Courseiva
PRINCE2 Practices →hardMultiple Choice

PRINCE2F PRINCE2 Practices Practice Question

During the Managing a Stage Boundary process, the Project Manager produces an Exception Plan. What triggers the creation of an Exception Plan?

⚠ Common exam trap

The trap is confusing the trigger for an Exception Plan with routine stage-end planning; candidates pick 'end of a stage' when the real trigger is Project Board approval of an Exception Report.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

The Project Board approves an Exception Report

An Exception Plan is produced during the Managing a Stage Boundary process when the Project Board approves an Exception Report. The Exception Report documents that a stage or the project is forecast to exceed its tolerances, and once the Board approves it, the Project Manager must prepare an Exception Plan to show how the project will recover and realign with the Project Plan.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    The project is closed prematurely

    Why it's wrong here

    Premature closure triggers the Closing a Project process.

  • ✓

    The Project Board approves an Exception Report

    Why this is correct

    An Exception Plan is triggered when the Project Board approves an Exception Report, since the board has agreed corrective action is needed. The Project Manager then plans how to recover from the tolerance breach, replacing the remainder of the current Stage Plan.

  • ✗

    The end of a stage is reached

    Why it's wrong here

    A Stage Plan is produced at stage boundaries, not an Exception Plan.

  • ✗

    The Project Manager identifies a new risk

    Why it's wrong here

    New risks are managed through the risk procedure, not automatically leading to an Exception Plan.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,189 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PeopleCert exam blueprint

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.