PRINCE2 ProcesseshardMultiple ChoiceObjective-mapped

PRINCE2F PRINCE2 Processes Practice Question

In the Closing a Project process, which document confirms that the project's products have been accepted?

⚠ Common exam trap

Candidates often confuse the Lessons Report with the End Project Report, but the Lessons Report focuses on learning for future projects, not on confirming product acceptance.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

End Project Report

The End Project Report is the document that formally confirms the project's products have been accepted. It is produced during the Closing a Project process and includes a summary of the project's achievements, including product acceptance records, to provide a formal basis for project closure.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Lessons Report

    Why it's wrong here

    The Lessons Report documents insights for future projects, not acceptance. The Closing a Project process requires the End Project Report to confirm product acceptance, as it formally records approval from the project board against the agreed acceptance criteria. This option is tempting because the Lessons Report is also produced during project closure, but its purpose is to capture what went well and what could be improved, not to serve as an acceptance record. It would be correct if the question asked which document captures learning for future benefit.

  • End Project Report

    Why this is correct

    The End Project Report summarizes project performance and includes acceptance records.

  • Project Initiation Documentation

    Why it's wrong here

    PID is produced in IP, not at closure.

  • Benefits Management Approach

    Why it's wrong here

    This document is updated during the project but does not confirm acceptance.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.