PRINCE2F PRINCE2 Practices Practice Question
In the risk management procedure, which step includes evaluating risk probability and impact?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Assess
The 'Assess' step of the risk management procedure includes evaluating risk probability and impact to prioritize risks.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Assess
Why this is correct
The Assess step includes estimation and evaluation of probability and impact.
- ✗
Implement
Why it's wrong here
The Implement step is about executing planned responses.
- ✗
Identify
Why it's wrong here
The Identify step is about identifying risks, not evaluating them.
- ✗
Plan
Why it's wrong here
The Plan step involves preparing specific management responses.
Go deeper
Related to this question
About these practice questions
One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.