PRINCE2 Processes →mediumMultiple Choice

PRINCE2F PRINCE2 Processes Practice Question

The Project Board is considering whether to authorize the next stage. Which document provides the information needed for this decision?

⚠ Common exam trap

PRINCE2F often tests the distinction between reports used at different levels and moments—Highlight and Checkpoint reports are progress reports, while only the End Stage Report feeds the stage authorization decision.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

End Stage Report

The End Stage Report is produced at the end of each stage and summarizes performance against the stage plan, business case, and risks, giving the Project Board the information it needs to decide whether to authorize the next stage. It is the formal input to the 'Authorize a Stage' activity.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    End Stage Report

    Why this is correct

    The End Stage Report summarises performance, products completed and issues against the Stage Plan, giving the Project Board the evidence needed to decide whether to authorise the next stage. It satisfies the stem's requirement for the decision-supporting document at a stage boundary.

  • ✗

    Highlight Report

    Why it's wrong here

    A Highlight Report summarises progress at a frequency the Project Manager chooses, covering status and issues, but it is not the formal product that consolidates actual versus planned performance for a stage-boundary authorisation decision. It would be correct for periodic progress communication between stage boundaries.

  • ✗

    Checkpoint Report

    Why it's wrong here

    A Checkpoint Report records team-level progress at the frequency agreed for work packages, so it addresses delivery within a stage rather than the consolidated performance the Board reviews at a stage boundary. It would be correct for the Team Manager to report progress to the Project Manager during a stage.

  • ✗

    Exception Report

    Why it's wrong here

    An Exception Report is produced only when a stage or project deviates beyond tolerance, so it cannot supply the routine end-of-stage performance data the Board needs to authorise the next stage. It would be correct when the Board must decide how to respond to a forecast breach of tolerance.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,189 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PeopleCert exam blueprint

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.