Courseiva

PRINCE2F People: organizations, teams, and leadership Practice Question

Who chairs the Project Board in PRINCE2?

⚠ Common exam trap

Many exam-takers confuse the Project Manager as the chair because they lead project meetings, but PRINCE2 explicitly assigns the Project Board chair to the Executive, not the Project Manager.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Senior Responsible Owner (Executive)

In PRINCE2, the Project Board is chaired by the Executive (also known as the Senior Responsible Owner in many organizations). The Executive is ultimately accountable for the project's success, provides business justification, and ensures the project remains viable. The chairperson role is explicitly assigned to the Executive in the PRINCE2 management structure, not to the Senior Supplier, Senior User, or Project Manager.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    Senior Responsible Owner (Executive)

    Why this is correct

    The Executive, often fulfilled by the Senior Responsible Owner, chairs the Project Board and owns the business case, holding ultimate accountability for the project's success. Other board roles, such as Senior User and Senior Supplier, represent user and supplier interests rather than chairing.

  • ✗

    Senior Supplier

    Why it's wrong here

    The Senior Supplier represents those delivering the project's products and holds one of the three Project Board roles, but chairing is not part of that remit. It is tempting because the role does sit on the board and contributes supplier-side assurance, yet the chair must come from the business side to own the business case.

  • ✗

    Senior User

    Why it's wrong here

    The Senior User specifies needs and represents those using the products, but chairs nothing on the board. It is tempting because this role provides user assurance and is a full board member, yet chairing belongs to the Executive, who owns the business case and remains accountable for the project.

  • ✗

    Project Manager

    Why it's wrong here

    The Project Manager runs the project day to day and reports to the board, but does not sit on it as a decision-making member, so cannot chair it. It is tempting because the manager coordinates board logistics and produces reports, yet PRINCE2 separates project management from the board's business-level direction.

About these practice questions

One of 1,189 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.