PRINCE2F PRINCE2 Processes Practice Question
The Project Board is considering whether to authorize the next stage. Which document provides the information needed for this decision?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
End Stage Report
The End Stage Report provides a summary of the current stage's performance and the next stage plan for the Board to decide on continuation.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
End Stage Report
Why this is correct
The End Stage Report is produced at the end of each stage and includes the next stage plan for approval.
- ✗
Highlight Report
Why it's wrong here
Highlight Reports provide periodic updates within a stage, not at stage boundaries.
- ✗
Checkpoint Report
Why it's wrong here
Checkpoint Reports are from Team Managers to Project Managers within a stage.
- ✗
Exception Report
Why it's wrong here
Exception Reports are used when tolerances are forecast to be exceeded, not for routine stage boundary decisions.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.