Which THREE of the following are activities performed during the Directing a Project process?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Authorise a Stage Plan or Exception Plan
Directing a Project includes authorising initiation, authorising the project, authorising stage/exception plans, giving ad-hoc direction, and authorising closure. Authorising a Work Package is done by the Project Manager in Controlling a Stage. Highlight Reports are produced by the Project Manager in Controlling a Stage.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
Same concept, more angles
3 more ways this is tested on PRINCE2F
These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.
Variation 1. Which THREE of the following are activities performed during the Directing a Project process?
hard- ✓ A.Authorize closure of the project
- B.Appoint the Project Manager
- ✓ C.Authorize initiation
- ✓ D.Give ad-hoc direction to the Project Manager
- E.Produce Highlight Reports
Why A: Directing a Project includes authorizing initiation, authorizing stages, giving ad-hoc direction, and authorizing closure. Producing Highlight Reports is for the PM during Controlling a Stage. Appointing the Project Manager is during Starting Up a Project.
Variation 2. Which TWO of the following are activities performed in the Directing a Project process?
medium- A.Produce Highlight Reports
- ✓ B.Authorize initiation
- ✓ C.Authorize the project
- D.Escalate issues to the Project Board
- E.Manage product delivery
Why B: The Directing a Project process includes authorizing initiation and authorizing the project. Producing Highlight Reports is an activity in the Controlling a Stage process, managing product delivery is part of Managing Product Delivery, and escalating issues is typically a project manager role, not a Directing a Project activity. Therefore, the correct answers are B and C.
Variation 3. Which TWO of the following are activities performed in the Directing a Project process?
medium- A.Produce the Project Initiation Documentation
- B.Take corrective action within stage tolerances
- C.Manage day-to-day work of a stage
- ✓ D.Authorize a stage or exception plan
- ✓ E.Authorize initiation
Why D: The Directing a Project process includes the activity of authorizing a stage or exception plan, which is a key decision-making step performed by the project board. Option E is correct because authorizing initiation is also an activity within Directing a Project, where the project board gives formal approval to proceed with the initiation stage. These activities ensure the project board maintains control over major decisions and boundaries.
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.