 exams is confusing the outputs of Starting Up a Project (pre-project) with those of Initiating a Project. Specifically, the Project Brief and Initiation Stage Plan are produced in Starting Up a Project, while the Project Initiation Documentation and Benefits Management Approach are created later during the Initiating a Project process.

857
MCQeasy

Who is responsible for maintaining the Business Case throughout the project?

A.The Senior User
B.The Project Assurance
C.The Project Manager
D.The Senior Supplier
AnswerC

The Project Manager maintains the Business Case on behalf of the Executive.

Why this answer

The Executive (Senior Responsible Owner) is the owner of the Business Case. The Project Manager maintains (updates) the Business Case on behalf of the Executive.

858
MCQmedium

What is the purpose of the Managing a Stage Boundary process?

A.To plan the next stage and update the Project Plan and Business Case
B.To produce the Project Initiation Documentation
C.To manage the work of the current stage
D.To close the project
AnswerA

Correct. Managing a Stage Boundary produces the next stage plan and updates the PID.

Why this answer

The Managing a Stage Boundary process is designed to provide the Project Board with sufficient information to review the current stage's performance, approve the next stage plan, and update the Project Plan and Business Case with any new information. This ensures that the project remains viable and aligned with business objectives before committing to the next stage.

Exam trap

The trap here is that candidates often confuse the Managing a Stage Boundary process with the Controlling a Stage process, because both involve stage-level activities, but Managing a Stage Boundary is specifically about planning the next stage and updating key documents, not managing current work.

How to eliminate wrong answers

Option B is wrong because producing the Project Initiation Documentation is the purpose of the Initiating a Project process, not the Managing a Stage Boundary process. Option C is wrong because managing the work of the current stage is the purpose of the Controlling a Stage process, which handles day-to-day work and issue management. Option D is wrong because closing the project is the purpose of the Closing a Project process, which ensures the project is formally completed and benefits are measured.

859
Multi-Selectmedium

Which TWO of the following are characteristics of the Project Assurance role?

Select 2 answers
A.It is responsible for producing Work Packages
B.It is often performed by the Project Manager
C.It reports to the Project Board
D.It is a subset of Project Support
E.It must be independent of the Project Manager
AnswersC, E

Assurance reports to the Board, not the PM.

Why this answer

The Project Assurance role is specifically tasked with monitoring and reporting on the project's adherence to PRINCE2 standards, and it reports directly to the Project Board to provide independent oversight. This ensures that the Project Board receives objective assessments of the project's progress and compliance, separate from the Project Manager's perspective.

Exam trap

PeopleCert often tests the misconception that Project Assurance is a subset of Project Support or can be performed by the Project Manager, but PRINCE2 strictly requires independence to maintain objective oversight.

860
MCQeasy

What is the purpose of the Managing a Stage Boundary process?

A.To initiate the project and create the Project Plan
B.To plan the next stage in detail and obtain Project Board approval for the next stage
C.To manage the work of the current stage and report progress
D.To close the project and produce the End Project Report
AnswerB

This is the primary purpose of Managing a Stage Boundary.

Why this answer

The purpose of Managing a Stage Boundary is to provide the Project Board with sufficient information to review the current stage, approve the next stage plan, and confirm continued business justification.

861
Multi-Selectmedium

Which TWO of the following are responsibilities of the Project Board?

Select 2 answers
A.Manage day-to-day activities
B.Authorize the Project Plan
C.Produce Checkpoint Reports
D.Authorize the start of each stage
E.Update the Daily Log
AnswersB, D

The board approves the Project Plan.

Why this answer

The Project Board is responsible for overall project governance, including authorizing the Project Plan (which defines the project's scope, cost, and schedule) and authorizing the start of each management stage. These decisions ensure the project remains aligned with business objectives and that stage boundaries are properly controlled.

Exam trap

PeopleCert often tests the distinction between strategic governance (Project Board) and operational management (Project Manager), so candidates mistakenly assign day-to-day tasks like updating logs or producing reports to the board.

862
MCQhard

During a stage, a Team Manager identifies a quality problem with a product. The product fails its quality inspection. What should the Team Manager do?

A.Proceed with delivery and inform the Project Manager in the next Checkpoint Report
B.Reject the Work Package and stop all work
C.Raise an Exception Report directly to the Project Board
D.Raise an Issue Report to the Project Manager
AnswerD

The Team Manager should raise an Issue Report (Off-specification) to the PM via the CS process.

Why this answer

According to PRINCE2, if a product fails its quality inspection, the Team Manager should raise an Issue Report (specifically, an Off-specification) to the Project Manager. The PM then decides how to handle it. Option D is correct; Option B is wrong because the Team Manager should not bypass the PM.

863
Multi-Selectmedium

Which TWO of the following are outputs of the Starting Up a Project process?

Select 2 answers
A.Project Initiation Documentation
B.Benefits Management Approach
C.Daily Log
D.End Stage Report
E.Project Brief
AnswersC, E

Yes, Daily Log is created in SU.

Why this answer

SU produces the Project Brief, Daily Log, and Initiation Stage Plan. PID is from IP.

864
MCQeasy

Which management product defines the quality criteria and acceptance methods for a product?

A.The Business Case
B.The Project Plan
C.The Quality Register
D.The Product Description
AnswerD

The Product Description defines quality criteria and acceptance methods.

Why this answer

The Product Description is the PRINCE2 management product that defines the quality criteria, quality methods, and acceptance methods for a specific product. It is created during the Initiating a Project process and is used to ensure that the product meets its required quality standards before it is approved.

Exam trap

The trap here is that candidates often confuse the Quality Register (which tracks quality activities) with the Product Description (which defines the quality criteria and methods), leading them to select Option C instead of D.

How to eliminate wrong answers

Option A is wrong because the Business Case provides justification for the project, including costs, benefits, and risks, but does not define quality criteria or acceptance methods for individual products. Option B is wrong because the Project Plan defines the schedule, resources, and costs for the project, not the quality criteria or acceptance methods for a specific product. Option C is wrong because the Quality Register is a log used to record and track all quality activities and results, but it does not define the quality criteria or acceptance methods themselves.

865
MCQeasy

How often should the Project Board meet during a PRINCE2 project?

A.Only at the end of the project
B.Monthly
C.Weekly
D.At the end of each stage and when exceptions occur
AnswerD

The Project Board meets at stage boundaries and when an exception is raised.

Why this answer

Project Board meetings are held at key decision points (end of stages) and when exceptions occur. They are not scheduled at regular intervals but are exception-driven.

866
MCQmedium

During which process is the Benefits Management Approach first produced?

A.Managing a Stage Boundary
B.Closing a Project
C.Initiating a Project
D.Starting Up a Project
AnswerC

IP produces all management approaches, including Benefits Management Approach.

Why this answer

The Benefits Management Approach is first produced during the Initiating a Project process, as it forms part of the Project Initiation Documentation (PID). Options A, B, and D are incorrect: Managing a Stage Boundary reviews and may update the approach, Closing a Project evaluates benefits, and Starting Up a Project does not create it.

867
MCQeasy

Which process is the Project Board's primary process for making key decisions?

A.Starting Up a Project
B.Managing a Stage Boundary
C.Directing a Project
D.Controlling a Stage
AnswerC

Correct: DP covers all key decision points for the Project Board.

Why this answer

Directing a Project (DP) is the process used by the Project Board to authorize initiation, stage plans, exception plans, and closure.

868
MCQmedium

During the Controlling a Stage process, the Project Manager receives a Highlight Report from a Team Manager. What should the Project Manager do with this information?

A.File the report and take no further action
B.Escalate any deviations immediately to the Project Board via an Exception Report
C.Review the report and use it to update the Stage Plan and produce the next Highlight Report for the Project Board
D.Forward the report directly to the Project Board as the next Highlight Report
AnswerC

Correct. The Project Manager uses Checkpoint Reports (and Highlight Reports from Team Managers) to monitor progress and report to the Board.

Why this answer

The Project Manager uses the Controlling a Stage process to monitor progress, review Highlight Reports, and report to the Project Board via Highlight Reports.

869
MCQmedium

Which role is responsible for ensuring that the project's products meet specified quality criteria?

A.Project Assurance
B.Senior User
C.Project Manager
D.Senior Supplier
AnswerB

The Senior User represents the users who will use the product and defines quality needs.

Why this answer

The Senior User is responsible for specifying the requirements and ensuring the final product meets the agreed quality criteria.

870
Matchingmedium

Match each PRINCE2 process to its purpose.

Drag a concept onto its matching description — or click a concept then click the description.

Concepts
Matches

To ensure that the prerequisites for initiating a project are in place.

To enable the project board to be accountable for the project's success.

To establish solid foundations for the project.

To assign work, monitor progress, and handle issues.

To control the link between the project manager and the team managers.

Why these pairings

The correct matches are: Starting Up a Project ensures prerequisites are in place; Initiating a Project establishes the project's foundation. Common confusion: mixing up these two processes.

871
MCQmedium

During the Closing a Project process, which document is produced to capture lessons for future projects?

A.Lessons Log
B.Lessons Report
C.Project Plan
D.End Project Report
AnswerB

The Lessons Report is created during CP.

Why this answer

The Lessons Report is produced during CP to document what went well and what could be improved, for the benefit of future projects.

872
MCQmedium

Who is responsible for authorising the initiation of a project?

A.Project Manager
B.Team Manager
C.Project Board
D.Senior User
AnswerC

Why this answer

The Project Board (in the Directing a Project process) is responsible for authorising project initiation, as well as authorising the project itself.

873
MCQmedium

Which document describes the quality criteria and quality methods to be applied during the project?

A.Quality Register
B.Product Description
C.Project Plan
D.Quality Management Approach
AnswerD

The Quality Management Approach defines the quality procedures, criteria, and methods for the project.

Why this answer

The Quality Management Approach defines the quality management system, including quality criteria and methods. The Product Description defines quality for a specific product. The Quality Register logs quality activities.

The Project Plan includes schedules.

874
MCQeasy

Which document is used to capture and track all identified risks throughout the project?

A.Quality Register
B.Risk Register
C.Configuration Item Record
D.Issue Register
AnswerB

The Risk Register captures and tracks all risks.

Why this answer

The Risk Register is the document used to record and track risks.

875
MCQeasy

Which risk response is appropriate for a threat that the project team decides to eliminate by changing the project approach?

A.Transfer
B.Accept
C.Reduce
D.Avoid
AnswerD

Avoid eliminates the threat by changing the plan.

Why this answer

Avoid is the response where action is taken to eliminate the threat by changing the plan or approach.

876
MCQmedium

What is the purpose of the Managing a Stage Boundary process?

A.To define the project scope and create the Project Initiation Documentation
B.To authorize the initiation of the project
C.To enable the Project Board to review the current stage's performance and approve the next Stage Plan
D.To control the day-to-day work of the project and manage issues
AnswerC

SB provides a control point between stages.

Why this answer

The Managing a Stage Boundary process is designed to provide the Project Board with the information needed to review the current stage's performance, approve the next Stage Plan, and update the Business Case and Project Plan. This ensures that the project remains viable and aligned with business objectives before committing further resources.

Exam trap

A common mistake in PRINCE2 is to confuse the Managing a Stage Boundary process (stage-end review and planning) with the Controlling a Stage process (day-to-day management), leading candidates to select an incorrect answer that describes day-to-day control.

How to eliminate wrong answers

Option A is wrong because defining the project scope and creating the Project Initiation Documentation is the purpose of the Initiating a Project process, not Managing a Stage Boundary. Option B is wrong because authorizing the initiation of the project is the purpose of the Directing a Project process, specifically the 'Authorize Initiation' activity. Option D is wrong because controlling the day-to-day work of the project and managing issues is the purpose of the Controlling a Stage process, which handles work packages and issue resolution within a stage.

877
Multi-Selectmedium

Which THREE of the following are roles on the PRINCE2 Project Board?

Select 3 answers
A.Project Manager
B.Senior Responsible Owner (Executive)
C.Senior User
D.Senior Supplier
E.Team Manager
AnswersB, C, D

Yes, this is the chair of the Project Board.

Why this answer

The Project Board consists of the Senior Responsible Owner (Executive), Senior User, and Senior Supplier.

878
MCQmedium

During which process are team plans typically created?

A.Managing a Stage Boundary
B.Initiating a Project
C.Directing a Project
D.Managing Product Delivery
AnswerD

Correct. Team plans are created by the team manager in MP.

Why this answer

Team plans are created by the team manager during the Managing Product Delivery process.

879
MCQmedium

During the Managing Product Delivery process, what does the Team Manager produce to inform the Project Manager of progress?

A.Exception Report
B.Checkpoint Report
C.End Stage Report
D.Highlight Report
AnswerB

Correct. Checkpoint Reports are produced by the Team Manager.

Why this answer

In PRINCE2, the Team Manager produces a Checkpoint Report during the Managing Product Delivery process to inform the Project Manager of progress at a regular, predefined frequency. This report provides a snapshot of actual progress against the Work Package plan, including achievements, next steps, and any issues or risks. It is the primary mechanism for the Team Manager to communicate status to the Project Manager within this process.

Exam trap

The trap here is that candidates often confuse the Checkpoint Report (produced by the Team Manager) with the Highlight Report (produced by the Project Manager), as both report progress but at different levels and to different audiences.

How to eliminate wrong answers

Option A is wrong because an Exception Report is produced by the Project Manager (not the Team Manager) to escalate a deviation that exceeds tolerance thresholds to the Project Board. Option C is wrong because an End Stage Report is produced by the Project Manager at the end of a management stage to summarize performance and is not part of the Managing Product Delivery process. Option D is wrong because a Highlight Report is produced by the Project Manager to inform the Project Board of progress between stage boundaries, not by the Team Manager during product delivery.

880
MCQmedium

What is the purpose of the Managing a Stage Boundary process?

A.To enable the Project Board to review the stage and approve the next
B.To control day-to-day activities within a stage
C.To plan the entire project in detail
D.To close the project
AnswerA

This is the correct purpose.

Why this answer

The Managing a Stage Boundary process is designed to provide the Project Board with sufficient information to review the current stage's performance, approve the next Stage Plan, and update the Business Case and Project Plan. It ensures that the project remains viable and aligned with business objectives before committing further resources.

Exam trap

The trap here is confusing the Managing a Stage Boundary process with the Controlling a Stage process, as both involve stage-level activities, but only Managing a Stage Boundary focuses on the transition between stages and obtaining approval for the next stage.

How to eliminate wrong answers

Option B is wrong because controlling day-to-day activities within a stage is the purpose of the Controlling a Stage process, not Managing a Stage Boundary. Option C is wrong because planning the entire project in detail is done during the Initiating a Project process, not at stage boundaries. Option D is wrong because closing the project is the purpose of the Closing a Project process, which occurs after the final stage is completed.

881
MCQeasy

Who is responsible for maintaining the Business Case throughout the project?

A.Project Assurance
B.Senior User
C.Project Manager
D.Executive (Senior Responsible Owner)
AnswerD
882
MCQmedium

A Team Manager sends a Checkpoint Report to the Project Manager. Which process is the Team Manager executing?

A.Managing Product Delivery
B.Managing a Stage Boundary
C.Controlling a Stage
D.Directing a Project
AnswerA

MP includes Checkpoint Reports.

Why this answer

The Team Manager is executing the 'Managing Product Delivery' process because this process controls the work of the team, including the creation and delivery of products. A key activity within this process is the production of Checkpoint Reports, which provide the Project Manager with progress updates on the work assigned to the team. The Checkpoint Report is a formal PRINCE2 management product that is specifically defined as an output of the 'Managing Product Delivery' process.

Exam trap

The trap here is that candidates often confuse the process that produces the Checkpoint Report (Managing Product Delivery) with the process that receives and uses it (Controlling a Stage), leading them to incorrectly select 'Controlling a Stage'.

How to eliminate wrong answers

Option B is wrong because 'Managing a Stage Boundary' is executed by the Project Manager, not the Team Manager, and its outputs include End Stage Reports and Exception Reports, not Checkpoint Reports. Option C is wrong because 'Controlling a Stage' is executed by the Project Manager to monitor and control the stage, and while it receives Checkpoint Reports, it does not produce them. Option D is wrong because 'Directing a Project' is executed by the Project Board, not the Team Manager, and its focus is on high-level decision-making and authorization, not on producing operational progress reports like Checkpoint Reports.

883
MCQhard

During the Closing a Project process, the Project Manager produces a Lessons Report. What should happen to this report?

A.It should be filed in the project records and not reviewed
B.It should be published to the organization's lessons database
C.It should be destroyed to maintain confidentiality
D.It should be passed to the Executive for personal use
AnswerB

Lessons are recorded and shared to improve future projects.

Why this answer

The Lessons Report is used to inform future projects and improve organizational project management. It should be shared with the relevant stakeholders and added to the organizational lessons database. It is not just filed or destroyed.

884
MCQmedium

What is the purpose of the Managing a Stage Boundary process?

A.To close the project
B.To enable the Project Board to review the current stage and authorize the next
C.To control the work of the current stage
D.To plan the entire project
AnswerB

Correct. The process provides the basis for stage boundary decisions.

Why this answer

The Managing a Stage Boundary process is designed to provide the Project Board with sufficient information to review the current stage's performance, approve its completion, and authorize the next stage plan. This ensures that the project remains viable and aligned with business justification before committing further resources.

Exam trap

The trap here is confusing the Managing a Stage Boundary process with the Controlling a Stage process, as both involve stage-level activities, but only Managing a Stage Boundary handles the formal end-of-stage review and authorization of the next stage.

How to eliminate wrong answers

Option A is wrong because closing the project is the purpose of the Closing a Project process, not Managing a Stage Boundary. Option C is wrong because controlling the work of the current stage is the purpose of the Controlling a Stage process, which handles day-to-day management and issue resolution. Option D is wrong because planning the entire project is done during the Initiating a Project process, which creates the Project Plan; Managing a Stage Boundary only produces Stage Plans for the next stage.

885
MCQmedium

In PRINCE2, what is the definition of quality?

A.Customer satisfaction
B.Fit for purpose
C.Conformance to specification
D.Zero defects
AnswerB

This is the correct PRINCE2 definition.

Why this answer

In PRINCE2, quality is defined as 'fit for purpose,' meaning the product meets the stated requirements and is suitable for its intended use. This definition aligns with the PRINCE2 principle of continued business justification, ensuring the product delivers value to the stakeholders. It is not merely about conformance to specification or zero defects, but about satisfying the user's needs in the operational environment.

Exam trap

The trap here is that candidates often confuse 'conformance to specification' (a traditional manufacturing view) with PRINCE2's broader 'fit for purpose' definition, which includes the requirement that the specification itself must be appropriate for the user's needs and the business case.

How to eliminate wrong answers

Option A is wrong because 'customer satisfaction' is a broader outcome of quality but not the PRINCE2 definition; PRINCE2 focuses on the product's fitness for its stated purpose, not just subjective satisfaction. Option C is wrong because 'conformance to specification' is a narrower, manufacturing-focused view that ignores whether the specification itself is correct for the user's needs; PRINCE2 emphasizes that the product must be suitable for its intended use, which may require adapting specifications. Option D is wrong because 'zero defects' is an idealistic goal from total quality management, not PRINCE2's definition; PRINCE2 accepts that some defects may be tolerable if the product remains fit for purpose, and it manages quality through tolerances and acceptance criteria.

886
MCQmedium

What is the main difference between the Starting Up a Project process and the Initiating a Project process?

A.SU is done by the Project Manager; IP is done by the Project Board
B.SU includes risk management; IP does not
C.SU creates the Project Brief; IP creates the Project Initiation Documentation
D.SU is optional; IP is mandatory
AnswerC

Correct. SU produces a high-level brief; IP produces detailed PID.

Why this answer

SU is a pre-project process to determine if the project is viable and worth initiating, while IP formally establishes the project foundation with detailed plans.

887
MCQeasy

Who is responsible for maintaining the Business Case throughout the project?

A.Senior User
B.Project Support
C.Project Manager
D.Executive (Senior Responsible Owner)
AnswerC

The Project Manager maintains the Business Case on behalf of the Executive.

Why this answer

According to PRINCE2, the Project Manager is responsible for maintaining the Business Case, while the Executive (Senior Responsible Owner) owns it and is accountable for its justification.

888
MCQhard

During a project, the cost-benefit ratio becomes unfavorable. What is the first action the project manager should take?

A.Update the Business Case without informing the board
B.Reduce project scope to cut costs
C.Stop the project immediately
D.Request a formal review of the Business Case by the project board
AnswerD

Correct: escalate for board decision.

Why this answer

In PRINCE2, the Business Case is the key document for justifying the project's continued viability. When the cost-benefit ratio becomes unfavorable, the project manager must escalate this issue to the project board, which holds the authority to approve changes to the Business Case or decide on project continuation. Option D is correct because the project manager's first action is to request a formal review by the project board, as per the 'continued business justification' principle and the 'manage by stages' theme.

Exam trap

PeopleCert often tests the misconception that the project manager can independently adjust the Business Case or stop the project, when in fact the project board holds the authority for such decisions under PRINCE2's management by exception and continued business justification principles.

How to eliminate wrong answers

Option A is wrong because the project manager cannot unilaterally update the Business Case; this is a project board responsibility, and doing so without informing the board violates the 'management by exception' principle. Option B is wrong because reducing project scope without a formal change control process and board approval is unauthorized and could undermine the project's objectives and business justification. Option C is wrong because stopping the project immediately is a decision reserved for the project board; the project manager must first escalate the issue and await a formal decision, as per the 'manage by stages' theme.

889
MCQmedium

What document is a key output of the Initiating a Project process?

A.Project Brief
B.Project Plan
C.Business Case
D.Project Initiation Documentation
AnswerD

The PID is the main output of Initiating a Project, containing the Business Case, Project Plan, and other baselines.

Why this answer

The Project Initiation Documentation (PID) is the definitive output of the Initiating a Project process. It consolidates the Project Brief, Business Case, and Project Plan into a single, controlled document that defines the project's scope, objectives, and governance. PRINCE2 mandates that the PID is created and approved during this process to provide a firm foundation for the project.

Exam trap

PRINCE2 often tests the distinction between inputs and outputs of processes; the trap here is confusing the Project Brief (an input) or the Business Case (a component) with the PID, which is the comprehensive output that bundles them together.

How to eliminate wrong answers

Option A is wrong because the Project Brief is created during the Starting Up a Project process, not the Initiating a Project process; it serves as input to the latter. Option B is wrong because the Project Plan is a component within the PID, but the PID itself is the key output, not the plan alone. Option C is wrong because the Business Case is also a component of the PID; while it may be refined during Initiating a Project, the PID is the overarching deliverable.

890
MCQmedium

Which document is the key output of the Initiating a Project process?

A.Business Case
B.Project Initiation Documentation
C.Project Plan
D.Stage Plan
AnswerB

The PID is the comprehensive set of documents that form the project baseline.

Why this answer

The Project Initiation Documentation (PID) is the key output of the Initiating a Project process, containing the business case, project plan, and other baselines.

891
MCQmedium

The Project Board has authorized the project and the first stage. Which process is used by the Project Manager to manage the work of the first stage?

A.Initiating a Project
B.Controlling a Stage
C.Managing a Stage Boundary
D.Managing Product Delivery
AnswerB

CS is used by the PM to manage the stage.

Why this answer

After the Project Board authorizes the project and the first stage, the Project Manager uses the Controlling a Stage process to assign work, monitor progress, handle issues, and report to the Board throughout the stage. This process governs the day-to-day management of the stage and ensures it stays within tolerance.

Exam trap

The trap here is confusing the Project Manager's role in Controlling a Stage with the Team Manager's role in Managing Product Delivery, or assuming that Initiating a Project continues into the first stage.

How to eliminate wrong answers

Option A is wrong because Initiating a Project is used to create the Project Initiation Documentation and plan the project, not to manage the work of an authorized stage. Option C is wrong because Managing a Stage Boundary is used to prepare the next stage plan and update the business case at the end of a stage, not to manage ongoing work. Option D is wrong because Managing Product Delivery is the process used by the Team Manager to accept and deliver work packages, not by the Project Manager to manage the stage.

892
MCQmedium

What is the difference between a Request for Change and an Off-specification?

A.A Request for Change is a proposal to modify a baseline; an Off-specification is a failure to meet the baseline
B.A Request for Change is raised by the Project Manager; an Off-specification is raised by the team
C.A Request for Change is always urgent; an Off-specification is not
D.There is no difference; they are the same thing
AnswerA

This is the correct distinction.

Why this answer

In PRINCE2, a Request for Change (RFC) is a formal proposal to modify a product baseline (e.g., a specification or plan), while an Off-specification is a notification that a product has failed to meet its agreed baseline (e.g., a defect or missing requirement). Option A correctly captures this fundamental distinction: RFCs propose changes to baselines, whereas Off-specifications report deviations from baselines.

Exam trap

In PRINCE2, candidates often confuse the roles responsible for raising issues (Option B) or assume urgency (Option C), but PRINCE2 explicitly defines RFCs and Off-specifications by their relationship to baselines, not by who raises them or their urgency.

How to eliminate wrong answers

Option B is wrong because both RFCs and Off-specifications can be raised by any project role (e.g., Project Manager, team members, or stakeholders), not exclusively by the Project Manager or team. Option C is wrong because neither RFCs nor Off-specifications are inherently urgent; urgency is determined by impact analysis, not by the type of issue. Option D is wrong because RFCs and Off-specifications are distinct concepts with different purposes and triggers in PRINCE2's change control process.

893
MCQmedium

During which process does the Project Manager produce a Highlight Report for the Project Board?

A.Controlling a Stage
B.Managing a Stage Boundary
C.Starting Up a Project
D.Managing Product Delivery
AnswerA

Highlight Reports are produced by the PM in CS to inform the Project Board.

Why this answer

The Controlling a Stage process includes producing Highlight Reports at intervals defined by the Project Board. Managing Product Delivery produces Checkpoint Reports from the Team Manager to the PM. Managing a Stage Boundary produces End Stage Reports.

Starting Up a Project does not produce Highlight Reports.

894
Multi-Selecthard

Which TWO of the following are true about the Managing Product Delivery process?

Select 2 answers
A.It produces Highlight Reports for the Project Board
B.It is performed by the Project Manager
C.It includes the acceptance of Work Packages
D.It produces End Stage Reports
E.It produces Checkpoint Reports for the Project Manager
AnswersC, E

Correct. Team Managers accept Work Packages in this process.

Why this answer

Managing Product Delivery is the process where Team Managers accept Work Packages, execute them, and deliver products. Checkpoint Reports are produced by Team Managers for the Project Manager. Highlight Reports are produced by the PM, and End Stage Reports are produced in Managing a Stage Boundary.

895
Multi-Selectmedium

Which TWO of the following are outputs of the Initiating a Project process?

Select 2 answers
A.End Project Report
B.Lessons Report
C.Project Brief
D.Project Initiation Documentation
E.Stage Plan for the next stage
AnswersD, E

Key output of IP.

Why this answer

The Initiating a Project process produces the Project Initiation Documentation (PID), which is the definitive document that defines the project's scope, objectives, and approach. It also produces the Stage Plan for the next stage, which details the work, resources, and controls for the first management stage. These are mandatory outputs that enable the Project Board to authorize the project to proceed.

Exam trap

PeopleCert often tests the confusion between the Project Brief (an input from Starting Up a Project) and the Project Initiation Documentation (an output of Initiating a Project), leading candidates to incorrectly select the Project Brief as an output.

896
MCQhard

In the Managing Product Delivery process, who produces the Checkpoint Report?

A.The Project Manager
B.The Team Manager
C.The Project Board
D.The Senior User
AnswerB

The Team Manager produces Checkpoint Reports during MP.

Why this answer

The Team Manager (or Team Member acting on behalf of the Team Manager) produces Checkpoint Reports to inform the Project Manager of progress against the Work Package. The Project Manager produces Highlight Reports. The Project Board receives Highlight Reports.

The Senior User is a Project Board role.

897
MCQmedium

In the Managing Product Delivery process, who is responsible for producing Checkpoint Reports?

A.The Project Support
B.The Project Board
C.The Team Manager
D.The Project Manager
AnswerC

The Team Manager produces Checkpoint Reports to report progress on Work Packages.

Why this answer

In PRINCE2, the Checkpoint Report is produced by the Team Manager to inform the Project Manager of progress on Work Packages. The Team Manager (or the team) prepares these reports at intervals defined in the Work Package. The Project Manager receives them, not the Project Board.

Therefore, option C is correct.

898
MCQmedium

What is the difference between a Request for Change and an Off-specification?

A.A Request for Change is submitted by the Project Board, whereas an Off-specification is submitted by the Project Manager
B.A Request for Change is a type of risk, whereas an Off-specification is a type of issue
C.A Request for Change requires a change budget, whereas an Off-specification does not
D.A Request for Change proposes a modification to an approved baseline, whereas an Off-specification occurs when a product does not meet its specification
AnswerD

This correctly distinguishes the two issue types.

Why this answer

In PRINCE2, a Request for Change (RFC) is a formal proposal to modify an approved baseline (e.g., a product description or project plan), while an Off-specification (Off-spec) is an issue that arises when a product does not meet its agreed specification or quality criteria. The RFC seeks to change the baseline, whereas the Off-spec identifies a deviation from the existing baseline. This distinction is fundamental to PRINCE2's issue management and change control processes.

Exam trap

The trap here is confusing the source or budget implications of issues; candidates often assume RFCs always need a change budget or that Off-specs are only raised by the Project Manager, but PRINCE2 defines them strictly by their relationship to baselines and specifications.

How to eliminate wrong answers

Option A is wrong because both a Request for Change and an Off-specification can be submitted by any stakeholder, not exclusively by the Project Board or Project Manager; the Project Manager typically logs all issues, but the source can be anyone. Option B is wrong because a Request for Change is a type of issue (not a risk), and an Off-specification is also a type of issue; PRINCE2 classifies issues into three types: Request for Change, Off-specification, and Problem/Concern. Option C is wrong because both a Request for Change and an Off-specification may require a change budget if the resolution involves additional cost; the need for a change budget depends on the impact and the stage, not on the issue type itself.

899
MCQmedium

Who is responsible for providing assurance that the project is being conducted properly?

A.Project Support
B.Project Manager
C.Project Board
D.Team Manager
AnswerC

The Project Board is responsible for project assurance, ensuring the project is conducted properly.

Why this answer

In PRINCE2, the Project Board is responsible for providing assurance that the project is being conducted properly. This includes ensuring that the project remains viable, that risks are managed, and that the business case is still valid. The Project Board delegates day-to-day management to the Project Manager but retains overall accountability and oversight through assurance activities.

Exam trap

PRINCE2 often tests the distinction between the Project Manager's role (managing the project) and the Project Board's role (providing assurance and making key decisions), leading candidates to mistakenly select the Project Manager as the assurance provider.

How to eliminate wrong answers

Option A is wrong because Project Support provides administrative and clerical services, such as maintaining files and producing reports, but does not have the authority to provide independent assurance. Option B is wrong because the Project Manager is responsible for the day-to-day management of the project and is the recipient of assurance, not the provider; they cannot assure their own work. Option D is wrong because the Team Manager is responsible for delivering the work within a work package and reports to the Project Manager, not for providing assurance on the project as a whole.

900
MCQeasy

In PRINCE2, who is responsible for maintaining the Business Case throughout the project?

A.The Project Manager
B.The Project Support
C.The Executive
D.The Senior User
AnswerA

The Project Manager maintains the Business Case on behalf of the Executive.

Why this answer

The Project Manager maintains the Business Case, but the Executive (SRO) owns it and is ultimately responsible for ensuring business justification.

Page 11

Page 12 of 22

Page 13